Description

Book Synopsis
This key text for the building team is an authoritative guide and gives a detailed account of the team's roles and responsibilities, with best industry practice required to ensure that building projects meet clients' expectations on time, cost and quality.

Table of Contents

Part I Briefing The Project Team 1

1 The Project Team 3

Introduction 3

Parties to a building contract and their supporting teams 3

Rights, duties and responsibilities 4

The employer 5

The architect/contract administrator 5

The quantity surveyor 5

The principal designer 5

The clerk of works 6

The status of named consultants 6

Unnamed consultants with delegated powers 7

The project manager 7

The principal contractor 7

Sub-contractors 9

Statutory requirements 9

The CDM regulations 10

Avoiding disputes 12

Communications 12

2 Assessing the Needs 14

The structure 14

The strategic definition 14

Contribution to the initial project brief 16

The initial programme 17

The appointment 17

Appointment documents 19

Collateral warranties 20

3 Buildings as Assets 21

Buildings as assets as well as buildings 21

Single building or programme? 22

Buildings as solutions to business challenges? 23

Everyday solutions-based thinking 24

Summary 25

Part II Available Procurement Methods 27

4 Principles of Procurement 29

Simple theory – complex practice 29

The eternal triangle 29

Other considerations 32

The Construction (Design and Management) Regulations 2015 32

Risk 33

Accountability 33

Entering into the contract 33

Type of contract 34

Selection of the contractor – the tendering procedure 35

Establishing price and time 35

The dynamics of tendering 36

5 Basic Concepts 37

Economic use of resources 38

Labour 38

Materials 39

Plant 39

Capital 39

Contractor’s contribution to design and contract programme 40

Production cost savings 40

Continuity 41

Risk and accountability 41

Accountability 43

Summary 43

6 Accountability 45

Background 45

The modern concept of public accountability 46

Contract documentation 46

Proper price 47

Dispensing with competition 47

Inflation 47

Value for money 48

Summary 49

Contents vii

7 Value and Risk Management 50

Value management 50

Value articulation and project definition 52

Optimisation of benefits and costs 52

Learning lessons and performance optimisation 53

Risk management 54

Risk must be managed 54

Nothing ventured, nothing gained 55

Understanding the project 56

Risk management strategies 57

Allocating management actions 58

Value and risk are complementary 59

Similarities in the processes 63

The integrated process 63

8 Fixed Price and Cost Reimbursement 64

Fixed price 64

Cost reimbursement 65

Application to contract elements 65

Fluctuations 66

Target cost contracts 66

Use 67

The employer’s position 67

The contractor’s position 67

Programme 68

Summary 69

9 Fixed Price Contracts 70

JCT fixed price contracts 70

The standard building contract 71

Design and build contract 71

Major project construction contract 73

Intermediate building contract 74

Minor works building contract 75

Other fixed price contracts available 75

Advantages and disadvantages of fixed price contracts 76

Advantages 76

Disadvantages 76

10 Cost Reimbursement Contracts 77

The fee 77

The prime cost building contract 78

Characteristics of the form 78

Advantages and disadvantages of cost reimbursement contracts 79

Advantages 79

Disadvantages 80

Budget and cost control 80

Administering the contract 80

Procedure for keeping prime costs 81

Contractor’s site staff and direct workforce 81

Materials 82

Plant 82

Credits 82

Sub-letting 83

Defective work 83

Cost control 83

Final account 84

11 Target Cost Contracts 85

Guaranteed maximum price contracts 87

Competition 88

Contract 88

Advantages and disadvantages 89

Use 89

12 Management and Construction Management Contracts 90

Payment and cost control 90

Selection and appointment of the contractor 92

Contract conditions 93

Contract administration 94

