Construction and engineering law Books

170 products


  • Out of stock

    £12.93

  • 15 in stock

    £36.71

  • Amazon Digital Services LLC - Kdp The Made Easy US Master Depreciation Guide 2026 2027

    15 in stock

    15 in stock

    £20.44

  • Amazon Digital Services LLC - Kdp AllinOne Construction Estimating Handbook 3in1

    Out of stock

    Out of stock

    £17.50

  • Independently Published Delaware Contractor License Exam Prep

    15 in stock

    15 in stock

    £17.67

  • Adjudication in Construction Law

    Taylor & Francis Ltd Adjudication in Construction Law

    5 in stock

    Book SynopsisThis book collects all the relevant material regarding the process of adjudication in construction. It provides clarity for those involved in the adjudication process or related proceedings with detailed and reliable analysis of them supported by statutory provisions and judicial observations. Adjudication in Construction Law discusses the role of true value' adjudications following smash and grab decisions on the basis of the absence of a pay less notice, the restraint of adjudication by injunction, hybrid contracts dealing with both construction operations and other operations and timing and content of payment notices and pay less notices. Additionally, this book includes a summary of the different procedures adopted in other jurisdictions, as well as an explanation of the payment procedures under the statutory framework. It also goes on to append all the relevant statutory material, contractual adjudication procedures and forms. A new feature of this edition is a deTrade Review'This is an extremely well researched book with extensive and very useful reference to case law and statute.'Lindy Patterson KC, 39 Essex Chambers, UKTable of Contents1. Statutory regulation of construction contracts 2. Beginning Adjudication 3. Appointment and Referral 4. Procedure Leading to the Decision 5. The Decision 6. Enforcement and Court Proceedings 7. Other Jurisdictions 8. Review, Proposals for Reform and Reform 9. Contractual Adjudication 10. Payment under the UK Statutory Framework 11. Rules and Fallacies

    5 in stock

    £380.00

  • The Practice of International Commercial

    Taylor & Francis Ltd The Practice of International Commercial

    1 in stock

    Book SynopsisFocusing on practical principles or guidelines for arbitrators, this book covers everything a prospective international commercial arbitrator should know about conducting an arbitration in Hong Kong. Specifically geared to those interested in or starting work as an international commercial arbitrator in Hong Kong, the book takes readers step-by-step through the problems that are likely to arise in the conduct of a commercial arbitration and in the development of their careers as international commercial arbitrators.Table of Contents1. Introduction 2. Theory 3. Infrastructure 4. Rules 5. Appointment 6. Start 7. Interlocutory 8. Evidence 9. Trial 10. Finish 11. ADR Support 12. Judicial Support 13. Complex Arbitrations 14. Specialized Arbitrations 15. Challenges

    1 in stock

    £266.00

  • International Contractual and Statutory

    Taylor & Francis Ltd International Contractual and Statutory

    5 in stock

    Book SynopsisA compilation of commentaries on the various jurisdictions where there either is, or is planned, a statutory adjudication system , this is a review of such systems worldwide in the commercial and construction fields. It features analysis by specialist advisory editors on the adjudication system in place in each separate jurisdiction, together with a copy of the relevant local legislation, and permits a comparative approach between each. This book addresses statutory adjudication in a way that is practically useful and academically rigorous. As such, it remains an essential reference for any lawyer, project manager,contractor or academic involved with the commercial and construction fields. Table of ContentsForeword by Sir Robert Akenhead Introduction and Organisation England and Wales Australia: the East Coast Model (with New South Wales as the Principal Legislation) Australia: the East Coast Model: Victoria, Tasmania, The Australian Capital Territory and South Australia Australia: the East Coast Model (Queensland) Australia: the West Coast Model Chartered Institute of Arbitrators' Dispute Board Rules Federation International des Ingenieurs-Conseils (FIDIC) Dispute Board Rules Germany Hong Kong International Chamber of Commerce Dispute Board Rules Ireland Malaysia Mauritius New Zealand Northern Ireland Scotland Singapore South Africa 20. United States of America

    5 in stock

    £332.50

  • FIDIC Contracts: Law and Practice

    Taylor & Francis Ltd FIDIC Contracts: Law and Practice

    5 in stock

    Book SynopsisFIDIC Contracts: Law and Practice is sure to become the leading industry standard guide to using the FIDIC forms, and is the only book to date which deals with the whole suites of contracts, including the new gold book for Design, Build and Operate projects. The White & Case work is outstanding in its detailed consideration and treatment of the legal aspects of the interpretation and application of the Conditions, touching on many points that most people would not have encountered.Humphrey LLoyd, International Construction Law Review [2010] ICLR 386Table of ContentsChapter 1. FIDIC Chapter 2. The FIDIC Contract Chapter 3. Product Chapter 4. Price Chapter 5. Time Chapter 6. Contract Administration and Claims Chapter 7. Risk, Insurance and Securities Chapter 8. Remedies Chapter 9. Dispute Resolution

    5 in stock

    £475.00

  • Kohlhammer Koordinierungspflichten Am Bau: Leistung -

    2 in stock

    Book Synopsis

    2 in stock

    £55.20

  • Kohlhammer Der Artenschutz Im Bebauungsplanverfahren

    1 in stock

    Book Synopsis

    1 in stock

    £43.20

  • Kohlhammer W. Landesbauordnung Fur BadenWurttemberg

    2 in stock

    Book Synopsis

    2 in stock

    £47.20

  • Kohlhammer Ausfuhrungsverordnung Zur Landesbauordnung

    1 in stock

    Book Synopsis

    1 in stock

    £35.70

  • 2 in stock

    £37.40

  • Kohlhammer W. Die Neue Landesbauordnung Fur BadenWurttemberg

    2 in stock

    Book Synopsis

    2 in stock

    £22.50

  • 1 in stock

    £31.50

  • Planung der Planung: Kurzanleitung Heft 2

    Springer Fachmedien Wiesbaden Planung der Planung: Kurzanleitung Heft 2

    1 in stock

    Book SynopsisDas Buch behandelt die fünf Handlungsbereiche der Steuerung von Immobilienprojekten: Management der Informationen, der Kosten und der Finanzierung, der Abläufe, Termine und Logistik, der Verträge und Versicherungen sowie die alle Elemente übergreifende Organisation, Koordination und Dokumentation.Die Komplexität bei der Planung und Errichtung von Bauwerken hat zugenommen. Die Handhabung ist eine Managementaufgabe. In allen Phasen der Planung und Realisierung von Bauvorhaben müssen viele, teilweise parallel laufende Abläufe geplant, kontrolliert und – wenn notwendig – korrigiert werden. Neben rein fachlichen Kenntnissen in Entwurf und Konstruktion werden deshalb Kenntnisse der Organisationsmethodik und deren praktischer Umsetzung sowie des Ablaufmanagements gefordert.Table of ContentsFachliche Abdeckung der Zielerreichung organisieren.- Vollmachten und Aufgabenverteilung organisieren.- Zeichnungsmanagement.- Objektstruktur als durchgehendes Ordnungsprinzip.- Zeichnungsinhalte.- Ablaufplanung durch Zusammenarbeit organisieren.- Abläufe organisieren (Ausschreibungsmanagement).- Zeichnungsverteilung organisieren (Zeichnungsmanagement).- Bemusterungen organisieren.

    1 in stock

    £37.99

  • Residential Building Codes Illustrated

    John Wiley & Sons Inc Residential Building Codes Illustrated

    1 in stock

    Book SynopsisAn easy-to-use illustrated guide to building codes for residential structures As the construction industry moves to a single set of international building codes, architects and construction professionals need an interpretive guide to understand how the building code affects the early design of specific projects. This newest addition to Wiley's series of focused guides familiarizes code users with the 2009 International Residential Code (IRC) as it applies to residential buildings. The book provides architects, engineers, and other related building professionals with an understanding of how the International Residential Code was developed, and how it is likely to be interpreted when applied to the design and construction of residential buildings. User-friendly visual format that makes finding the information you need quick and easy The book's organization follows the 2009 International Residential Code itself Nearly 900 illustrations, by architectural illustratoTable of ContentsPreface vi 1 Building Codes 1 2 Navigating the Code, Adminisrative Procedures, Definitions 9 3 Building Planning 25 4 Foundations 107 5 Floors 139 6 Wall Construction 171 7 Wall Covering 255 8 Roof-Ceiling Construction 281 9 Roof Assemblies 305 10 Chimneys and Fireplaces 325 Bibliography 335 Index 336

    1 in stock

    £38.95

  • A Contractors Guide to the Fidic Conditions of

    John Wiley & Sons Inc A Contractors Guide to the Fidic Conditions of

    Book SynopsisThis guide will help the contractor's staff overcome some of the difficulties encountered on a typical international contract using FIDIC forms. The majority of FIDIC-based contracts use the Red Book (Conditions of Contract for Construction), so this book concentrates on the use of those particular forms. Supplementary comments are included in Appendix C for the Yellow Book (Plant & Design-Build) recommended for use where the contractor has a design responsibility. The Contractor is represented on site by the Contractor's Representative who carries the overall responsibility for all the Contractor's on-site activities. In order to provide guidance to the Contractor's Representative and his staff, this book is divided into five sections: A summarized general review of the Red Book from the Contractor's perspective. A review of the activities and duties of the Contractor's Representative in the same clause sequencing as they appear in thTable of ContentsPreface v Acknowledgements and dedication ix Chapter 1 Review of the FIDIC Conditions of Contract for Construction (CONS) – ‘The Red Book’ 1 Chapter 2 Activities and duties of the FIDIC Contractor’s Representative discussed in the same order as they appear in the FIDIC Conditions of Contract 105 Chapter 3 Activities and duties of the FIDIC Contractor’s Representative summarised and arranged in time sequence 143 Appendices 157 Appendix A Contractor’s claims under a CONS contract 159 Appendix B Employer’s claims under a CONS contract 161 Appendix C Conditions of Contract for Plant and Design-build (P & DB) – ‘The Yellow Book’ 162 Appendix D Conditions of Contract for EPC/Turnkey projects (EPCT) – ‘The Silver Book’ 165 Appendix E Other FIDIC publications 166 Appendix F Model form for submissions to the Engineer for approval and/or consent 168 Appendix G Model form of daywork/daily record sheets 169 Appendix H Evaluation of cost 171 Appendix I Contractor’s overhead costs 173 Appendix J Model letters for use by the Contractor 178 Introduction to indexes 250 Index of sub-clauses (FIDIC system) 251 Index of sub-clauses (sorted according to FIDIC clause numbering system) 258

    £64.55

  • Joint Ventures in Construction

    Emerald Publishing Limited Joint Ventures in Construction

    Book SynopsisA collection of carefully selected papers from the International Conference on Multi-National Joint Ventures for Construction Works held in varying locations within the Asia Pacific region, this book endeavours to report the theory and practice of contract and contract formation, governance, performance and risk in joint ventures.Table of ContentsIntroduction Part 1: Contract -What are the terms and conditions those parties in a joint venture for construction works agree on? -General contractors' perception towards collaboration with specialty contractors -Partner selection for international joint ventures based on fuzzy approach -Strategic implementation of international joint venture in Taiwan: a case study on Taiwan High Speed Rail Corp Part 2: Governance -Construction joint ventures in the project coalition: a conceptual framework -Administrative structures of construction joint ventures in Thailand -Corruption and contract governance construction projects in developing countries -Application of environmentally-conscious contract law to a PFI project -Payment deductions in PFI projects -The application of BOT contract by Majlis Agama Wilayah Persekutan Malaysia (MAIWP) in developing wagf land -Why do contractors sub-contract work to sub-contractors? -International labour movement and welfare effects: Malaysia as a case study -Using alternative dispute resolution for managing disputes in joint venture projects in Malaysia Part 3: Performance and Risk -Technological matching and economic value of performance specification in public procurement -Investigation on the influence factors of international joint venture performance on land development in Taiwan -Developing reflexive capability for successful joint ventures between Australasian and Malaysian property and construction professionals -Relational finance in project finance -Application of target cost contracting in the construction industry of Hong Kong -Risk sharing in joint ventures -The moral hazard issues in PPP projects

