Description

Book Synopsis

Addresses the daily challenges faced by contractors who use the NEC3 ECC with clear, practical and useable advice on how to solve them

Written in plain English for contractors and their staff, this book explains how the NEC3 contract works and provides answers to common questions. It presents complicated concepts in a simple, straightforward and understandable way, focusing mainly on day-to-day use. Steven Evans, an expert with thirty years of experience in construction, considers all the provisions of the contract and explains the procedures, obligations, and liabilities contained within it.

NEC3 ECC is a process-based contract based on project management best practices. The basic philosophy behind it differs radically from the more adversarial approaches embodied by traditional contracts. While the NEC3 ECC may appear quite simple on the surface, it is often misunderstood and mismanaged by its day-to-day users. Despite the clear and urgent need for expert guid

Table of Contents

About the Book xiii

About the Author xv

1 Introduction 1

Ten Things You Need to Know 1

Author’s Note 2

2 The Contract 5

About the NEC Contract 5

Clarity and Simplicity 5

Flexibility 5

Stimulus to Good Management 6

Collaborate…or Else! 6

The Latham Report 6

The NEC3 Suite 7

Contracts 7

Flow Charts and Guidance Notes 8

The ECC Form 9

The Core Clauses 9

The Main Options 9

Option A – Priced Contract with Activity Schedule 10

Option B – Priced Contract with Bill of Quantities 11

Option C – Target Contract with Activity Schedule 11

Option D – Target Contract with Bill of Quantities 12

Option E – Cost Reimbursable Contract 12

Option F – Management Contract 13

W Clauses 13

The Secondary Options 14

X Clauses 14

Y Clauses 14

Z Clauses 15

The Contract Data 15

The Schedules 16

The Schedule of Cost Components 16

The Shorter Schedule of Cost Components 16

Formation of the Contract 16

Offer and Acceptance 16

Attestation 17

Necessary Contract Documents 17

Frequently Asked Questions 17

3 General 19

Overview 19

Actions 19

The Employer 20

The Contractor 22

The Project Manager 27

Impartiality 32

The Supervisor 32

The Obligations 33

Identified and Defined Terms 34

(1) The Accepted Programme 35

(2) Completion 36

(3) Completion Date 38

(4) The Contract Date 38

(5) Defect 39

(6) Defects Certificate 39

(7) Equipment 40

(8) The Fee 40

(9) Key Date 41

(10) Others 42

(11) Parties 42

(12) Plant and Materials 42

(13) To Provide the Works 43

(14) The Risk Register 44

(15) The Site 44

(16) Site Information 45

(17) Subcontractor 45

(18) Working Areas 46

(19) Works Information 46

(20) The Activity Schedule (Main Options A and C Only) 49

Who Prepares the List of Activities? 49

What Should be Included in the Schedule? 50

Relationship to the Accepted Programme 50

Changes to the Activity Schedule 50

Use Under Option A 51

Use Under Option C 51

Errors in the Activity Schedule 51

(21) The Bill of Quantities (Main Options B and D Only) 52

Changes to the Bill of Quantities 53

Use Under Option B 53

Use Under Option D 53

Errors in the Bill of Quantities 54

(22) to (26) Defined Cost 54

Main Options A and B 54

Main Options C to E 54

Main Option F 55

(25) Disallowed Costs 55

(27) Price for Work Done to Date (Option A) 56

(28) Price for Work Done to Date (Option B) 56

(29) Price for Work Done to Date (Options C to F) 57

(30) Prices (Main Options A and C) 57

(31) Prices (Main Options B and D) 57

(32) Prices (Main Options E and F) 57

(33) The Total of the Prices (Option D) 57

Interpretation and the Law 57

Communications 58

Notification 59

The Project Manager and the Supervisor 60

Adding to the Working Areas 61

Early Warning 61

Ambiguities and Inconsistencies 63

Illegalities and Impossibilities 64

Prevention 64

Frequently Asked Questions 65

4 The Contractor’s Main Responsibilities 71

Overview 71

Providing the Works 77

The Contractor’s Design 78

Acceptance of the Contractor’s Design 78

Using the Contractor’s Design 79

Design of Equipment 79

People 80

Working With the Employer and Others 81

Subcontracting 82

Other Responsibilities 84

Frequently Asked Questions 85

5 Time 89

Overview 89

Starting, Completion and Key Dates 89

Commencement and Completion 89

Completion Certificate 90

Key Dates 91