Professional advisers 94

Advantages and disadvantages 95

Advantages 95

Disadvantages 95

Construction management 96

Use 97

Programme 97

13 Design and Build Contracts 99

The contract 100

Where to use DB (and when not to do so) 101

Managing the design process 102

Novation 103

Evaluation of submissions 104

Post-contract administration 104

Financial administration 104

Programme 105

Advantages and disadvantages 106

Advantages 106

Disadvantages 106

14 Continuity Contracts 107

Serial contracting 108

Purpose and use 109

Operation 109

Continuation contracts 110

Purpose and use 110

Operation 111

Term contracts 112

Purpose and use 112

JCT Measured Term Contract 113

Operation 113

15 Partnering 115

A definition 115

When to adopt a partnering approach 117

The agreement 117

JCT Partnering Charter 118

JCT Framework Agreement 118

JCT constructing excellence 119

The partnering workshop 119

The benefits 119

The risks 120

Future of partnering 121

16 EU Procurement 122

Introduction 122

The scope of procurement law 123

The general principles 123

Procedures 124

Key principles 124

Evaluating tenderers 124

Evaluating tenders 125

Framework agreements 126

Contract change 127

Cancellation of the process 127

Information obligations debrief and disclosure 127

Commencing proceedings 128

Remedies 128

Complaints to the EU commission and other challenge procedures 129

Tendering contracts 130

Notes 130

Part III Preparing For And Inviting Tenders 131

17 Procedure from Brief to Tender 133

Initial brief 133

Developing the brief 133

Feasibility stage 134

Sketch scheme 134

Costs 135

Procurement 135

Detailed design 136

Programming 137

Design team meetings 138

Drawings 138

Specifications 139

Bills of quantities 140

Specialist sub-contractors and suppliers 140

Quality assurance 140

Obtaining tenders 141

18 Pre-Contract Cost Control 142

Introduction 142

The purpose of pre-contract cost control 142

Framework for pre-contract estimating 143

Order of cost estimate 145

Information used to prepare an order of cost estimate 146

Treatment of on-costs and other costs in order of cost estimates 147

Presenting an order of cost estimate 148

Cost plans 149

Treatment of on-costs and other costs in cost plans 151

Presenting a cost plan 153

Challenges associated with the production of cost plans 155

Cash flow 155

Whole life costs 156

Summary 158

Notes 158

19 Drawings and Schedules 159

The language of drawing 159

The changing role of drawings and documents 159

Quality 162

Standards 162

Quality manuals 162

Quality procedure codes 163

Quality review 164

Types, sizes and layout of drawings 164

Size 165

Layout and revision 165

Scale 166

Nature and sequence of drawing production 167

RIBA Plan of Work 2013 167

Drawings for SBC contracts 167

Drawings for design and build or management contracts 168

Design intent information 169

Computer aided design 170

Drawing file formats and translation 171

Project extranets 171

Contents of drawings 174

Survey plan 174

Site plan, layout and drainage 175

General arrangement 175

Elevations of all parts of the building 177

Descriptive sections 177

Ceiling plans at all floor levels 177

Construction details (scale 1 : 20 and 1 : 10) 177

Large-scale details (scale 1 : 10 and 1 : 15) 178

Schedules 178

Drawings and schedules for records 179

Notes 184

20 Specifications 185

The use of specifications 185

Specifying by prescription 187

Specifying by performance 187

Specifying by description 187

Specification writing 188

Decide on format 188

Collect information 194

Input information 194

Check and test 195

Deliver 195

BIM 196

21 Building Information Modelling 197

The BIM revolution – what is BIM, and who/what is it for? 197

The role of government and its BIM strategy 199

The levels of BIM adoption 202

The BIM journey 203

Plan of work, deliverables and work stages 203

Loading the model: language and libraries 205

Bringing different software programmes together – the search for interoperability 206