    £88.35

  • Fidic Users Guide

    Emerald Publishing Limited Fidic Users Guide

    Book SynopsisFIDIC Users'' Guide: A practical guide to the Red, Yellow, MDB Harmonised and Subcontract Books focuses on the practical administration of the Federation Internationale des Ingenieurs-Conseils (FIDIC) Conditions of Contract for Construction and the Conditions of Contract for Plant & Design-Build, a revised family of Conditions of Contract published in 1999 to address the increasing size and complexity of construction projects. Brian Barr and Leo Grutters have comprehensively updated Brian Totterdill's previous edition, taking into account newly published forms of contract, case studies, and FIDIC's expansion into a more international arena. The book recognises the growing tendency for projects to be administered by local employers, consultants and contractors as well as by experienced international organisations. Thus, the new edition of the FIDIC Users'' Guide aims improve working relationships between all contract parties. FIDIC Users'' Guide: ATrade ReviewThis work of reference brings professional insights into and practical solutions for the more contentious and controversial issues when dealing with FIDIC contracts. -- Dr. Cyril Chern, Barrister, Dispute Board FederationTable of ContentsPart 1. The Traditional and the 1999 FIDIC Conditions of Contract Part 2. The FIDIC Conditions of Contract for Construction and for Plant and Design-Build Part 3. Appendices Part 4. MDB Harmonised Edition of the FIDIC Conditions of Contract for Construction Part 5. Sub-Clause comparison

    £85.02

  • CDM Regulations 2015 Explained

    Emerald Publishing Limited CDM Regulations 2015 Explained

    Book SynopsisCDM Regulations 2015 Explained provides a straightforward, independent and authoritative assessment and analysis of the 2015 CDM Regulations.The individual roles of each party involved in a construction project are detailed in light of the latest updates to the Regulations.The book navigates through the radical changes from the previous CDM Regulations and includes helpful checklists to assist each of the duty holders to comply with their obligations and avoid the penalties of non-compliance. CDM Regulations 2015 Explained will be an invaluable source of information for those responsible for the procurement or management of construction projects or anyone wishing to master the latest developments in construction law and health and safety law.CDM Regulations 2015 Explained: offers clear, straightforward guidance to the new Regulations in an established format sets out a checklist for each duty holder to ensure quick and easy assimilaTable of Contents1. Introduction 2. Framework of health and safety law 3. An overview of the Regulations 4. General principles 5. Considerations for the welfare of workers 6. Consideration for hazardous operations 7. Competence 8. The client 9. The designer 10. The CDM co-ordinator 11. The principal contractor 12. The contractor 13. The construction phase plan 14. The health and safety file 15. Contract documentation 16. Criminal and civil liability and enforcement 17 Transitional provisions

    £81.70

  • FIDIC Quick Reference Guide

    Emerald Publishing Limited FIDIC Quick Reference Guide

    7 in stock

    Book SynopsisThis book provides commentary on the FIDIC Pink Book: The MDB Harmonised Edition of the Red Book for use with contracts which have been financed by one of the participating multilateral development banks.

    7 in stock

    £42.00

  • Procurement and Contract Strategies for

    Emerald Publishing Limited Procurement and Contract Strategies for

    Book SynopsisProcurement and Contract Strategies for Construction is essential reading for a wide range of construction professionals, particularly commercial, contractual and procurement staff. It will also be of interest to students on university and professional courses that cover procurement and contract strategy.

    £47.00

  • Specification for Tunnelling

    Emerald Publishing Limited Specification for Tunnelling

    Book SynopsisThe ebook edition of this title is Open Access and freely available to read online. Specification for Tunnelling, is a standard industry document for tunnelling contracts and forms the basis of tunnelling specifications for projects throughout the world..Table of ContentsChapter 1. General requirements Chapter 2. Materials Chapter 3. Methods Chapter 4. Ground stabilisation processes Chapter 5. Working environment

    £50.00

  • Applying the ADA

    John Wiley & Sons Inc Applying the ADA

    Book SynopsisA guide to real-world applications of The 2010 Americans with Disabilities Act Standards for Accessible Design Applying the ADA helps architects and developers understand better how the rules for eliminating barriers in the built environment apply to everyday life and how to best implement them in the design and construction of a broad variety of buildings and facilities. By showing how The 2010 Americans with Disabilities Act Standards for Accessible Design have been applied in various contexts and building types, this extensively illustrated guide helps readers quickly understand the requirements of the standards and how to apply them to both new construction and renovation. Written by an architect who consults regularly on accessibility issues for design professionals, building owners, and facility managers, this user-friendly guide features 100 photos and 150 drawings that take the guesswork out of applying the standards to real-world projects. BuildiTable of ContentsAcknowledgments ix Introduction xi History xi Summary xii Chapter 1 General Guidelines 1 by Marcela Abadi Rhoads, AIA RAS General Guidelines 1 Building Blocks 2 Accessible Routes 9 General Site 10 Changes in Level 16 Accessible Entrances 16 Interior Accessible Route 17 Plumbing Fixtures 18 Communication Features 23 Summary 25 Chapter 2 Retail and Mixed-Use Facilities 27 by Marcela Abadi Rhoads, AIA RAS Introduction 27 Shopping Malls 28 Site Arrival Points 28 Minimum Number of Parking Spaces Closest to the Entrances 29 Accessible Route to Entrances 32 Accessible Entrances 38 Interior Accessible Route to Spaces 38 Retail Spaces 41 Checkout and Sales Counters 43 Dressing and Fitting Rooms 44 Employee Areas 46 Common-Use Spaces 52 Food Court 56 Play Areas 60 Strip Shopping Center 61 Site Arrival Point 63 Parking 66 Accessible Route 66 Tenant Entrances 66 Lifestyle Center 72 Parking 72 Accessible Route 74 Residential Facilities/Offices on Upper Floors 75 Summary 81 Chapter 3 Primary Education 85 by Wally Tirado, ICC RAS Introduction 85 Administrative Areas 86 Employee Work Areas 87 Service Areas 88 Service Yards and Loading Docks 89 General Application for Children Areas 89 Reach Ranges and Operating Mechanisms 92 Dining and Work Surfaces 92 Toilet Rooms and Elements 97 Drinking Fountains 98 Toilet Compartments 99 Water Closets and Accessories 99 Mirrors 102 Lavatories and Sinks 102 Dressing and Fitting Rooms 104 Signage 104 Ramps and Stairs 106 Assembly Areas 108 Outdoor Play Areas 111 Transportation Facilities 112 Passenger Loading Zones 112 Bus Loading Zones 112 Summary 113 Chapter 4 Secondary and Postsecondary Educa tion 117 by Wally Tirado, ICC RAS Introduction 117 Accessible Sites and Parking 118 Bus Loading Zones 118 Location and Dispersion of Parking 120 Leased/Assigned Parking 121 Playing Fields and Exterior Athletic Facilities 122 General Accessible Areas 127 Security Barriers 128 Temporary Structures and Facilities 129 Assembly Areas 129 Classrooms 130 Other Box Seating and Outdoor Seating 132 Performance Areas 135 Assistive Listening Systems (ALS) 141 Ticket Booths and Concession Stands 142 Libraries 142 Physical Education Facilities 143 Exercise Machines and Equipment 143 Dressing, Fitting, and Locker Rooms 146 Swimming Pools 148 Other Spectator Sports Areas 150 Dining Facilities 151 Administrative Areas 153 Housing at a Place of Education 158 Kitchens 159 Multi-Bedroom 159 Apartment or Townhouse Facilities 159 Summary 160 Chapter 5 Hospitality 163 by Jeromy Murphy, AIA RAS Introduction 163 New Construction 164 Existing Facilities 164 Public and Guest Areas 164 Guest Rooms with Mobility Features or Communications Features 173 Examples 177 Summary 179 Chapter 6 Healthcare and Senior Living Communities 183 by Greg Hunteman, AIA RAS Introduction 183 Different Types of Healthcare 183 Alterations to Existing Healthcare and Long-Term Care Facilities 184 General Guidelines 186 Accessible Routes 186 Individual Spaces 190 Patient and Resident Sleeping Rooms 191 Summary 198 Chapter 7 Amusement Parks and Play Areas 201 by Marcela Abadi Rhoads, AIA RAS Site Arrival 202 Play Areas 204 Ground Play Components 206 Elevated Play Components 209 Accessible Route 210 Entry Points and Seats 217 Play for Visually and Hearing Impaired 217 Amusement Rides 217 Fishing Piers 229 Summary 231 Chapter 8 Historic Preservation and Remodels 235 by Marcela Abadi Rhoads, AIA RAS Alterations 236 Entrances 242 Accessible Route 242 Path of Travel Elements 243 Tenant Finish-Outs 244 Alterations of Medical Care Facilities’ Patient Rooms 245 Alterations of Transient Lodging Sleeping Rooms 246 Alterations of Holding Cells 247 Alterations of Residential Dwelling Units 248 Alterations of Restaurants 249 Alterations of Dressing Rooms and Lockers Rooms 249 Disproportionality: The 20% Rule 249 Series of Smaller Alterations 250 Safe Harbor 251 Historic Facilities 252 Summary 254 Chapter 9 Residential Projects 259 by Jeromy Murphy, AIA RAS Introduction 259 Residential versus Transient Lodging 259 Applicability 260 Public and Common Use Spaces 263 Residential Dwelling Units 265 Summary 270 Chapter 10 Universal Design beyond the ADA 273 by Marcela Abadi Rhoads, AIA RAS PRINCIPLE ONE: Equitable Use 274 Principle One Design Guidelines 274 PRINCIPLE TWO: Flexibility in Use 277 Principle Two Design Guidelines 278 PRINCIPLE THREE: Simple and Intuitive Use 282 Principle Three Design Guidelines 282 PRINCIPLE FOUR: Perceptible Information 285 Principle Four Design Guidelines 286 PRINCIPLE FIVE: Tolerance for Error 289 Principle Five Design Guidelines 289 PRINCIPLE SIX: Low Physical Effort 294 Principle Six Design Guidelines 294 PRINCIPLE SEVEN: Size and Space for Approach and Use 298 Principle Seven Design Guidelines 298 Summary 302 Appendix A: Reference Ta bles 303 Appendix B: Resources 317 Index 319

    £50.36

  • An Employers and Engineers Guide to the Fidic

    John Wiley and Sons Ltd An Employers and Engineers Guide to the Fidic

    Book SynopsisWhen all parties involved in the construction process fully understand their roles and are able to anticipate potential points of conflict, disputes and delays will be minimised. The Employer's and Engineer's Guide to the FIDIC Conditions of Contract sets out the essential administrative requirements of a FIDIC based contract by reference to the FIDIC 1999 Red Book. The obligations and duties of the Employer and the Engineer are identified and discussed. Potential pitfalls are highlighted and likely consequences pointed out. The importance of the Employer's role in the preparation of tenders, which fully reflect his requirements and duties and obligations arising in the execution of the works, is emphasised. The key role of the Engineer in the effective administration of contracts after award is examined and commentary provided. Included in the guide are a number of appendices, including model letters which will be of value to less experienced stafTable of ContentsPreface vii Acknowledgements and Dedication xi Chapter 1 The Employer and the FIDIC Conditions of Contract for Construction (CONS) – ‘The Red Book’ 1 Chapter 2 The Engineer and the FIDIC Conditions of Contract for Construction (CONS) – ‘The Red Book’ 71 Appendices 145 Appendix A Conditions of Contract for Plant and Design-Build 1999 (P & DB) ‘The Yellow Book’ 147 Appendix B Conditions of Contract for EPC/Turnkey Projects (EPCT) ‘The Silver Book’ 150 Appendix C Other FIDIC Publications 151 Appendix D Employer’s Claims under a CONS Contract 153 Appendix E Contractor’s Claims under a CONS Contract 154 Appendix F Preparation of Interim Payment Certificates 156 Appendix G Model Form for Submissions to the Engineer for Approval and/or Consent 160 Appendix H Model Form of Engineer’s Order for Varied Works 161 Appendix I Model Form of Daywork/Daily Record Sheets 162 Appendix J Model Letters for Use by the Employer 164 Appendix K Model Letters for Use by the Engineer 175 Introduction to Indexes 205 Index of Sub-Clauses (FIDIC System) 206 Index of Sub-Clauses (sorted according to FIDIC Clause numbering system) 212