The Programme 91

The First Programme 92

Information on the Programme 92

Acceptance of the Programme 95

Rejection of the Programme 95

Revising the Programme 96

Access to and Use of the Site 98

Instructions to Stop or Not to Start the Work 98

Takeover 98

Acceleration 99

Frequently Asked Questions 100

6 Testing and Defects 105

Overview 105

Tests and Inspections 106

Tests and Inspections Before Delivery 107

Searching For and Notifying Defects 107

Searching 107

Notifying 108

Correcting Defects 108

Correction 108

Defect Correction Period 108

Defects Certificate 109

Accepting Defects 109

Uncorrected Defects 110

Frequently Asked Questions 111

7 Payment 115

Overview 115

Assessing the Amount Due 115

Main Option A 116

Main Option B 117

Main Option C 117

Amounts Due to Subcontractors 118

The Cost of Components in the Schedule of Cost Components 119

Disallowed Costs 119

The Fee 120

Main Option D 120

Amounts Due to Subcontractors 121

The Cost of Components in the Schedule of Cost Components 121

Disallowed Costs 121

The Fee 122

Main Option E 122

Amounts Due to Subcontractors 123

The Cost of Components in the Schedule of Cost Components 124

Disallowed Costs 124

The Fee 125

Main Option F 125

Amounts Due to Subcontractors 126

The Prices for the Work Done by the Contractor 127

Disallowed Costs 127

The Fee 127

Unfixed Materials on Site 128

Main Option A 128

Main Option B 128

Main Options C, D and E 128

Main Option F 128

The First Programme 128

Payment 128

The Primary Legislation 129

The Secondary Legislation 129

How it Works 129

A ‘Construction Contract’ 129

The Payment Provisions 130

The Payment Notice 130

The ECC Provisions 131

Interest 132

Defined Cost 132

The Contractor’s Share 133

The Activity Schedule 134

The Bill of Quantities 135

Frequently Asked Questions 135

8 Compensation Events 139

Overview 139

Compensation Events 140

Core Clause Compensation Events 140

Weather Measurement 146

Weather Data 146

Once in Ten Years 146

Bill of Quantity Compensation Events 149

Secondary Option Compensation Events 150

Clause X2.1 – Changes in the Law 150

Clause X12.3(6) and (7) – Changes in Partnering Information 151

Clause X14.2 – Delay in Making Advanced Payment 151

Clause X15.2 – Correction of a Defect 151

Clause Y2.4 – Suspension Under the Housing Grants,

Construction and Regeneration Act 1996 151

Compensation Event Procedure 151

Notifying Compensation Events 151

Quotations for Compensation Events 154

Assessing Compensation Events 156

Effect of the Event on Defined Cost 157

Effect of the Event on Planned Completion 158

Failure to Give Early Warning 159

The Project Manager’s Assessment 159

Exhaustive Remedy 161

Implementing Compensation Events 161

Main Option Clauses 161

Summary of Sanctions 163

Other Remedies 164

Frequently Asked Questions 164

9 Title 169

Overview 169

The Employer’s Title to Plant and Materials 169

Marking Equipment, Plant and Materials Outside the

Working Areas 170

Removing Equipment 171

Objects and Materials within the Site 171

Frequently Asked Questions 171

10 Risks and Insurance 173

Overview 173

Employer’s Risks 173

Contractor’s Risks 174

Repairs 175

Indemnity 175

Insurance Cover 175

Insurance Policies 176

If the Contractor Does Not Insure 176

Insurance by the Employer 177

Frequently Asked Questions 177

11 Termination 179

Overview 179

Termination 179

Reasons for Termination 180

Procedures on Termination 181

Payment on Termination 181

Frequently Asked Questions 183

12 Dispute Resolution (W1 and W2 Adjudication) 185

Overview 185

Option W1 185

Dispute Resolution 185

The Adjudicator 186

The Adjudication 188

Review by a Tribunal 191

Option W2 192

Dispute Resolution 192

The Adjudicator 193

The Adjudication 196

Review by a Tribunal 199

Frequently Asked Questions 200

13 X and Y Clauses 203

Introduction 203

The X Clauses 203

X1 – Price Adjustment for Inflation 203

X2 – Changes in the Law 204

X3 – Multiple Currencies 204

X4 – Parent Company Guarantees 205

X5 – Sectional Completion 205

X6 – Bonus for Early Completion 205

X7 – Delay Damages 206

X12 – Partnering 206

X13 – Performance Bond 207

X14 – Advanced Payment to the Contractor 207

X15 – Limitation of Contractor’s Liability for his Design to Reasonable Skill and Care 207