Operation and maintenance 207

Terms of appointment and changes to other business practices 208

Level 3 and the future 209

Epilogue 209

Notes 210

22 Bills of Quantities 211

Tender and contract document 211

The wider role 211

Basic information 212

Preliminaries 212

Preambles 213

Measured works 213

Formats 214

23 Sub-contractors 220

Introduction 220

Specialist sub-contractors 221

Design by the sub-contractor 221

The SBC and sub-contract agreements 222

SBC provisions under the main contract 223

24 Obtaining Tenders 224

Introduction 224

Tender list 225

Preliminary enquiry 226

Tender documents and invitation 226

Tender period 227

Tender compliance 227

Late tenders 228

Opening tenders 228

Examination and adjustment of the priced document 228

Negotiated reduction of a tender 229

Notification of results 229

Tender analysis 230

E-Tendering 230

Part IV Contract Administration 231

25 Placing the Contract 233

Preparing and signing the contract documents 233

Sectional completion 234

Contractor’s designed portion 234

Executing the contract 235

Performance bonds and parent company guarantees 236

Collateral warranties 236

Third party rights 240

Issue of documents 241

Insurances 242

26 Meetings 245

Initial meeting 245

Introductions 246

Factors affecting the carrying out of the works 246

Programme 247

Sub-contractors and suppliers 248

Lines of communication 248

Financial matters 248

Procedure to be followed at subsequent meetings 250

Contractor’s meetings 251

Employer’s meetings 251

27 Site Duties 256

The architect on site 256

The architect’s duty of inspection and supervision 258

Supervision and Inspection duties 258

Routine site visits 259

Consultants’ site visits 260

Inspections by statutory officials 260

Records and reports 261

Samples and testing 262

Considerate constructors scheme 263

Site safety 264

Health and Safety Policy 264

Fire precautions on site 267

Regulatory control 268

The Joint Fire Code 268

Means of escape 269

Fire-fighting equipment 270

Emergency plans 270

Providing information 270

28 Instructions 277

Architect/contract administrator’s instructions 277

Clerk of works’ directions 279

Format and distribution of instructions 279

29 Variations and Post-Contract Cost Control 281

Variations 281

Valuing variations 282

Dayworks 286

Cost control 287

30 Interim Payments 290

Introduction 290

Payments of pre-determined amounts at regular intervals 292

Pre-determined payments at pre-determined stages 293

Regular payments by detailed valuation 293

Certificates and payments under the SBC 293

The architect/contract administrator 293

The quantity surveyor 294

The employer 294

The contractor 295

Interim certificates under the SBC 296

Unfixed materials and goods on site 298

Unfixed materials and goods off site 298

Retention under the SBC 299

Payments to sub-contractors under the SBC 299

Value added tax 299

Valuation and certificate forms 300

31 Completion, Defects and the Final Account 304

Practical completion 304

Partial possession 307

Possession of the building 307

Defects and making good 308

Final account 309

Adjustment of the contract sum 309

Practical considerations 311

Final certificate 312

32 Delays and Disputes 316

Introduction 316

Delays caused by the contractor 317

Delays caused by the employer or his representatives 317

Delays caused by events outside the control of either party 318

Force majeure 319

Exceptionally adverse weather conditions 319

SBC procedure in the event of delay 320

Best endeavours 320

Notification of delay 321

New completion dates 321

Final adjustment 322

Duties and decisions 322

Reimbursement of loss and/or expense under the SBC 323

Liquidated damages 324

Disputes and dispute resolution 325

Mediation 326

Adjudication 326

Arbitration 330

Litigation 332

33 An Introduction to Sustainability in Construction 335

Sustainable development 335

Key concepts 335

The importance of the environment and the importance of energy 336

Sustainability in the built environment 336

The regulatory framework for construction 337

European Union developments 337

UK regulatory and policy developments 338

Assessing the sustainability of construction and buildings 340

UK building environmental assessment schemes and standards 341

International building environmental assessment schemes and standards 342

Author’s comment 343

Sustainable procurement 344

Key concepts 344

Guidance and standards 345

Other important issues 346

References 346

34 Future Trends 349

Global -v- local 349

Industry and corporate trends 351

Opportunities and challenges 352

BIM 352

Lean process and procedures 353

Knowledge management 353

Behaviours 354

Index 357

The Aqua Group Guide to Procurement Tendering and

    Product form

    £37.95

    Includes FREE delivery

    RRP £39.95 – you save £2.00 (5%)

    Order before 4pm tomorrow for delivery by Tue 7 Jul 2026.