    £65.66

  • The JCT 2011 Building Subcontracts 2e

    Wiley-Blackwell The JCT 2011 Building Subcontracts 2e

    Book SynopsisThe majority of construction work is carried out by subcontractors. As building projects become more complex, subcontractors need to understand the implications of the agreements they sign. The JCT 2011 Building Subcontracts has been written to help the busy subcontractor deal effectively with the range of JCT 2011 subcontracts they will encounter.Table of ContentsPreface xiii 1 Background and Introduction 1 1.1 The Joint Contracts Tribunal (JCT) 1 1.2 Sub-contracting 1 1.3 The formation of contracts and sub-contracts 2 1.4 Standard forms of contract and sub-contract 6 1.5 The JCT Sub-contracts dealt with within the chapters of this book 7 1.6 The JCT Sub-contracts not dealt with in the chapters of this book 10 2 The Sub-contract Agreement 17 2.1 Introduction 17 2.2 The structure of the sub-contract agreement 19 2.3 The recitals 20 2.4 The articles 22 2.5 The sub-contract particulars 23 2.6 Attestation forms 35 2.7 Schedule of information 37 2.8 Supplementary particulars 38 2.9 Equivalent sub-contract provisions 38 3 Definitions and Interpretations 44 3.1 Introduction 44 3.2 Definitions 44 3.3 Interpretation 45 3.4 Reckoning periods of days 46 3.5 Contracts (Rights of Third Parties) Act 1999 46 3.6 Giving of service of notices and other documents 46 3.7 Effect of the final payment notice (or the default payment notice) 47 3.8 Applicable law 49 3.9 Equivalent sub-contract provisions 49 4 Sub-contractors’ General Obligations 51 4.1 Introduction 51 4.2 General obligations 53 4.3 Sub-contractor’s design 59 4.4 Materials, goods and workmanship 71 4.5 Compliance with main contract and indemnity 75 4.6 Errors, discrepancies and divergences 76 4.7 Equivalent sub-contract provisions 80 5 Time 85 5.1 Introduction 85 5.2 Time and the adjustment to the period for completion 86 5.3 Practical completion and lateness 96 5.4 Equivalent sub-contract provisions 98 6 Defects, Design Documents and Warranties 102 6.1 Introduction 102 6.2 Defects 103 6.3 Sub-contractor’s design documents 107 6.4 Collateral warranties 108 6.5 Equivalent sub-contract provisions 113 7 Control of the Sub-contract Works 114 7.1 Introduction 114 7.2 Assignment and sub-letting 116 7.3 Person-in-charge 118 7.4 Access provided by the sub-contractor 119 7.5 Opening up the works and remedial measures 119 7.6 Attendance and site conduct 123 7.7 Health and safety and CDM 129 7.8 The CDM Regulations (i.e. the Construction (Design and Management) Regulations 2015) 135 7.9 Suspension of the main contract by the contractor 142 7.10 Benefits under the main contract 146 7.11 Certificates/statements or notices under the main contract 146 7.12 Equivalent sub-contract provisions 147 8 Payment 150 8.1 Introduction 150 8.2 The amount due in respect of interim payments 151 8.3 Unfixed materials 152 8.4 The amount due in respect of the final payment 153 8.5 Retention 156 8.6 Payment due dates and final dates for payment for interim payments 159 8.7 Payment Notices and Pay Less Notices for interim payments 160 8.8 The payment due date and the final date for payment for the final payment 162 8.9 Payment Notices and Pay Less Notices in respect of the final payment 162 8.10 VAT (Value Added Tax) 164 8.11 Construction Industry Scheme (CIS) 164 8.12 Interest 164 8.13 Sub-contractor’s right of suspension 165 8.14 Fluctuations 166 8.15 Equivalent sub-contract provisions 167 9 Loss and Expense 171 9.1 Introduction 171 9.2 Can common law damages claims be excluded by the contract? 173 9.3 Are claims for extensions of time and loss and/or expense linked? 173 9.4 What are the grounds/requirements for loss and expense? 174 9.5 What are Relevant Sub-contract Matters? 174 9.6 Can the contractor recover direct loss and/or expense from the sub-contractor? 176 9.7 In pursuing a loss and expense claim, what does a sub-contractor need to prove? 177 9.8 What needs to be proved in a loss and expense claim document? 179 9.9 What is a global claim? 180 9.10 Common heads of a loss and expense claim 182 9.11 Prolongation costs 183 9.12 Disruption claims 186 9.13 Winter working 187 9.14 Head office overheads and profit 187 9.15 Loss of profit 190 9.16 Increased costs 190 9.17 Cost of claim preparation 191 9.18 Interest and finance charges 191 9.19 Acceleration 192 9.20 Common law damages 193 9.21 Equivalent sub-contract provisions 196 10 Variations 197 10.1 Introduction 197 10.2 What is a variation? 198 10.3 How is a variation instructed? 198 10.4 Can a variation vitiate a contract? 199 10.5 Must a sub-contractor comply with all variation directions issued? 200 10.6 Must a sub-contractor comply with all variation directions issued that may injuriously affect the efficacy of the sub-contractor’s design? 200 10.7 What happens if a sub-contractor does not comply with a direction issued? 201 10.8 How should variations be valued? 201 10.9 How should variations that relate to a sub-contractor’s design work be valued? 201 10.10 What is the procedure to be followed in respect of a schedule 2 quotation? 202 10.11 What are the valuation rules? 205 10.12 Equivalent sub-contract provisions 210 11 Injury, Damage and Insurance 214 11.1 Introduction 214 11.2 Sub-contractor’s liability for personal injury or death 215 11.3 The sub-contractor’s liability for injury or damage to property 216 11.4 The sub-contractor’s liability for loss or damage to the sub-contract works 217 11.5 What Specified Perils insurance cover, in respect of loss or damage to works and site materials, does the sub-contractor obtain under the joint names all risks policies? 218 11.6 What is the sub-contractor’s liability for damage to the sub-contract works? 218 11.7 What are the employer’s options where terrorism cover is not available? 220 11.8 Is the contractor responsible for damage caused to the sub-contractor’s plant, etc.? 221 11.9 Is the sub-contractor required to take out professional indemnity insurance? 221 11.10 When and how does the Joint Fire Code apply? 222 11.11 Equivalent sub-contract provisions 223 12 Termination of Sub-contract 226 12.1 Introduction 226 12.2 How can a contract come to an end? 227 12.3 What can cause a sub-contract to be terminated? 228 12.4 What is a breach of contract? 228 12.5 Will any breach of contract enable one to terminate the sub-contract? 228 12.6 What is a repudiatory breach at common law? 229 12.7 Why have termination provisions in the contract if the sub-contract can be terminated at common law? 229 12.8 What is the effect of a sub-contract being terminated at common law? 230 12.9 Are the effects of a sub-contract being terminated under common law or by contractual provisions the same? 230 12.10 Where can the contractual termination provisions be located in the Sub-contract? 231 12.11 Are the party’s common law termination rights preserved under the Sub-contract? 231 12.12 What reasons give the contractor a right to terminate the sub-contractor’s employment under the JCT Sub-contract Conditions? 231 12.13 What is deemed to be default by the sub-contractor under clause 7.4.1 of SBCSub/D/C? 231 12.14 What happens when a sub-contractor commits a specified default noted at clause 7.4.1 of SBCSub/D/C? 232 12.15 Must all notices either by the Contractor or the Sub-contractor referred to under Section 7 ‘Termination’ of the sub-contract conditions be given in accordance with clause 1.7.4? 233 12.16 What does insolvency of the sub-contractor mean? 233 12.17 What happens when the sub-contractor becomes insolvent? 234 12.18 What does corruption entail? 235 12.19 What are the consequences of the contractor terminating the sub-contractor’s employment? 235 12.20 What reasons give the sub-contractor the right to terminate his or her employment under the JCT subcontract conditions? 237 12.21 What is deemed to be default by the contractor under clause 7.8.1 of SBCSub/D/C? 237 12.22 What happens when a contractor commits a specified default noted under clause 7.8.1 of SBCSub/D/C? 238 12.23 What does insolvency of the contractor mean? 239 12.24 What happens when the contractor becomes insolvent? 239 12.25 What are the consequences of the sub-contractor terminating his or her own employment? 240 12.26 If a sub-contractor’s employment is terminated for any reason, can it subsequently be reinstated? 242 12.27 Equivalent sub-contract provisions 242 13 Settlement of Disputes 245 13.1 Introduction 245 13.2 Mediation 245 13.3 Adjudication 247 13.4 Arbitration 253 13.5 Litigation 260 13.6 Equivalent Sub]contract provisions 263 Table of Cases 265 Table of Statutes and Regulations 269 Index 271

    £58.85

  • The Jct Standard Building Contract 2011

    John Wiley and Sons Ltd The Jct Standard Building Contract 2011

    Book SynopsisBooks about construction contracts tend to be dense and wordy, but what most architects, quantity surveyors, project managers, builders and employers are looking for is an easily navigable, simple guide to using a contract, written in plain language.Table of ContentsPreface xiv Abbreviations used in the text xvi Notes before reading xvii Part I Preliminaries 1 1 Introduction 1 1.1 What is a contract? 1 1.2 Purpose of building contracts 4 1.3 Types of construction contracts 4 1.4 Characteristics of a standard form 7 1.5 Commonly used contracts 9 1.6 Important background to SBC 11 1.7 SBC and variants 11 2 Basic matters 13 2.1 Works 13 2.2 Drawings 13 2.3 Specification 14 2.4 Schedules 15 2.5 Bills of quantities 15 2.6 The Standard Method of Measurement 16 2.7 Privity of contract and the Third Party Act 17 2.8 Third party rights and collateral warranties 18 2.9 Base Date 19 2.10 Common problems 20 3 About the contract documents 23 3.1 What constitutes the contract? 23 3.2 What are articles and recitals? 24 3.3 How to complete the contract form 25 3.4 Priority of documents 29 3.5 Errors, discrepancies and divergences 30 3.6 Custody and copies 34 3.7 Limits to use 35 3.8 Reckoning days 35 3.9 Certificates, notices and other communications 36 3.10 Applicable law 37 3.11 Common problems 37 4 Related matters 40 4.1 The Housing Grants, Construction and Regeneration Act 1996 as amended 40 4.2 Entire contracts 42 4.3 Express and implied terms 43 4.4 Limitation periods 44 4.5 Letters of intent 46 4.6 Quantum meruit 47 4.7 Limited companies 48 4.8 Bonds 49 4.9 Common problems 51 Part Ii Participants 53 5 The architect’s powers and duties 53 5.1 What the architect can do or must do 53 5.2 Specific requirements under the JCT contract 54 5.3 Powers 54 5.4 The architect’s design role under SBC 54 5.5 The architect as agent for the employer 61 5.6 No power to direct contractor 62 5.7 Issue of certificates 63 5.8 The issue of instructions 66 5.9 Instructions in detail 70 5.10 Issue of information 70 5.11 Duties under the contract 73 5.12 General duties 77 5.13 Does the architect have any duty to the contractor? 79 5.14 Common problems 79 6 The contractor’s powers and duties 82 6.1 What the contractor can do or must do 82 6.2 Person-in-charge 82 6.3 Access to the Works and premises 82 6.4 Carrying out the Works 96 6.5 Levels and setting out 98 6.6 Workmanship and materials 98 6.7 Contractor’s master programme and other documents 100 6.8 Statutory obligations 103 6.9 Antiquities 104 6.10 Drawings, details and information 104 6.11 Compliance with architect’s instructions 106 6.12 Suspension of performance 107 6.13 Does the contractor have a duty to warn of design defects? 108 6.14 Common problems 108 7 The employer’s powers and duties 110 7.1 What the employer can or must do 110 7.2 Express and implied powers and duties 110 7.3 General powers 115 7.4 General duties 122 7.5 Common problems 123 8 Consultants 125 8.1 General points 125 8.2 Quantity surveyors 126 8.3 Employer’s representative/project manager 128 8.4 Structural engineers, mechanical engineers and others 129 8.5 Common problems 129 9 The clerk of works 131 9.1 Method of appointment 131 9.2 Duties 131 9.3 Snagging lists 132 9.4 Defacing materials 132 9.5 Common problems 133 10 Sub-contractors and suppliers 134 10.1 General 134 10.2 Assignment 135 10.3 Sub-contracting 136 10.4 Listed sub-contractors 138 10.5 Named specialists 139 10.6 Common problems 140 11 Statutory authorities 143 11.1 Work not forming part of the contract 143 11.2 Statutory authorities in contract 143 11.3 The CDM Regulations 2007 145 11.4 Common problems 147 Part Iii Work in Progress 149 12 Insurance 149 12.1 Why insurance? 149 12.2 Types of insurance in the contract 149 12.3 What is an indemnity? 150 12.4 Injury to persons and property 151 12.5 Things that are the liability of the employer 152 12.6 Insurance terms 153 12.7 Insurance of the Works: alternatives 154 12.8 A new building where the contractor is required to insure 155 12.9 A new building where the employer insures 156 12.10 Alterations or extensions to an existing building 157 12.11 Benefits for sub-contractors 158 12.12 The Joint Fire Code 158 12.13 Terrorism cover 159 12.14 Common problems 159 13 Possession of the site 161 13.1 General 161 13.2 Date of possession 162 13.3 Common problems 163 14 Extension of time 165 14.1 Basics 165 14.2 Extension of time 166 14.3 Grounds 168 14.4 Procedure 177 14.5 Important conditions 186 14.6 Common problems 188 15 Liquidated damages 190 15.1 What are liquidated damages? 190 15.2 Procedure 191 15.3 Common problems 193 16 Financial claims 195 16.1 Loss and expense claims 195 16.2 Procedure 196 16.3 Effect on regular progress 200 16.4 The architect’s opinion 201 16.5 Ascertainment 202 16.6 Reimbursement under other contract provisions 203 16.7 Relevant matters forming the basis of a claim 203 16.8 Certification of direct loss and/or expense 207 16.9 Contractor’s other rights and remedies 208 16.10 Common problems 208 17 Architect’s instructions 210 17.1 Purpose 210 17.2 Scope 210 17.3 Common problems 216 18 Variations 219 18.1 What is a variation? 219 18.2 Does extra work always involve payment? 221 18.3 Valuation 222 18.4 Treatment of approximate quantities, defined and undefined provisional sums 227 18.5 If the conditions for carrying out other work are altered 228 18.6 Valuation of obligations and restrictions 229 18.7 Schedule 2 quotations 229 18.8 Acceleration 231 18.9 Daywork 232 18.10 Valuation of contractor’s designed portion 233 18.11 Common problems 233 19 Payment 235 19.1 The Contract Sum 235 19.2 Valuation 237 19.3 Method and timing 239 19.4 Payment procedure 240 19.5 Retention 243 19.6 Final payment 245 19.7 The effect of certificates 248 19.8 Off-site materials 250 19.9 Fluctuations 251 19.10 Common problems 252 20 Contractor’s design 254 20.1 Contractor’s Designed Portion (CDP) 254 20.2 Documents 254 20.3 The contractor’s obligations 255 20.4 Liability 258 20.5 Variations 259 20.6 Insurance 260 20.7 Common problems 261 Part Iv Closing Stages 263 21 Practical completion 263 21.1 Definition 263 21.2 What the contract says 263 21.3 Consequences 265 21.4 Partial possession and sectional completion 265 21.5 Common problems 267 22 Defects liability 269 22.1 During construction 269 22.2 Rectification period 271 22.3 Definition 271 22.4 Defects, shrinkages or other faults 271 22.5 Frost 272 22.6 Procedure 272 22.7 Common problems 275 23 Termination 276 23.1 General points 276 23.2 Termination by the employer 278 23.3 Grounds: contractor’s defaults 279 23.4 Grounds: insolvency of contractor 282 23.5 Grounds: corruption 283 23.6 Grounds: neutral causes 283 23.7 Grounds: insurance risks and terrorism cover 284 23.8 Consequences of termination for contractor’s default or insolvency 285 23.9 Consequences of termination for neutral causes or insurance risks 288 23.10 Termination by the contractor 288 23.11 Grounds: employer’s defaults 288 23.12 Grounds: insolvency of employer 292 23.13 Grounds: neutral causes 293 23.14 Grounds: insurance risks and terrorism cover 293 23.15 Consequences of termination for employer’s default, neutral causes or insolvency of the employer, etc. 293 23.16 Consequences of termination for insurance risks 294 23.17 Suspension of the Works by the contractor 295 23.18 Common problems 295 Part V Intractable Problems 297 24 Dispute resolution procedures 297 24.1 General 297 24.2 Adjudication 301 24.3 Arbitration 310 24.4 Legal proceedings (litigation) 317 24.5 Mediation 317 24.6 Common problems 317 Notes and references 319 Table of cases 330 Subject index 339 Clause number index to text 346