X17 – Low Performance Damages 208

X18 – Limitation of Liability 208

X20 – Key Performance Indicators 209

The Y Clauses 209

Y(UK)1 – Project Bank Account 209

Overview 209

Definitions 210

Project Bank Account 210

Named Suppliers 210

Payments 211

Effect of Payment 211

Trust Deed 211

Termination 211

Y(UK)2 – Housing Grants, Construction and Regeneration Act 1996 212

Overview 212

Definitions 212

Dates for Payment 212

Notice of Intention to Pay Less 212

Suspension of Performance 212

Y(UK)3 – Contracts (Rights of Third Parties) Act 1999 213

Overview 213

Frequently Asked Questions 213

14 Z Clauses 215

Overview 215

Additional Conditions of Contract 215

Frequently Asked Questions 216

15 Schedules of Cost Components 219

Overview 219

Schedule of Cost Components 219

Subcontractors 220

People 220

Equipment 220

Plant and Materials 221

Charges 222

Manufacture and Fabrication 222

Design 222

Insurance 222

Shorter Schedule of Cost Components 223

Subcontractors 223

People 223

Equipment 224

Plant and Materials 225

Charges 225

Manufacture and Fabrication 225

Design 225

Insurance 226

Frequently Asked Questions 226

Index 229

The Contractors NEC3 ECC Handbook

    Product form

    £62.65

    Includes FREE delivery

    RRP £65.95 – you save £3.30 (5%)

    Order before 4pm today for delivery by Sat 27 Jun 2026.

    A Paperback / softback by Steven C. Evans

    1 in stock

      Trusted by thousands of customers. See 2,385+ Customer Reviews

      View other formats and editions of The Contractors NEC3 ECC Handbook by Steven C. Evans

      Publisher: John Wiley and Sons Ltd
      Publication Date: 25/08/2017
      ISBN13: 9781119137498, 978-1119137498
      ISBN10: 1119137497

      Description

      Book Synopsis

      Addresses the daily challenges faced by contractors who use the NEC3 ECC with clear, practical and useable advice on how to solve them

      Written in plain English for contractors and their staff, this book explains how the NEC3 contract works and provides answers to common questions. It presents complicated concepts in a simple, straightforward and understandable way, focusing mainly on day-to-day use. Steven Evans, an expert with thirty years of experience in construction, considers all the provisions of the contract and explains the procedures, obligations, and liabilities contained within it.

      NEC3 ECC is a process-based contract based on project management best practices. The basic philosophy behind it differs radically from the more adversarial approaches embodied by traditional contracts. While the NEC3 ECC may appear quite simple on the surface, it is often misunderstood and mismanaged by its day-to-day users. Despite the clear and urgent need for expert guid