    A Paperback / softback by Mark Hackett, Gary Statham

      Trusted by thousands of customers. See 2,385+ Customer Reviews

      View other formats and editions of The Aqua Group Guide to Procurement Tendering and by Mark Hackett

      Publisher: John Wiley and Sons Ltd
      Publication Date: 15/04/2016
      ISBN13: 9781118346549, 978-1118346549
      ISBN10: 1118346548

      Description

      Book Synopsis
      This key text for the building team is an authoritative guide and gives a detailed account of the team's roles and responsibilities, with best industry practice required to ensure that building projects meet clients' expectations on time, cost and quality.

      Table of Contents

      Part I Briefing The Project Team 1

      1 The Project Team 3

      Introduction 3

      Parties to a building contract and their supporting teams 3

      Rights, duties and responsibilities 4

      The employer 5

      The architect/contract administrator 5

      The quantity surveyor 5

      The principal designer 5

      The clerk of works 6

      The status of named consultants 6

      Unnamed consultants with delegated powers 7

      The project manager 7

      The principal contractor 7

      Sub-contractors 9

      Statutory requirements 9

      The CDM regulations 10

      Avoiding disputes 12

      Communications 12

      2 Assessing the Needs 14

      The structure 14

      The strategic definition 14

      Contribution to the initial project brief 16

      The initial programme 17

      The appointment 17

      Appointment documents 19

      Collateral warranties 20

      3 Buildings as Assets 21

      Buildings as assets as well as buildings 21

      Single building or programme? 22

      Buildings as solutions to business challenges? 23

      Everyday solutions-based thinking 24

      Summary 25

      Part II Available Procurement Methods 27

      4 Principles of Procurement 29

      Simple theory – complex practice 29

      The eternal triangle 29

      Other considerations 32

      The Construction (Design and Management) Regulations 2015 32

      Risk 33

      Accountability 33

      Entering into the contract 33

      Type of contract 34

      Selection of the contractor – the tendering procedure 35

      Establishing price and time 35

      The dynamics of tendering 36

      5 Basic Concepts 37

      Economic use of resources 38

      Labour 38

      Materials 39

      Plant 39

      Capital 39

      Contractor’s contribution to design and contract programme 40

      Production cost savings 40

      Continuity 41

      Risk and accountability 41

      Accountability 43

      Summary 43

      6 Accountability 45

      Background 45

      The modern concept of public accountability 46

      Contract documentation 46

      Proper price 47

      Dispensing with competition 47

      Inflation 47

      Value for money 48

      Summary 49

      Contents vii

      7 Value and Risk Management 50

      Value management 50

      Value articulation and project definition 52

      Optimisation of benefits and costs 52

      Learning lessons and performance optimisation 53

      Risk management 54

      Risk must be managed 54

      Nothing ventured, nothing gained 55

      Understanding the project 56

      Risk management strategies 57

      Allocating management actions 58

      Value and risk are complementary 59

      Similarities in the processes 63

      The integrated process 63

      8 Fixed Price and Cost Reimbursement 64

      Fixed price 64

      Cost reimbursement 65

      Application to contract elements 65

      Fluctuations 66

      Target cost contracts 66

      Use 67

      The employer’s position 67

      The contractor’s position 67

      Programme 68

      Summary 69

      9 Fixed Price Contracts 70

      JCT fixed price contracts 70

      The standard building contract 71

      Design and build contract 71

      Major project construction contract 73

      Intermediate building contract 74

      Minor works building contract 75

      Other fixed price contracts available 75

      Advantages and disadvantages of fixed price contracts 76

      Advantages 76

      Disadvantages 76

      10 Cost Reimbursement Contracts 77

      The fee 77

      The prime cost building contract 78

      Characteristics of the form 78

      Advantages and disadvantages of cost reimbursement contracts 79

      Advantages 79

      Disadvantages 80

      Budget and cost control 80

      Administering the contract 80