    £56.95

  • The Contractors NEC3 ECC Handbook

    John Wiley and Sons Ltd The Contractors NEC3 ECC Handbook

    1 in stock

    Book SynopsisAddresses the daily challenges faced by contractors who use the NEC3 ECC with clear, practical and useable advice on how to solve them Written in plain English for contractors and their staff, this book explains how the NEC3 contract works and provides answers to common questions. It presents complicated concepts in a simple, straightforward and understandable way, focusing mainly on day-to-day use. Steven Evans, an expert with thirty years of experience in construction, considers all the provisions of the contract and explains the procedures, obligations, and liabilities contained within it. NEC3 ECC is a process-based contract based on project management best practices. The basic philosophy behind it differs radically from the more adversarial approaches embodied by traditional contracts. While the NEC3 ECC may appear quite simple on the surface, it is often misunderstood and mismanaged by its day-to-day users. Despite the clear and urgent need for expert guidTable of ContentsAbout the Book xiii About the Author xv 1 Introduction 1 Ten Things You Need to Know 1 Author’s Note 2 2 The Contract 5 About the NEC Contract 5 Clarity and Simplicity 5 Flexibility 5 Stimulus to Good Management 6 Collaborate…or Else! 6 The Latham Report 6 The NEC3 Suite 7 Contracts 7 Flow Charts and Guidance Notes 8 The ECC Form 9 The Core Clauses 9 The Main Options 9 Option A – Priced Contract with Activity Schedule 10 Option B – Priced Contract with Bill of Quantities 11 Option C – Target Contract with Activity Schedule 11 Option D – Target Contract with Bill of Quantities 12 Option E – Cost Reimbursable Contract 12 Option F – Management Contract 13 W Clauses 13 The Secondary Options 14 X Clauses 14 Y Clauses 14 Z Clauses 15 The Contract Data 15 The Schedules 16 The Schedule of Cost Components 16 The Shorter Schedule of Cost Components 16 Formation of the Contract 16 Offer and Acceptance 16 Attestation 17 Necessary Contract Documents 17 Frequently Asked Questions 17 3 General 19 Overview 19 Actions 19 The Employer 20 The Contractor 22 The Project Manager 27 Impartiality 32 The Supervisor 32 The Obligations 33 Identified and Defined Terms 34 (1) The Accepted Programme 35 (2) Completion 36 (3) Completion Date 38 (4) The Contract Date 38 (5) Defect 39 (6) Defects Certificate 39 (7) Equipment 40 (8) The Fee 40 (9) Key Date 41 (10) Others 42 (11) Parties 42 (12) Plant and Materials 42 (13) To Provide the Works 43 (14) The Risk Register 44 (15) The Site 44 (16) Site Information 45 (17) Subcontractor 45 (18) Working Areas 46 (19) Works Information 46 (20) The Activity Schedule (Main Options A and C Only) 49 Who Prepares the List of Activities? 49 What Should be Included in the Schedule? 50 Relationship to the Accepted Programme 50 Changes to the Activity Schedule 50 Use Under Option A 51 Use Under Option C 51 Errors in the Activity Schedule 51 (21) The Bill of Quantities (Main Options B and D Only) 52 Changes to the Bill of Quantities 53 Use Under Option B 53 Use Under Option D 53 Errors in the Bill of Quantities 54 (22) to (26) Defined Cost 54 Main Options A and B 54 Main Options C to E 54 Main Option F 55 (25) Disallowed Costs 55 (27) Price for Work Done to Date (Option A) 56 (28) Price for Work Done to Date (Option B) 56 (29) Price for Work Done to Date (Options C to F) 57 (30) Prices (Main Options A and C) 57 (31) Prices (Main Options B and D) 57 (32) Prices (Main Options E and F) 57 (33) The Total of the Prices (Option D) 57 Interpretation and the Law 57 Communications 58 Notification 59 The Project Manager and the Supervisor 60 Adding to the Working Areas 61 Early Warning 61 Ambiguities and Inconsistencies 63 Illegalities and Impossibilities 64 Prevention 64 Frequently Asked Questions 65 4 The Contractor’s Main Responsibilities 71 Overview 71 Providing the Works 77 The Contractor’s Design 78 Acceptance of the Contractor’s Design 78 Using the Contractor’s Design 79 Design of Equipment 79 People 80 Working With the Employer and Others 81 Subcontracting 82 Other Responsibilities 84 Frequently Asked Questions 85 5 Time 89 Overview 89 Starting, Completion and Key Dates 89 Commencement and Completion 89 Completion Certificate 90 Key Dates 91 The Programme 91 The First Programme 92 Information on the Programme 92 Acceptance of the Programme 95 Rejection of the Programme 95 Revising the Programme 96 Access to and Use of the Site 98 Instructions to Stop or Not to Start the Work 98 Takeover 98 Acceleration 99 Frequently Asked Questions 100 6 Testing and Defects 105 Overview 105 Tests and Inspections 106 Tests and Inspections Before Delivery 107 Searching For and Notifying Defects 107 Searching 107 Notifying 108 Correcting Defects 108 Correction 108 Defect Correction Period 108 Defects Certificate 109 Accepting Defects 109 Uncorrected Defects 110 Frequently Asked Questions 111 7 Payment 115 Overview 115 Assessing the Amount Due 115 Main Option A 116 Main Option B 117 Main Option C 117 Amounts Due to Subcontractors 118 The Cost of Components in the Schedule of Cost Components 119 Disallowed Costs 119 The Fee 120 Main Option D 120 Amounts Due to Subcontractors 121 The Cost of Components in the Schedule of Cost Components 121 Disallowed Costs 121 The Fee 122 Main Option E 122 Amounts Due to Subcontractors 123 The Cost of Components in the Schedule of Cost Components 124 Disallowed Costs 124 The Fee 125 Main Option F 125 Amounts Due to Subcontractors 126 The Prices for the Work Done by the Contractor 127 Disallowed Costs 127 The Fee 127 Unfixed Materials on Site 128 Main Option A 128 Main Option B 128 Main Options C, D and E 128 Main Option F 128 The First Programme 128 Payment 128 The Primary Legislation 129 The Secondary Legislation 129 How it Works 129 A ‘Construction Contract’ 129 The Payment Provisions 130 The Payment Notice 130 The ECC Provisions 131 Interest 132 Defined Cost 132 The Contractor’s Share 133 The Activity Schedule 134 The Bill of Quantities 135 Frequently Asked Questions 135 8 Compensation Events 139 Overview 139 Compensation Events 140 Core Clause Compensation Events 140 Weather Measurement 146 Weather Data 146 Once in Ten Years 146 Bill of Quantity Compensation Events 149 Secondary Option Compensation Events 150 Clause X2.1 – Changes in the Law 150 Clause X12.3(6) and (7) – Changes in Partnering Information 151 Clause X14.2 – Delay in Making Advanced Payment 151 Clause X15.2 – Correction of a Defect 151 Clause Y2.4 – Suspension Under the Housing Grants, Construction and Regeneration Act 1996 151 Compensation Event Procedure 151 Notifying Compensation Events 151 Quotations for Compensation Events 154 Assessing Compensation Events 156 Effect of the Event on Defined Cost 157 Effect of the Event on Planned Completion 158 Failure to Give Early Warning 159 The Project Manager’s Assessment 159 Exhaustive Remedy 161 Implementing Compensation Events 161 Main Option Clauses 161 Summary of Sanctions 163 Other Remedies 164 Frequently Asked Questions 164 9 Title 169 Overview 169 The Employer’s Title to Plant and Materials 169 Marking Equipment, Plant and Materials Outside the Working Areas 170 Removing Equipment 171 Objects and Materials within the Site 171 Frequently Asked Questions 171 10 Risks and Insurance 173 Overview 173 Employer’s Risks 173 Contractor’s Risks 174 Repairs 175 Indemnity 175 Insurance Cover 175 Insurance Policies 176 If the Contractor Does Not Insure 176 Insurance by the Employer 177 Frequently Asked Questions 177 11 Termination 179 Overview 179 Termination 179 Reasons for Termination 180 Procedures on Termination 181 Payment on Termination 181 Frequently Asked Questions 183 12 Dispute Resolution (W1 and W2 Adjudication) 185 Overview 185 Option W1 185 Dispute Resolution 185 The Adjudicator 186 The Adjudication 188 Review by a Tribunal 191 Option W2 192 Dispute Resolution 192 The Adjudicator 193 The Adjudication 196 Review by a Tribunal 199 Frequently Asked Questions 200 13 X and Y Clauses 203 Introduction 203 The X Clauses 203 X1 – Price Adjustment for Inflation 203 X2 – Changes in the Law 204 X3 – Multiple Currencies 204 X4 – Parent Company Guarantees 205 X5 – Sectional Completion 205 X6 – Bonus for Early Completion 205 X7 – Delay Damages 206 X12 – Partnering 206 X13 – Performance Bond 207 X14 – Advanced Payment to the Contractor 207 X15 – Limitation of Contractor’s Liability for his Design to Reasonable Skill and Care 207 X17 – Low Performance Damages 208 X18 – Limitation of Liability 208 X20 – Key Performance Indicators 209 The Y Clauses 209 Y(UK)1 – Project Bank Account 209 Overview 209 Definitions 210 Project Bank Account 210 Named Suppliers 210 Payments 211 Effect of Payment 211 Trust Deed 211 Termination 211 Y(UK)2 – Housing Grants, Construction and Regeneration Act 1996 212 Overview 212 Definitions 212 Dates for Payment 212 Notice of Intention to Pay Less 212 Suspension of Performance 212 Y(UK)3 – Contracts (Rights of Third Parties) Act 1999 213 Overview 213 Frequently Asked Questions 213 14 Z Clauses 215 Overview 215 Additional Conditions of Contract 215 Frequently Asked Questions 216 15 Schedules of Cost Components 219 Overview 219 Schedule of Cost Components 219 Subcontractors 220 People 220 Equipment 220 Plant and Materials 221 Charges 222 Manufacture and Fabrication 222 Design 222 Insurance 222 Shorter Schedule of Cost Components 223 Subcontractors 223 People 223 Equipment 224 Plant and Materials 225 Charges 225 Manufacture and Fabrication 225 Design 225 Insurance 226 Frequently Asked Questions 226 Index 229