      Table of Contents

      About the Book xiii

      About the Author xv

      1 Introduction 1

      Ten Things You Need to Know 1

      Author’s Note 2

      2 The Contract 5

      About the NEC Contract 5

      Clarity and Simplicity 5

      Flexibility 5

      Stimulus to Good Management 6

      Collaborate…or Else! 6

      The Latham Report 6

      The NEC3 Suite 7

      Contracts 7

      Flow Charts and Guidance Notes 8

      The ECC Form 9

      The Core Clauses 9

      The Main Options 9

      Option A – Priced Contract with Activity Schedule 10

      Option B – Priced Contract with Bill of Quantities 11

      Option C – Target Contract with Activity Schedule 11

      Option D – Target Contract with Bill of Quantities 12

      Option E – Cost Reimbursable Contract 12

      Option F – Management Contract 13

      W Clauses 13

      The Secondary Options 14

      X Clauses 14

      Y Clauses 14

      Z Clauses 15

      The Contract Data 15

      The Schedules 16

      The Schedule of Cost Components 16

      The Shorter Schedule of Cost Components 16

      Formation of the Contract 16

      Offer and Acceptance 16

      Attestation 17

      Necessary Contract Documents 17

      Frequently Asked Questions 17

      3 General 19

      Overview 19

      Actions 19

      The Employer 20

      The Contractor 22

      The Project Manager 27

      Impartiality 32

      The Supervisor 32

      The Obligations 33

      Identified and Defined Terms 34

      (1) The Accepted Programme 35

      (2) Completion 36

      (3) Completion Date 38

      (4) The Contract Date 38

      (5) Defect 39

      (6) Defects Certificate 39

      (7) Equipment 40

      (8) The Fee 40

      (9) Key Date 41

      (10) Others 42

      (11) Parties 42

      (12) Plant and Materials 42

      (13) To Provide the Works 43

      (14) The Risk Register 44

      (15) The Site 44

      (16) Site Information 45

      (17) Subcontractor 45

      (18) Working Areas 46

      (19) Works Information 46

      (20) The Activity Schedule (Main Options A and C Only) 49

      Who Prepares the List of Activities? 49

      What Should be Included in the Schedule? 50

      Relationship to the Accepted Programme 50

      Changes to the Activity Schedule 50

      Use Under Option A 51

      Use Under Option C 51

      Errors in the Activity Schedule 51

      (21) The Bill of Quantities (Main Options B and D Only) 52

      Changes to the Bill of Quantities 53

      Use Under Option B 53

      Use Under Option D 53

      Errors in the Bill of Quantities 54

      (22) to (26) Defined Cost 54

      Main Options A and B 54

      Main Options C to E 54

      Main Option F 55

      (25) Disallowed Costs 55

      (27) Price for Work Done to Date (Option A) 56

      (28) Price for Work Done to Date (Option B) 56

      (29) Price for Work Done to Date (Options C to F) 57

      (30) Prices (Main Options A and C) 57

      (31) Prices (Main Options B and D) 57

      (32) Prices (Main Options E and F) 57

      (33) The Total of the Prices (Option D) 57

      Interpretation and the Law 57

      Communications 58

      Notification 59

      The Project Manager and the Supervisor 60

      Adding to the Working Areas 61

      Early Warning 61

      Ambiguities and Inconsistencies 63

      Illegalities and Impossibilities 64

      Prevention 64

      Frequently Asked Questions 65

      4 The Contractor’s Main Responsibilities 71

      Overview 71

      Providing the Works 77

      The Contractor’s Design 78

      Acceptance of the Contractor’s Design 78

      Using the Contractor’s Design 79

      Design of Equipment 79

      People 80

      Working With the Employer and Others 81

      Subcontracting 82

      Other Responsibilities 84

      Frequently Asked Questions 85

      5 Time 89

      Overview 89

      Starting, Completion and Key Dates 89

      Commencement and Completion 89

      Completion Certificate 90

      Key Dates 91

      The Programme 91

      The First Programme 92

      Information on the Programme 92

      Acceptance of the Programme 95

      Rejection of the Programme 95

      Revising the Programme 96

      Access to and Use of the Site 98

      Instructions to Stop or Not to Start the Work 98

      Takeover 98

      Acceleration 99

      Frequently Asked Questions 100

      6 Testing and Defects 105

      Overview 105

      Tests and Inspections 106

      Tests and Inspections Before Delivery 107

      Searching For and Notifying Defects 107

      Searching 107

      Notifying 108

      Correcting Defects 108

      Correction 108

      Defect Correction Period 108

      Defects Certificate 109

      Accepting Defects 109

      Uncorrected Defects 110

      Frequently Asked Questions 111

      7 Payment 115

      Overview 115

      Assessing the Amount Due 115

      Main Option A 116

      Main Option B 117

      Main Option C 117

      Amounts Due to Subcontractors 118

      The Cost of Components in the Schedule of Cost Components 119

      Disallowed Costs 119

      The Fee 120

      Main Option D 120

      Amounts Due to Subcontractors 121

      The Cost of Components in the Schedule of Cost Components 121

      Disallowed Costs 121

      The Fee 122

      Main Option E 122

      Amounts Due to Subcontractors 123

      The Cost of Components in the Schedule of Cost Components 124

      Disallowed Costs 124

      The Fee 125

      Main Option F 125