      Procedure for keeping prime costs 81

      Contractor’s site staff and direct workforce 81

      Materials 82

      Plant 82

      Credits 82

      Sub-letting 83

      Defective work 83

      Cost control 83

      Final account 84

      11 Target Cost Contracts 85

      Guaranteed maximum price contracts 87

      Competition 88

      Contract 88

      Advantages and disadvantages 89

      Use 89

      12 Management and Construction Management Contracts 90

      Payment and cost control 90

      Selection and appointment of the contractor 92

      Contract conditions 93

      Contract administration 94

      Professional advisers 94

      Advantages and disadvantages 95

      Advantages 95

      Disadvantages 95

      Construction management 96

      Use 97

      Programme 97

      13 Design and Build Contracts 99

      The contract 100

      Where to use DB (and when not to do so) 101

      Managing the design process 102

      Novation 103

      Evaluation of submissions 104

      Post-contract administration 104

      Financial administration 104

      Programme 105

      Advantages and disadvantages 106

      Advantages 106

      Disadvantages 106

      14 Continuity Contracts 107

      Serial contracting 108

      Purpose and use 109

      Operation 109

      Continuation contracts 110

      Purpose and use 110

      Operation 111

      Term contracts 112

      Purpose and use 112

      JCT Measured Term Contract 113

      Operation 113

      15 Partnering 115

      A definition 115

      When to adopt a partnering approach 117

      The agreement 117

      JCT Partnering Charter 118

      JCT Framework Agreement 118

      JCT constructing excellence 119

      The partnering workshop 119

      The benefits 119

      The risks 120

      Future of partnering 121

      16 EU Procurement 122

      Introduction 122

      The scope of procurement law 123

      The general principles 123

      Procedures 124

      Key principles 124

      Evaluating tenderers 124

      Evaluating tenders 125

      Framework agreements 126

      Contract change 127

      Cancellation of the process 127

      Information obligations debrief and disclosure 127

      Commencing proceedings 128

      Remedies 128

      Complaints to the EU commission and other challenge procedures 129

      Tendering contracts 130

      Notes 130

      Part III Preparing For And Inviting Tenders 131

      17 Procedure from Brief to Tender 133

      Initial brief 133

      Developing the brief 133

      Feasibility stage 134

      Sketch scheme 134

      Costs 135

      Procurement 135

      Detailed design 136

      Programming 137

      Design team meetings 138

      Drawings 138

      Specifications 139

      Bills of quantities 140

      Specialist sub-contractors and suppliers 140

      Quality assurance 140

      Obtaining tenders 141

      18 Pre-Contract Cost Control 142

      Introduction 142

      The purpose of pre-contract cost control 142

      Framework for pre-contract estimating 143

      Order of cost estimate 145

      Information used to prepare an order of cost estimate 146

      Treatment of on-costs and other costs in order of cost estimates 147

      Presenting an order of cost estimate 148

      Cost plans 149

      Treatment of on-costs and other costs in cost plans 151

      Presenting a cost plan 153

      Challenges associated with the production of cost plans 155

      Cash flow 155

      Whole life costs 156

      Summary 158

      Notes 158

      19 Drawings and Schedules 159

      The language of drawing 159

      The changing role of drawings and documents 159

      Quality 162

      Standards 162

      Quality manuals 162

      Quality procedure codes 163

      Quality review 164

      Types, sizes and layout of drawings 164

      Size 165

      Layout and revision 165

      Scale 166

      Nature and sequence of drawing production 167

      RIBA Plan of Work 2013 167

      Drawings for SBC contracts 167

      Drawings for design and build or management contracts 168

      Design intent information 169

      Computer aided design 170

      Drawing file formats and translation 171

      Project extranets 171

      Contents of drawings 174

      Survey plan 174

      Site plan, layout and drainage 175

      General arrangement 175

      Elevations of all parts of the building 177

      Descriptive sections 177

      Ceiling plans at all floor levels 177

      Construction details (scale 1 : 20 and 1 : 10) 177