    1 in stock

    £62.65

  • MultiParty and MultiContract Arbitration in the

    John Wiley and Sons Ltd MultiParty and MultiContract Arbitration in the

    Book SynopsisMulti-Party and Multi-Contract Arbitration in the Construction Industry provides the first detailed review of multi-party arbitration in the international construction sector. Highly practical in approach, the detailed interpretation and assessment of the arbitration of multi-party disputes will facilitate understanding and decision making by arbitrators, clients and construction contractors.Trade Review"Dr Dimitar Kondev's book on multi-party and multi-contract arbitration in the construction industry tackles a complex topic, which presents many hurdles in practice. Dr Kondev has successfully accomplished this difficult task. He leads the reader through the intricacies and pitfalls of this subject in an efficient and well-structured manner. He also takes a convincing stance on the most controversial issue and proposes pragmatic and workable solutions to the recurring problems that arise with respect to multi-party arbitration in construction disputes. This book might be of interest not only for practitioners specialised in construction arbitration but also for the arbitration community... In view of the foregoing, there is no doubt that this book is a must read for arbitration practitioners. Let us hope that Dr Kondev’s recommendations will be well received and implemented by the practitioners and drafters of international standard forms and arbitration rules. This would be a significant step-forward in enhancing dispute resolution in the construction industry." Fabrice Robert-Tissot, International Business Law Journal (RDAI 2018/1, pp 121-124) “This is the first book which deals with multi-party and multi-contract arbitration in the construction sector.… In his book, Dr Kondev makes an in-depth analysis of the legal regulation of this type of arbitration contained in the most popular institutional arbitration rules and the arbitration laws of different jurisdictions. The book also offers an up-to-date and thorough review of how multi-party and multi-contract arbitration is dealt with in the most widely used international standard forms of construction contract (such as the FIDIC books, NEC3, etc.) and some domestic standard forms (used mostly in Great Britain, the US and some Scandinavian countries)… The book also contains practical guidelines for drafting multi-party arbitration clauses… Because of the importance of the matters discussed in this treatise, it would be of great value to lawyers, arbitrators and academics in the field of international commercial arbitration.” Society and Law (5/2017, pp 111-112) "Complex arbitration disputes involving multiple parties and multiple contracts are both an evergreen – as demonstrated by the extensive literature on the subject – and a hot topic – confirmed, eg, by numerous amendments to arbitration rules in recent years... Given this background, is it possible to add anything new or meaningful? KONDEV has demonstrated that it definitely is. On the one hand, his study is clearly structured, well written, and thoroughly researched; this alone makes it stand out and merit a strong recommendation. On the other hand, KONDEV adds a specialist perspective to the debate, namely that of the construction industry... The author ‘attempted to bridge the gap between the theoretical proposals regarding multi-party arbitration and their practical application’ (pp 326-327). It is submitted that he fully succeeded. Anyone dealing with multi-party, multicontract issues in the construction industry will benefit from this new book – drafters of contracts or rules as well as counsel, arbitrators, or judges in pending proceedings." Johannes Landbrecht, 36 ASA Bulletin 1/2018 (March), p. 256 “Another publication on multi-party arbitration? Was that necessary, given that a lot has been written about this topic over the years already? It was. For at least two reasons. First, most of the existing contributions discuss the issue in a general context without regard to the peculiarities of disputes and specific contractual frameworks found in the construction industry. Second, many articles identify the numerous problems of multi-party arbitration without providing any self-contained practical solutions. Dimitar Kondev’s 408-page book fills these two gaps… For a number of reasons, Kondev’s book is of great value. It provides a useful overview of different approaches in arbitration rules, arbitration legislation and standard form contracts. It explains the importance of tailoring arbitration agreements to reflect the peculiarities of each project, the peculiarities of the underlying contracts, the peculiarities of the applicable arbitration rules and relevant national laws. Finally, the author addresses concerns and provides thoughts and ideas that are absolutely essential for drafting multi-party arbitration clauses. Not only, but in particular, the last two chapters of the book are very inspiring, even for experienced practitioners, and the various committees and working groups involved in the development of standard form contracts and arbitration rules.” Hein-Jürgen Schramke, Construction Law International 13 (1) (March 2018) “As surprising as it may sound, Multi-Party and Multi-Contract Arbitration in the Construction Industry appears to be the first published monograph dealing specifically with the topic of multi-party and multi-contract arbitration in the construction sector. [Dr Kondev's] dual background as practicing lawyer and scholar allows him to address with success the topic of this book from both theoretical and practical standpoints... Dr Kondev’s expertise and well researched approach makes this monograph a highly informative read. Dr Kondev’s insightful book will be of use first and foremost to construction practitioners who are looking for a comprehensive study of the difficulties raised by the multi-party and multi-contract nature of construction disputes. That book, however, should also appeal to general arbitration practitioners and academics looking to deepen their understanding of multi-party and multi-contract arbitration, as much of the insights transpose well into areas of arbitration practice other than construction." Dr. Remy Gerbay, ICC Dispute Resolution Bulletin, Issue 2 (2018), pp. 83-84 “Dr Kondev’s book provides a useful in-depth analysis of the three main legal sources of the regulation of multi-party arbitration: the arbitration agreement, applicable arbitration rules and arbitration laws… Dr Kondev’s clear analysis leads him to conclude that the current legal framework has largely failed to provide workable solutions for the construction sector. He suggests two ways in which this framework could be improved: through the contractual regulation of multi-party disputes and by amendments to the arbitration institutional rules. Of particular practical use, recognising that the drafting of multi-party arbitration clauses can be a daunting complex exercise, Dr Kondev considers in detail the drafting of such clauses. He provides clear, and sensible guidelines, as a checklist for the drafter. Overall Dr Kondev has achieved his aim: to contribute at the theoretical level and to produce a book with a clear practical approach to the problems discussed. His book is of interest to anyone involved or interested in international construction arbitration including in-house lawyers, arbitrators, private practitioners, academics and those involved in drafting international standard forms and arbitration rules. “ Marion Smith QC, 35 The International Construction Law Review, No. 3 (2018), pp. 359-360 Table of ContentsAbout the Author x Foreword xi Preface xiii Acknowledgements xv List of Abbreviations xvi 1 Introduction 1 1.1 General background and research problem 1 1.2 Scope of the book, limitations and literature review 4 1.2.1 Scope of the book 4 1.2.2 Limitations 4 1.2.3 Literature review 5 1.3 Sources used 6 1.4 Structure of the book 9 1.5 Aims and contribution of the book 10 2 Multi‐Party Arbitration in General 11 2.1 Terminology notes 11 2.1.1 Definition of multi‐party arbitration 11 2.1.2 Multi‐party and multi‐contract arbitration: divergent or similar concepts? 12 2.1.3 Group of contracts doctrine 14 2.2 Legal techniques introducing multi‐party arbitration 15 2.2.1 Single request for arbitration 16 2.2.2 Joinder 16 2.2.3 Intervention 16 2.2.4 Consolidation 17 2.3 Advantages of multi‐party arbitration 18 2.3.1 Avoids risk of inconsistent findings 18 2.3.2 Less time and fewer costs 19 2.3.3 Fewer factual errors 20 2.4 Obstacles to multi‐party arbitration 21 2.4.1 Consensual nature of arbitration 21 2.4.2 Arbitration as a two‐party setup 23 2.4.3 Arbitration as a confidential process 24 2.4.4 Setting aside proceedings and non‐recognition and / or non‐enforcement of arbitral awards 26 2.4.5 Practical difficulties 30 3 The Need for Multi‐Party Arbitration in the Construction Sector 31 3.1 Specifics of construction disputes and construction arbitration 31 3.2 Introduction to international standard form construction agreements 33 3.2.1 FIDIC Conditions of Contract 33 3.2.2 NEC contracts 36 3.2.3 ICC contracts 37 3.2.4 ENAA model forms 38 3.2.5 IChemE contracts 39 3.2.6 PPC International and SPC International 39 3.3 Contractual structures in construction projects 40 3.3.1 ‘Build‐only’ projects 40 3.3.2 ‘Design‐build’ or ‘turnkey’ projects 41 3.3.3 Construction management 43 3.3.4 Management contracting 44 3.3.5 ‘Design‐build‐operate’ (‘DBO’) model 45 3.3.6 Partnering and alliancing 46 3.4 Parties’ interests in multi‐party arbitration 46 3.4.1 Employer 46 3.4.2 Contractor 51 3.4.3 Subcontractor 52 3.4.4 Designer 53 3.4.5 Engineer 54 3.4.6 Suppliers 56 3.4.7 Technical consultants 56 3.4.8 Guarantors 56 3.4.9 Concluding remarks 58 4 Multi‐Party Arbitration Solutions under Arbitration Rules 60 4.1 ICC Rules 61 4.1.1 Multi‐contract claims and prima facie assessment 62 4.1.2 Joinder 67 4.1.3 Consolidation 69 4.2 CEPANI Rules 71 4.2.1 Multiple parties and multi‐contract claims 71 4.2.2 Joinder and intervention 73 4.2.3 Consolidation 75 4.3 LCIA Rules 77 4.4 UNCITRAL Rules 80 4.5 Swiss Rules 84 4.5.1 Prima facie test 84 4.5.2 Consolidation 84 4.5.3 Joinder and intervention 88 4.6 Rules adopted by the American Arbitration Association (‘AAA’) 90 4.6.1 Construction Industry Arbitration Rules (‘CIAR’) 90 4.6.2 ICDR Rules 92 4.7 Vienna Rules 94 4.7.1 Joinder 95 4.7.2 Consolidation 98 4.8 DIS Arbitration Rules 99 4.9 SCC Rules 100 4.10 DIA Rules 101 4.11 Arbitration rules in Asia 102 4.11.1 CIETAC Rules 102 4.11.2 SIAC Rules 106 4.11.3 HKIAC Rules 109 4.11.4 JCAA Rules 114 4.12 Concluding remarks regarding arbitration rules 115 5 Multi‐Party Arbitration Solutions under Arbitration Laws 121 5.1 UNCITRAL Model Law 122 5.2 The United Kingdom 124 5.3 The Netherlands 129 5.4 Belgium 131 5.5 New Zealand 132 5.6 Hong Kong 133 5.7 Canada 137 5.8 Australia 138 5.9 Other countries 139 5.10 Multi‐party arbitration in the United States 140 5.10.1 Legal framework 140 5.10.2 United States’ case law on multi‐party arbitration 146 5.11 Should arbitration laws deal with multi‐party arbitration? 158 5.12 Concluding remarks regarding arbitration laws 164 6 Contractual Solutions to Multi‐Party Arbitration 167 6.1 FIDIC Conditions of Contract 169 6.2 Blue Form 175 6.2.1 Clause 18(2) of the 1984 Blue Form 175 6.2.2 Use of the Blue Form in conjunction with the FIDIC Conditions of Contract 183 6.2.3 Commentary on clause 18(2) 189 6.2.4 Clause 18(8) of the 1991 Blue Form 201 6.2.5 Clause 18(10) of the 1998 Blue Form 205 6.2.6 Clause 18C(4) of the 2008 Blue Form 206 6.3 JCT Contracts 208 6.3.1 JCT 80 approach to multi‐party arbitration 209 6.3.2 Commentary on the JCT 80 approach 219 6.3.3 New JCT approach 222 6.4 ACA standard forms 223 6.5 Nec3 226 6.5.1 Main contract provisions 227 6.5.2 Subcontract provisions 229 6.5.3 Do NEC3 provisions create a self‐contained mechanism for joint adjudication? 230 6.5.4 Compatibility between the joint adjudication provisions and the dispute notification requirements 232 6.6 IChemE contracts 234 6.7 ICC contracts 237 6.8 PPC and SPC International 238 6.9 ENAA Model forms 240 6.10 AIA standard forms 242 6.11 ConsensusDocs 247 6.12 AB 92 and ABT 93 250 6.13 Concluding remarks regarding contractual approaches 252 7 Proposed Solutions 255 7.1 Jurisdictional approach 256 7.2 Abstract consensual approach 262 7.3 Proposed contractual solutions 264 7.3.1 IBA guidelines for Drafting International Arbitration Clauses 267 7.3.2 AAA Guide to Drafting Alternative Dispute Resolution Clauses for Construction Contracts 271 7.3.3 Drafting Multi‐Party Arbitration Clauses 273 7.3.4 Sample multi‐party arbitration clause 303 7.4 Institutional approach 313 7.4.1 How to create a workable multi‐party arbitration mechanism under arbitration rules? 315 7.4.2 Compatibility of arbitration agreements 319 7.4.3 Other circumstances 322 8 Conclusion 325 Table 1 Summary of Multi-Party Arbitration Provisions under the Reviewed Arbitration Rules 328 Table 2 Summary of Multi-Party Arbitration Provisions under Arbitration Laws 333 Appendix 1 Second Alternative Clause of Clause 20 of the FIDIC Subcontract 337 Appendix 2 Multi‐Party Arbitration Provisions under the Blue Form 351 Appendix 3 Multi‐Party Arbitration Clauses under the ENAA Model Form – International Contract for Process Plant Construction, 2010 and Related Subcontracts 355 Bibliography 358 Index 381