      Amounts Due to Subcontractors 126

      The Prices for the Work Done by the Contractor 127

      Disallowed Costs 127

      The Fee 127

      Unfixed Materials on Site 128

      Main Option A 128

      Main Option B 128

      Main Options C, D and E 128

      Main Option F 128

      The First Programme 128

      Payment 128

      The Primary Legislation 129

      The Secondary Legislation 129

      How it Works 129

      A ‘Construction Contract’ 129

      The Payment Provisions 130

      The Payment Notice 130

      The ECC Provisions 131

      Interest 132

      Defined Cost 132

      The Contractor’s Share 133

      The Activity Schedule 134

      The Bill of Quantities 135

      Frequently Asked Questions 135

      8 Compensation Events 139

      Overview 139

      Compensation Events 140

      Core Clause Compensation Events 140

      Weather Measurement 146

      Weather Data 146

      Once in Ten Years 146

      Bill of Quantity Compensation Events 149

      Secondary Option Compensation Events 150

      Clause X2.1 – Changes in the Law 150

      Clause X12.3(6) and (7) – Changes in Partnering Information 151

      Clause X14.2 – Delay in Making Advanced Payment 151

      Clause X15.2 – Correction of a Defect 151

      Clause Y2.4 – Suspension Under the Housing Grants,

      Construction and Regeneration Act 1996 151

      Compensation Event Procedure 151

      Notifying Compensation Events 151

      Quotations for Compensation Events 154

      Assessing Compensation Events 156

      Effect of the Event on Defined Cost 157

      Effect of the Event on Planned Completion 158

      Failure to Give Early Warning 159

      The Project Manager’s Assessment 159

      Exhaustive Remedy 161

      Implementing Compensation Events 161

      Main Option Clauses 161

      Summary of Sanctions 163

      Other Remedies 164

      Frequently Asked Questions 164

      9 Title 169

      Overview 169

      The Employer’s Title to Plant and Materials 169

      Marking Equipment, Plant and Materials Outside the

      Working Areas 170

      Removing Equipment 171

      Objects and Materials within the Site 171

      Frequently Asked Questions 171

      10 Risks and Insurance 173

      Overview 173

      Employer’s Risks 173

      Contractor’s Risks 174

      Repairs 175

      Indemnity 175

      Insurance Cover 175

      Insurance Policies 176

      If the Contractor Does Not Insure 176

      Insurance by the Employer 177

      Frequently Asked Questions 177

      11 Termination 179

      Overview 179

      Termination 179

      Reasons for Termination 180

      Procedures on Termination 181

      Payment on Termination 181

      Frequently Asked Questions 183

      12 Dispute Resolution (W1 and W2 Adjudication) 185

      Overview 185

      Option W1 185

      Dispute Resolution 185

      The Adjudicator 186

      The Adjudication 188

      Review by a Tribunal 191

      Option W2 192

      Dispute Resolution 192

      The Adjudicator 193

      The Adjudication 196

      Review by a Tribunal 199

      Frequently Asked Questions 200

      13 X and Y Clauses 203

      Introduction 203

      The X Clauses 203

      X1 – Price Adjustment for Inflation 203

      X2 – Changes in the Law 204

      X3 – Multiple Currencies 204

      X4 – Parent Company Guarantees 205

      X5 – Sectional Completion 205

      X6 – Bonus for Early Completion 205

      X7 – Delay Damages 206

      X12 – Partnering 206

      X13 – Performance Bond 207

      X14 – Advanced Payment to the Contractor 207

      X15 – Limitation of Contractor’s Liability for his Design to Reasonable Skill and Care 207

      X17 – Low Performance Damages 208

      X18 – Limitation of Liability 208

      X20 – Key Performance Indicators 209

      The Y Clauses 209

      Y(UK)1 – Project Bank Account 209

      Overview 209

      Definitions 210

      Project Bank Account 210

      Named Suppliers 210

      Payments 211

      Effect of Payment 211

      Trust Deed 211

      Termination 211

      Y(UK)2 – Housing Grants, Construction and Regeneration Act 1996 212

      Overview 212

      Definitions 212

      Dates for Payment 212

      Notice of Intention to Pay Less 212

      Suspension of Performance 212

      Y(UK)3 – Contracts (Rights of Third Parties) Act 1999 213

      Overview 213

      Frequently Asked Questions 213

      14 Z Clauses 215

      Overview 215

      Additional Conditions of Contract 215

      Frequently Asked Questions 216

      15 Schedules of Cost Components 219

      Overview 219

      Schedule of Cost Components 219

      Subcontractors 220

      People 220

      Equipment 220

      Plant and Materials 221

      Charges 222

      Manufacture and Fabrication 222

      Design 222

      Insurance 222

      Shorter Schedule of Cost Components 223

      Subcontractors 223

      People 223

      Equipment 224

      Plant and Materials 225

      Charges 225

      Manufacture and Fabrication 225

      Design 225

      Insurance 226

      Frequently Asked Questions 226

      Index 229

      Recently viewed products

      © 2026 Book Curl

        • American Express
        • Apple Pay
        • Diners Club
        • Discover
        • Google Pay
        • Maestro
        • Mastercard
        • PayPal
        • Shop Pay
        • Union Pay
        • Visa

        Login

        Forgot your password?

        Don't have an account yet?
        Create account