    £82.60

  • Construction Adjudication

    John Wiley and Sons Ltd Construction Adjudication

    Book SynopsisAdjudication has been the main means of settling construction disputes since it was first introduced by the Housing Grants, Construction and Regeneration Act 1996, and a substantial body of case law has now built up. This book established itself as the key authority on adjudication when it was first published. It has now been revised to reflect the authors'' experience of adjudication in practice and to cover the large number of court decisions. It features useful appendices on adjudication materials.Trade Review'The book ... is the best in the business' Tony Bingham, Building 13 August 2004 'This is a cracking book, even better than the first edition and one I even took on holiday with me! Anyone practising adjudication or involved in the process should not have this work far from the corner of their desk. Go and buy it.' Construction Industry Law Letter 'A solid compilation which many readers will rely on heavily.' Paul Newman, Construction Law Aug/Sep 2005 ‘[From] highly experienced adjudicators this second edition distils five years of their experience and wisdom and is a welcome addition to the literature… thoroughly readable yet comprehensive’ John Uff QCTable of ContentsWhat is adjudication?; The Act: the overarching provisions; The Act: the adjudication provisions; The Act: the payment provisions; The secondary legislation; Adjudication clauses, rules and procedures; The appointment; Adjudicators’ agreements; Jurisdiction, powers and duties; The process; The decision; Enforcement and appeals; Appendices

    £100.76

  • Liquidated Damages and Extensions of Time

    John Wiley and Sons Ltd Liquidated Damages and Extensions of Time

    Book SynopsisLiquidated damages and extensions of time are complex subjects, frequently forming the basis of contract claims made under the standard building and civil engineering contracts. Previous editions of Liquidated Damages and Extensions of Time are highly regarded as a guide for both construction industry professionals and lawyers to this complex area. The law on time and damages continues to develop with an increasing flow of judgments from the courts. Alongside this, the standard forms of contract have also developed over time to reflect prevailing approaches to contractual relationships. Against this background a third edition will be welcomed by construction professionals and lawyers alike. Retaining the overall approach of the previous editions, the author clarifies, in a highly readable but legally rigorous way, the many misunderstandings on time and damages which abound in the construction industry. The third edition takes account of a Trade Review"Practitioners of construction contracts owe a debt to Brian Eggleston for this updated publication and the sooner they add this to their library the better." (The Expert and Dispute Resolver, Spring 2009) "Eggleston has once again hit the nail on the head with this high-quality, easy to understand legal textbook written for lawyers and the industry." (Building Magazine, February 2009)Table of ContentsPreface. References. Acknowledgements. 1 Introduction. 1.1 General overview. 1.2 Legal developments. 1.3 Contractual developments. 2 Time in contracts. 2.1 Problems with terminology. 2.2 Conditions and warranties. 2.3 Termination. 2.4 Time for performance. 2.5 Time of the essence. 2.6 Notice making time of the essence. 2.7 Time at large. 2.8 Reasonable time. 2.9 Fixing time by reference to correspondence. 2.10 The effect of time at large on the contract price. 3 Damages for late completion. 3.1 Liquidated and general damages distinguished. 3.2 Principles of general damages. 3.3 Alternative remedies. 3.4 Can general damages exceed liquidated damages? 3.5 Under-liquidation of damages. 3.6 Double damages. 3.7 Liability for damages in tort. 3.8 The Panatown problem. 4 Liquidated damages and penalties. 4.1 Penalties – general introduction. 4.2 Liquidated damages. 4.3 Liquidated damages and penalties distinguished. 4.4 Pre-estimates of damage. 4.5 Particular aspects of penalty clauses. 4.6 Evidential matters. 4.7 Bonus clauses. 4.8 Site occupation charges. 5 Prevention. 5.1 Principle of prevention. 5.2 Need for extension of time provisions. 5.3 Defining an act of prevention. 5.4 Prevention after the completion date. 5.5 Effect of late variations on unliquidated damages. 5.6 Prevention and time at large. 5.7 Conditions precedent and time-bars. 5.8 Steria v. Sigma (2007). 6 Legal construction of liquidated damages clauses. 6.1 Rules of construction. 6.2 Contra proferentem rule. 6.3 Restrictions on implied terms. 6.4 ’Catch all’ phrases. 6.5 Inconsistencies in drafting. 7 Effects of determination. 7.1 The question of continuing responsibility. 7.2 British Glanzstoff. 7.3 Contractual provisions. 7.4 Novations. 7.5 Summary on liquidated damages. 7.6 Determination and limitation on liability. 8 Problems with sectional completion. 8.1 Discovering the parties’ intentions. 8.2 Proportioning down clauses. 8.3 Provisions for sectional completion. 8.4 Requirements not fully specified. 9 Application to sub-contractors. 9.1 Effect of ‘stepping-down’ provisions. 9.2 Can there be a genuine pre-estimate of loss? 9.3 Commercial considerations. 9.4 Nominated sub-contracts. 10 Recovery of liquidated damages. 10.1 When do liquidated damages become payable? 10.2 Meaning of completion. 10.3 Certificates and conditions precedent. 10.4 Methods of recovery. 10.5 Time limits on recovery. 10.6 Interest on repayment. 10.7 Withholding notices. 10.8 Decisions of adjudicators. 11 Defences/challenges to liquidated damages. 11.1 Benefits of precedents. 11.2 Extension of time due. 11.3 Completion achieved earlier than certified. 11.4 Certificates not valid. 11.5 Conditions precedent not observed. 11.6 No date for commencement. 11.7 Prevention. 11.8 Penalties. 11.9 Provisions void for uncertainty. 11.10 Waiver/estoppel. 11.11 Unfair Contract Terms Act 1977. 12 Extensions of time. 12.1 Purposes of extension provisions. 12.2 Notices, applications and assessments. 12.3 Time for granting extensions. 12.4 Application to claims. 12.5 Proof of entitlement. 12.6 Global claims. 13 Relevant events. 13.1 Force majeure. 13.2 Adverse weather. 13.3 Civil commotion, strikes etc. 13.4 Damage to the works. 13.5 Sub-contractors. 13.6 Non-availability of resources. 13.7 Statutory undertakers’ works. 13.8 Other special circumstances. 13.9 Statutory powers. 13.10 Possession and access. 13.11 Late issue of drawings and instructions. 13.12 Variations and extra works. 13.13 Compliance with instructions. 13.14 Unforeseen physical conditions. 14 Causation and concurrency. 14.1 Introduction. 14.2 Causation generally. 14.3 Concurrency generally. 14.4 Dominant cause approach. 14.5 Apportionment. 14.6 Rules for extension of time. 14.7 Discussion on various approaches. 14.8 Extensions when in culpable delay. 15 Programmes, method statements and best endeavours. 15.1 Status of contractor’s programmes and method statements. 15.2 Programmes. 15.3 Shortened programmes. 15.4 Method statements. 15.5 Best endeavours and the like. 16 Delay analysis. 16.1 Introduction. 16.2 Critical paths. 16.3 Float. 16.4 Methods of delay analysis. 16.5 Judicial comments on delay analysis. 17 Building forms. 17.1 Introduction. 17.2 JCT 2005 contracts. 17.3 Commencement and completion. 17.4 Notification of delay. 17.5 Extension of time. 17.6 Relevant events. 17.7 Non-completion certificates. 17.8 Payment of liquidated damages. 17.9 Proportioning down liquidated damages. 18 Civil engineering forms. 18.1 NEC 3 – Engineering and Conditions of Contract, 2005. 18.2 ICE Conditions of Contract – 7th edition, 1999. 18.3 ICE Conditions of Contract for Minor Works – 3rd edition, 2001. 18.4 CECA Form of Sub-Contract, 2008. 19 Process and plant forms. 19.1 I.Chem.E. Red Book – 4th edition, 2001. 19.2 MF/1 (Rev. 4) – 2000 edition. 20 FIDIC Conditions of Contract 1999. 20.1 FIDIC contracts. 20.2 Commencement and completion. 20.3 Extension of time. 20.4 Delay damages. Table of Cases. Index.

    £100.76

  • The JCT Minor Works Building Contracts 2005

    John Wiley and Sons Ltd The JCT Minor Works Building Contracts 2005

    Book SynopsisThe Minor Works Building Contract is the most widely used of the JCT forms of contact, not only for simple, short contracts of moderate price, for which it is intended, but also for much larger projects for which it is often not suited at all. As a result, contractual difficulties can arise, and despite the form''s simplicity an understanding of the legal background to the form is essential. This book explains the practical applications of the form from the point of view of the employer, architect and contractor. It provides a straightforward explanation of the legal aspects of the form supported by flow charts, tables and sample letters. The Fourth Edition has been revised to cover the 2005 edition of the form, which has given the contract a completely new look. The book now covers the new JCT Minor Works Building Contract with contractor''s design (MWD).Trade Review'The first [edition] was an instant hit for me and edition four is just as good.' Tony Bingham, Building 'Makes interesting reading of a subject not many of us would expect to enjoy...A useful reference book for any architect, employer or contractor involved in minor or small works and one that is likely to be used time and time again'. The Expert and Dispute Resolver Summer 2007.Table of ContentsPreface to the Fourth Edition. Chapter 1 The Purpose and Use of MW and MWD . 1.1 The background. 1.2 The use of MW and MWD. 1.3 Arrangement and contents of MW and MWD. 1.4 Contractual formalities. 1.5 Problems with the contract documents. 1.6 Notices, time and the law. Chapter 2 Contract Comparisons . 2.1 Introduction. 2.2 JCT contracts compared. Chapter 3 Contract Documents and Insurance . 3.1 Contract documents. 3.1.1 Types and uses. 3.1.2 Importance and priority. 3.1.3 Custody and copies. 3.1.4 Limits to use. 3.2 Insurance. 3.2.1 Injury to or death of persons. 3.2.2 Damage to property. 3.2.3 Insurance of the Works against fire etc. 3.2.4 A new building where the contractor is. required to insure. 3.2.5 Alterations or extensions to existing structures. 3.3 Summary. Chapter 4 Architect . 4.1 Authority and duties. 4.2 Express provisions of the contract. 4.3 Architect’s instructions. 4.4 Summary. Chapter 5 Contractor . 5.1 Contractor’s obligations: express and implied. 5.1.1 Legal principles. 5.1.2 Execution of the works. 5.1.3 Workmanship and materials. 5.1.4 Statutory obligations. 5.1.5 Contractor’s representative. 5.2 Other obligations. 5.2.1 Access to the works and premises. 5.2.2 Compliance with architect’s instructions. 5.2.3 Suspension of obligations. 5.2.4 Other rights and obligations. 5.3 Summary. Chapter 6 Employer . 6.1 Powers and duties: express and implied. 6.2 Rights under MW and MWD. 6.2.1 General. 6.2.2 Damages for non-completion. 6.2.3 Other rights. 6.3 Duties under MW and MWD. 6.3.1 General. 6.3.2 Payment. 6.3.3 Retention. 6.3.4 Other duties. 6.4 Summary. Chapter 7 Quantity Surveyor and Clerk of Works . 7.1 Quantity surveyor. 7.1.1 Appointment. 7.1.2 Duties. 7.1.3 Responsibilities. 7.2 Clerk of works. 7.2.1 Appointment. 7.2.2 Duties. 7.2.3 Responsibilities. 7.3 Summary. Chapter 8 Subcontractors and Suppliers . 8.1 General. 8.2 Subcontractors. 8.2.1 Assignment. 8.2.2 Subcontracting. 8.2.3 Nominated subcontractors. 8.3 Statutory authorities. 8.4 Works not forming part of the contract. 8.5 Summary. Chapter 9 Possession, Completion and Defects Liability . 9.1 Possession. 9.1.1 Introduction. 9.1.2 Date for possession. 9.2 Practical completion. 9.2.1 Definition. 9.2.2 Consequences of practical completion. 9.3 Rectification period. 9.3.1 Definition. 9.3.2 Defects, shrinkages and other faults. 9.3.3 Frost. 9.3.4 Procedure. 9.4 Summary. Chapter 10 Claims . 10.1 General. 10.2 Extension of time. 10.2.1 Legal principles. 10.2.2 Liquidated damages. 10.2.3 Extending the contract period. 10.3 Money claims. 10.3.1 General. 10.3.2 Types of claims. 10.4 Summary. Chapter 11 Payment . 11.1 Contract sum. 11.2 Payment before practical completion. 11.3 Penultimate certificate. 11.4 Final certificate. 11.5 Effect of certificate. 11.6 Interest and withholding payment. 11.7 Retention. 11.8 Variations. 11.9 Order of work. 11.10 Provisional sums. 11.11 Fluctuations. 11.12 Summary. Chapter 12 Termination . 12.1 General. 12.2 Termination by the employer. 12.2.1 Grounds and procedure. 12.2.2 Consequences of employer termination. 12.3 Termination by the contractor. 12.3.1 General. 12.3.2 Grounds and procedure. 12.3.3 Consequences of contractor termination. 12.4 Termination by either employer or contractor. 12.5 Summary. Chapter 13 Contractor’s Designed Portion (CDP) . 13.1 General. 13.2 Documents. 13.3 The contractor’s obligations. 13.4 Liability. 13.5 Integration of the CDP. 13.6 Contractor’s information. 13.7 Variations. 13.8 Other matters. 13.9 Summary. Chapter 14 Dispute Resolution Procedures . 14.1 General. 14.2 Adjudication. 14.2.1 The contract provisions. 14.2.2 The Scheme: starting the adjudication process. 14.2.3 The Scheme: appointment of the adjudicator. 14.2.4 The Scheme: the adjudication process. 14.2.5 The Scheme: important powers and duties of. the adjudicator. 14.2.6 The Scheme: the decision. 14.2.7 The Scheme: award of costs. 14.3 Arbitration. 14.3.1 General. 14.3.2 The appointment of an arbitrator. 14.3.3 Powers of the arbitrator. 14.3.4 CIMAR procedure. 14.4 Legal proceedings. 14.5 Summary. Table of Cases . Clause Number Index to Text . Subject Index

    £71.96

  • Contract Changes: The Dark Side of EU Procurement

    Edward Elgar Publishing Ltd Contract Changes: The Dark Side of EU Procurement

    20 in stock

    Book SynopsisContract Changes comparatively analyses the contract modification regulation of 11 EU Member States, drawing on case law and common legal practice. As the first comparative study of material contract modifications, this book explores the interpretation of key concepts such as: unforeseen circumstances, non-equivocal clauses and the overall nature of the contract.Highlighting the discord between the transparency of the award of a public contract and the transparency of its implementation, the book interprets the execution phase of procurement contracts as the dark side of public procurement. Considering unforeseen circumstances, the change of the identity of the contractor, non-compliance and remedies, this book provides a unique insight into the challenges of interpretation and application of contract modification rules. It concludes that, whilst the flexibility to make contract amendments is required in some circumstances, the grounding principles of public procurement law must be considered and applied in these instances.This original book will be of interest to researchers who are working in public procurement, European and comparative law. It will also be valuable to lawyers, contractors and policymakers involved with public procurement contracts, contracting authorities and advising private companies.Trade Review‘The execution phase of public contracts is subject to public procurement law and principles, but it is non-transparent compared with the pre-award stages of public contracting. With its comparative study of procurement contract execution in several EU countries this book provides a highly valuable insight into this post-award area of public procurement law.’ -- Sune Troels Poulsen, Attorney at Sune Troels Poulsen Law FirmTable of ContentsContents: Foreword xi 1 Introduction: why the ‘Dark Side of procurement’? 1 Dacian C. Dragos and Bogdana Neamtu 2 Fundamentals of contract modifications in EU procurement law 17 Kirsi-Maria Halonen 3 Change of the identity of the contractual partner 35 Nicolas Gabayet 4 Non-compliance with government contract terms: a comparative view on procurement regulation and contractual remedies 48 Désirée Klingler and Pedro Telles 5 Unforeseen circumstances that justify changes to public contracts 68 Mari Ann Simovart 6 Modification of contracts in Denmark 96 Carina Risvig Hamer 7 Public contract modifications in England, Wales, and Northern Ireland 109 Pedro Telles 8 Contract changes in Finland 125 Merja Kortesuo and Pilvi Takala 9 Contract changes in France 140 François Lichère and Valentin Lamy 10 Contract changes in Germany and Austria 154 Christoph Krönke and Valentina Neubauer 11 Contract changes in Italy 178 Benedetta Biancardi, Roberto Caranta and Paolo Patrito 12 Contract modifications in Poland – Much ado about nothing? 194 Piotr Bogdanowicz 13 Contract changes in the Romanian law 206 Daniela Cimpean, Dacian C. Dragos and Bogdana Neamtu 14 Contract changes in the Spanish system on public procurement 220 Patricia Valcárcel Fernández 15 Contract modifications in the Netherlands: understanding the law, jurisprudence and practice 234 Erik Plas and Willem A. Janssen Index 249

    20 in stock

    £105.00

  • HOAI-Kommentar: zur Honorarordnung für

    Springer Fachmedien Wiesbaden HOAI-Kommentar: zur Honorarordnung für

    Book SynopsisAm 17. Juli 2013 ist die 7. HOAI-Novelle in Kraft getreten. Mit dieser vollständig überarbeiteten Auflage wird eine umfassende und praxisnahe juristische Kommentierung aller Leistungsbereiche der in der HOAI 2013 erfassten Architekten- und Ingenieurleistungen vorgelegt. Die Herausgeber kommentieren in Zusammenarbeit mit Fachingenieuren die gesamte Honorarordnung und stellen sowohl für Architekten und Ingenieure, als auch für Rechtsanwälte und Richter, die mit Fragen des Architektenhonorarrechts befasst sind, ein wichtiges Arbeitsmittel zur Verfügung, das Sicherheit in der Auslegung und Anwendung der Bestimmungen vermittelt und auch die neueste zur HOAI ergangene Rechtsprechung berücksichtigt. Bitte beachten: Für das Bearbeiterverzeichnis und die Zuordnung der Bearbeiter zu den Paragrafen wurde ein Erratum erstellt. Es steht auf dieser Seite als Download zur Verfügung.Table of ContentsWortlaut der HOAI 2013.- Amtliche Begründung.- Kommentar zur HOAI 2013.

    £132.99

  • Die Verordnung über Anlagen zum Umgang mit

    Springer Fachmedien Wiesbaden Die Verordnung über Anlagen zum Umgang mit

    1 in stock

    Book SynopsisDas Buch gliedert sich in 3 Abschnitte. Im ersten Abschnitt wird der Wortlaut der neuen Verordnung über Anlagen zum Umgang mit wassergefährdenden Stoffen (AwSV April 2017) wiedergegeben. Im zweiten Abschnitt wird die offizielle Begründung abgedruckt, die die Zielsetzung der AwSV für den Fachmann erläutert. Im dritten Abschnitt, der Synopse, wird der Text der neuen AwSV der alten Muster VAwS (Anlagenverordnung wassergefährdende Stoffe) gegenübergestellt. Dadurch werden die Änderungen der Novelle deutlich herausgearbeitet und der Planer und Gutachter kann entsprechend handeln.Table of ContentsVerordnungstext AwSV 2017.- Begründung zur AwSV (18.03.2016).- Synopse AwSV und Muster-VAwS.

    1 in stock

    £44.99

  • Die Honorarklage von Architekten und Ingenieuren

    Springer Fachmedien Wiesbaden Die Honorarklage von Architekten und Ingenieuren

    1 in stock

    Book SynopsisDer Architekten- und Ingenieur-Honorarprozess vor Gericht stellt besondere Anforderungen an beide Parteien, den Aufraggeber und den Aufragnehmer, sowie deren Prozessbevollmächtigte. Dies gilt gleichermaßen für die materiellen Anspruchsvoraussetzungen als auch hinsichtlich der prozessualen Besonderheiten des Honorarrechtsstreits. Für den Kläger kommt es darauf an, den Honoraranspruch unter Beachtung der Rechtsprechung schlüssig darzulegen und die Weichen im Verlauf des Prozesses richtig zu stellen. Dabei liegt ein besonderes Augenmerk auf der Honorarermittlung nach der HOAI. Der Beklagte muss eine effektive Verteidigungsstrategie festlegen. Dargestellt werden dabei nicht nur die relevanten Einwendungen, Einreden und denkbare Gegenforderungen, sondern auch den Prozess betreffende Fragen und Besonderheiten. Für Gesamtschuldfälle werden Fragen der Sicherung von möglichen Regressansprüchen erörtert.Trade Review“Diese Spezialkenntnisse erhält man in sehr verständlicher, praxisnaher und kompakter Form in dem Handbuch von Averhaus, wobei die für die Honorarforderung (Klage) relevanten Rechtsthemen ausreichend behandelt und mit zahlreichen Rechtssprechungs- und Literaturnachweisen unterlegt sind.“ (Dr. Christian Leesmeister, in: NzBau, Heft 6, 2017) Table of ContentsDen Honoraranspruch schlüssig einklagen.- Honorare nach der HOAI richtig ermitteln.- Effektive Verteidigung gegen die Honorarklage.- Prozessuale Besonderheiten.

    1 in stock

    £52.24

  • E-Vergabe – Praxishinweise und Marktüberblick:

    Springer Fachmedien Wiesbaden E-Vergabe – Praxishinweise und Marktüberblick:

    1 in stock

    Book SynopsisDieses essential bietet einen schnellen Überblick über die praxisrelevanten Aspekte der bis Herbst 2018 einzuführenden elektronischen Vergabe öffentlicher Aufträge. Der Übergang vom Papier zum Digitalen eröffnet Staat und Unternehmen viele Chancen zur Effektivität des Ausschreibungsprozesses und birgt zugleich Risiken. Mit dem entsprechenden rechtlichen, technischen und organisatorischen Know-how lässt sich die E-Vergabe aber gezielt als effizientes Einkaufsinstrument einsetzen. Hierfür setzt dieses essential erste Impulse und sorgt mit einem nahezu vollständigen Marktüberblick über die verfügbaren E-Vergabe-Standardlösungen für ein praxisnahes Verständnis bei Entscheidern.Table of ContentsNeuer Rechtsrahmen der E-Vergabe.- Strategische Aspekte für Vergabestellen, praxisrelevante Hürden für Bieter.- XVergabe als Standard für die E-Vergabe.- Marktüberblick über E-Vergabe-Lösungen.

    1 in stock

    £11.77

  • Abrechnung und Bezahlung von Bauleistungen:

    Springer Fachmedien Wiesbaden Abrechnung und Bezahlung von Bauleistungen:

    1 in stock

    Book SynopsisAndreas Schmidt gibt praktische Hilfestellung für die zeitnahe Realisierung und Absicherung von Vergütungsansprüchen. Dies ist für Bauunternehmen eine wesentliche Voraussetzung für den Unternehmenserfolg, denn diese sind nach der gesetzlichen Konzeption des Werkvertragsrechts grundsätzlich vorleistungspflichtig – d.h. sie müssen das für die Leistungserbringung erforderliche Personal, Material und Gerät zunächst vorfinanzieren. Der Autor zeigt, wie der Bauunternehmer die Regelungen im BGB und in der VOB/B betreffend die Abrechnung seiner Leistung sachgemäß anwendet, um Zahlungsflüsse zu beschleunigen. Zudem erfährt der Unternehmer, wie er reagieren kann, wenn der Auftraggeber verspätet oder gar nicht zahlt und wie er seinen Vergütungsanspruch für den Insolvenzfall absichern kann. Table of ContentsAbrechnung und Zahlung der Vergütung.- Folgen verspäteter Zahlung.- Verjährung und Sicherung des Vergütungsanspruchs.

    1 in stock

    £11.77

  • Intelligente Vergabestrategien bei Großprojekten:

    Springer Fachmedien Wiesbaden Intelligente Vergabestrategien bei Großprojekten:

    Out of stock

    Book SynopsisDie Autoren untersuchen die Voraussetzungen für eine erfolgreiche Vergabestrategie bei Großprojekten. Zunächst analysieren sie die Risiken für die am Bau Beteiligten und stellen Varianten dar, wie Planungs- und Bauleistungen zu vergeben sind. Danach werden die Möglichkeiten und Grenzen von in jüngerer Zeit „in Mode gekommenen“ Vergabemodellen, insbesondere die Vergabe mit Garantiertem Maximalpreis bzw. die Beauftragung von Construction Managern, diskutiert. Hierauf und auf einer Analyse der typischen Struktur eines (großen) Bauprojekts aufbauend, wird ein Vergabemodell entwickelt, das einerseits den Risiken der Baubeteiligten Rechnung trägt, andererseits dem Bauherrn die erforderliche Flexibilität belässt. So kann er in einem kompetitiven Umfeld ein seinen Vorstellungen bezüglich Kosten, Qualitäten und Terminen entsprechendes Bauvorhaben realisieren.Table of ContentsRisiken der Vergabemodelle.- Projektstrukturen als Grundlage der Vergabestrategie.- Beispiele zur erfolgreichen Projektabwicklung.

    Out of stock

    £999.99

  • Handkommentar zur VOB: VOB Teile A und B, VSVgV,

    Springer Fachmedien Wiesbaden Handkommentar zur VOB: VOB Teile A und B, VSVgV,

    Book SynopsisDer Schwerpunkt dieser überarbeiteten Kommentierung der VOB, Ausgabe 2016, liegt in der Umsetzung der Vergaberechtsreform 2016. Hieraus folgend wurden der Abschnitt 2 der VOB/A sowie der 4. Teil des GWB (Gesetz gegen Wettbewerbsbeschränkungen) und die übergreifend geltenden Regelungen der VgV (Vergabeverordnung) entsprechend neu kommentiert.Im Teil B wurden insbesondere die Änderungen der Kündigungsregelungen und das bevorstehende neue Bauvertragsrecht des BGB berücksichtigt.Kompetenz und Praxisnähe – die Vorzüge der vorherigen Auflagen, die den Erfolg des Werkes ausmachen, zeichnen auch diese Neubearbeitung aus.Trade Review“… Gezielt angesprochen werden sollen mit diesem Handkommentar vor allem Rechtsanwälte, Bauunternehmer, öffentliche und private Auftraggeber, Bauverwaltungen, Richter, Justitiare und Syndizi. Gekonnt vereint der Handkommentar auch in der 14. Auflage wieder einmal Kompetenz und Praxisnähe und ist durch seine prägnanten, klaren und verständlichen Aussagen besonders für Praktiker zu empfehlen.” (Rechtsanwältin A. Kullack, in: ZfBR - Zeitschrift für deutsches und internationales Bau- und Vergaberecht, Jg. 43, Heft 7, 2020) “... stellt das Werk eine lohnende Anschaffung für alle im Kontext Vergaberecht tätigen Praktiker der unterschiedlichen Fachdisziplinen dar.” (Architekten- u. Stadtplanerkammer Hessen, akh.de, 8. August 2019) “... Ausweislich des Vorworts ist Ziel des Kommentars, nicht nur Juristen, sondern auch Baupraktikern verständliche und nachvollziehbare Hilfestellungen zu geben. Dazu tragen der Aufbau und der Inhalt der Kommentierungen maßgeblich bei. ... ein empfehlenswertes Standardwerk für alle Berufsgruppen, die sich mit Vergaberecht beschäftigen.” (Ministerialrätin Dr. Irene Lausen, in: Staatsanzeiger für das Land Hessen, Heft 8, 19. Februar 2018)Table of ContentsVorbemerkungen zur VOB/A 2016.- Wortlaut und Kommentar VOB/A mit Erläuterungen zur Vergabverordnung (VgV).- Erläuterungen zur Verordnung Verteidigung und Sicherheit (VSVgV).- Vorbemerkungen zur VOB/B 2016.- Wortlaut und Kommentar VOB/B.- Rechtsschutz im Vergabeverfahren: Wortlaut und Kommentar GWB 4. Abschnitt.

    £151.99

  • Vergabepraxis für Auftraggeber: Rechtliche

    Springer Fachmedien Wiesbaden Vergabepraxis für Auftraggeber: Rechtliche

    1 in stock

    Book SynopsisAusschreibungs- und Vergabeverfahren von Bauleistungen bergen auch für den ausschreibenden Planer viele Tücken und Fallstricke. Dieses Praxisbuch erklärt die Verfahren und die Vorgehensweisen Schritt für Schritt und stellt anschaulich die Bezüge zu den relevanten Gesetzen und Verordnungen her (VOB/A und HOAI). Ein gut strukturierter Leitfaden für die fehlerfreie und regelkonforme Durchführung von Ausschreibung und Vergabe unter Berücksichtigung der VOB 2009.Table of ContentsEinleitung - Rechtliche Grundlagen - Vergaberecht - Recht für Architekten und Ingenieure - National oder Europäisch - Öffentliche Auftraggeber - Vorbereitung der Vergabe - Aufstellen von Leistungsbeschreibungen - Produktneutralität - Abstimmen und Koordinieren von Leistungsbeschreibungen - Mitwirkung bei der Vergabe - Zusammenstellen der Vergabe- und Vertragsunterlagen - Einholen von Angeboten - Aufklärungsgespräche - Prüfen und Werten der Angebote - Ausschluss von Angeboten - Eignungsprüfung - Erstellen Preisspiegel nach Teilleistungen - Abstimmen und Zusammenstellen der Leistungen - Verhandlung mit Bietern - Mitwirken bei der Auftragserteilung

    1 in stock

    £49.49

  • Der Architektenvertrag: Schnelleinstieg für

    Springer Fachmedien Wiesbaden Der Architektenvertrag: Schnelleinstieg für

    1 in stock

    Book SynopsisHendrik Hunold gibt einen konzentrierten Überblick über die Besonderheiten des Architektenrechts anhand des typischen Aufbaus eines Architektenvertrags. Leicht verständliche Beispiele, Tipps, Formulierungsbeispiele, Übersichten und Schaubilder helfen bei der täglichen Umsetzung. Der Leser bekommt so die für seine Praxis bedeutsamen rechtlichen Grundkenntnisse vermittelt, über zahlreiche Literatur- und aktuelle Rechtsprechungshinweise kann das Wissen bei Bedarf schnell vertieft werden. Das essential dient damit nicht nur der Vermittlung des täglich notwendigen Praxiswissens, sondern kann auch als gezieltes Nachschlagewerk und als Begleiter für die Verhandlung von Architektenverträgen dienen. Table of ContentsAbschluss des Architektenvertrags.- Welche Leistung muss ich erbringen? Und wie setze ich mein Honorar durch?.- Für was hafte ich unter welchen Voraussetzungen? Meine Haftpflichtversicherung.

    1 in stock

    £11.77

  • Kosteneinsparpotenziale einer effizienteren

    Springer Fachmedien Wiesbaden Kosteneinsparpotenziale einer effizienteren

    1 in stock

    Book SynopsisMichael Schleich zeigt die aus dem Vergleich mit der englischen Bauverordnung abzuleitenden Optimierungen der Landesbauordnung NRW auf. Sein Ziel ist es, aus dem Vergleich der Effizienz dieser Bauordnungen Kosteneinsparpotenziale abzuleiten. Zu diesem Zweck wendet der Autor die Methode der ökonomischen Analyse des Rechts bzw. der Kosten-Nutzwert-Analyse und der Transaktionskostenanalyse an. Anhand dreier Fallstudien von Wohngebäuden untersucht er empirisch, welche der beiden Bauordnungen unter welchem Aspekt effizienter ist.Table of ContentsStand der Forschung und Auswahl der Bauordnungen.- Rechtsvergleichung der Bauordnungen und Vergleich ihrer rechtshistorischen Entwicklung.- Ökonomische Analyse der Bauordnungen.- Vergleich der Brandschutzvorschriften (Kosten-Nutzwert-Analyse) und der Verfahrensvorschriften (Transaktionskostenanalyse).

    1 in stock

    £49.49

  • Der Ingenieurvertrag: Schnelleinstieg für

    Springer Fachmedien Wiesbaden Der Ingenieurvertrag: Schnelleinstieg für

    1 in stock

    Book SynopsisHendrik Hunold gibt einen rechtlich konzentrierten Überblick über die Besonderheiten des Ingenieurvertrags anhand leicht verständlicher Beispiele. Tipps, Formulierungshinweise. Übersichten und Schaubilder helfen bei der täglichen Umsetzung. Der Leser bekommt so die für seine Praxis bedeutsamen rechtlichen Grundkenntnisse vermittelt – über zahlreiche Literatur- und aktuelle Rechtsprechungshinweise kann das Wissen bei Bedarf schnell vertieft werden. Die „BGB-Baurechtsreform“ bis zum 01.01.2018 wurde vollständig berücksichtigt. Das essential dient damit nicht nur der Vermittlung des täglich notwendigen Praxiswissens, sondern kann auch gezielt als Nachschlagewerk und als Begleiter für die Verhandlung von Ingenieurverträgen eingesetzt werden. Der AutorDr. Hendrik Hunold ist seit seinem Berufseinstieg auf das private Baurecht, v.a. das Ingenieur-, Architekten-, Vergabe- und Immobilienrecht spezialisiert.Table of ContentsVorteilhafte Verträge und Konfliktvermeidung.- Grenzen der Vertragsgestaltung.- Form, Grundlagen und Inhalte des Ingenieurvertrags.

    1 in stock

    £11.77

  • Vorbereitung und Durchführung von Bauabnahmen:

    Springer Fachmedien Wiesbaden Vorbereitung und Durchführung von Bauabnahmen:

    1 in stock

    Book SynopsisDie fachgerechte und ordnungsgemäße Abnahme von Bauleistungen und Gebäuden ist für alle an Bauabnahmen Beteiligten im Bereich der Objektüberwachung komplex und birgt viele Fallstricke. Der Autor beschreibt, was bei der organisatorischen, technischen und rechtlichen Vorbereitung von Abnahmen zu beachten und was bei Störungen der Bauabnahme durch auftretende Mängel zu tun ist. Er informiert darüber, welche Dokumente, Qualitätsnachweise und Erklärungen bei der Abnahme erforderlich sind. Übersichten, Checklisten und Musterformulare runden den Schnelleinstieg in die Thematik ab.Der AutorDipl.-Ing., Dipl.-Ing.-Ök. Konrad Micksch arbeitete viele Jahre als Projekt- und Oberbauleiter im schlüsselfertigen Bahn-, Brücken-, Sport-, Gesellschafts- und Anlagenbau im In- und Ausland.Table of ContentsVorbereitung der Abnahme und Mängel.- Abnahmedurchführung und Abnahmeprotokoll.- Wirkungen der Abnahme.- Checklisten und Abnahmemuster.

    1 in stock

    £11.77

  • VOB/A 2019 - Textausgabe/Text Edition: Vergabe-

    Springer Fachmedien Wiesbaden VOB/A 2019 - Textausgabe/Text Edition: Vergabe-

    1 in stock

    Book SynopsisDiese zweisprachige Ausgabe der aktuellen VOB/A erleichtert den Dialog bei der Auftragsvergabe. Das Interesse an den Inhalten der VOB ist auch im Ausland groß. In den meisten Ländern gibt es keine vergleichbare Verordnung, um Aufträge zu vergeben, solide Bauverträge abzuschließen und verlässliche bauvertragliche Abmachungen zu vereinbaren. Table of ContentsWortlaut der VOB/A Ausgabe 2019 auf Deutsch.- Wortlaut der VOB/A Ausgabe 2019 auf Englisch.

    1 in stock

    £44.99

© 2026 Book Curl

    • American Express
    • Apple Pay
    • Diners Club
    • Discover
    • Google Pay
    • Maestro
    • Mastercard
    • PayPal
    • Shop Pay
    • Union Pay
    • Visa

    Login

    Forgot your password?

    Don't have an account yet?
    Create account