      Large-scale details (scale 1 : 10 and 1 : 15) 178

      Schedules 178

      Drawings and schedules for records 179

      Notes 184

      20 Specifications 185

      The use of specifications 185

      Specifying by prescription 187

      Specifying by performance 187

      Specifying by description 187

      Specification writing 188

      Decide on format 188

      Collect information 194

      Input information 194

      Check and test 195

      Deliver 195

      BIM 196

      21 Building Information Modelling 197

      The BIM revolution – what is BIM, and who/what is it for? 197

      The role of government and its BIM strategy 199

      The levels of BIM adoption 202

      The BIM journey 203

      Plan of work, deliverables and work stages 203

      Loading the model: language and libraries 205

      Bringing different software programmes together – the search for interoperability 206

      Operation and maintenance 207

      Terms of appointment and changes to other business practices 208

      Level 3 and the future 209

      Epilogue 209

      Notes 210

      22 Bills of Quantities 211

      Tender and contract document 211

      The wider role 211

      Basic information 212

      Preliminaries 212

      Preambles 213

      Measured works 213

      Formats 214

      23 Sub-contractors 220

      Introduction 220

      Specialist sub-contractors 221

      Design by the sub-contractor 221

      The SBC and sub-contract agreements 222

      SBC provisions under the main contract 223

      24 Obtaining Tenders 224

      Introduction 224

      Tender list 225

      Preliminary enquiry 226

      Tender documents and invitation 226

      Tender period 227

      Tender compliance 227

      Late tenders 228

      Opening tenders 228

      Examination and adjustment of the priced document 228

      Negotiated reduction of a tender 229

      Notification of results 229

      Tender analysis 230

      E-Tendering 230

      Part IV Contract Administration 231

      25 Placing the Contract 233

      Preparing and signing the contract documents 233

      Sectional completion 234

      Contractor’s designed portion 234

      Executing the contract 235

      Performance bonds and parent company guarantees 236

      Collateral warranties 236

      Third party rights 240

      Issue of documents 241

      Insurances 242

      26 Meetings 245

      Initial meeting 245

      Introductions 246

      Factors affecting the carrying out of the works 246

      Programme 247

      Sub-contractors and suppliers 248

      Lines of communication 248

      Financial matters 248

      Procedure to be followed at subsequent meetings 250

      Contractor’s meetings 251

      Employer’s meetings 251

      27 Site Duties 256

      The architect on site 256

      The architect’s duty of inspection and supervision 258

      Supervision and Inspection duties 258

      Routine site visits 259

      Consultants’ site visits 260

      Inspections by statutory officials 260

      Records and reports 261

      Samples and testing 262

      Considerate constructors scheme 263

      Site safety 264

      Health and Safety Policy 264

      Fire precautions on site 267

      Regulatory control 268

      The Joint Fire Code 268

      Means of escape 269

      Fire-fighting equipment 270

      Emergency plans 270

      Providing information 270

      28 Instructions 277

      Architect/contract administrator’s instructions 277

      Clerk of works’ directions 279

      Format and distribution of instructions 279

      29 Variations and Post-Contract Cost Control 281

      Variations 281

      Valuing variations 282

      Dayworks 286

      Cost control 287

      30 Interim Payments 290

      Introduction 290

      Payments of pre-determined amounts at regular intervals 292

      Pre-determined payments at pre-determined stages 293

      Regular payments by detailed valuation 293

      Certificates and payments under the SBC 293

      The architect/contract administrator 293

      The quantity surveyor 294

      The employer 294

      The contractor 295

      Interim certificates under the SBC 296

      Unfixed materials and goods on site 298

      Unfixed materials and goods off site 298

      Retention under the SBC 299

      Payments to sub-contractors under the SBC 299

      Value added tax 299

      Valuation and certificate forms 300

      31 Completion, Defects and the Final Account 304

      Practical completion 304

      Partial possession 307

      Possession of the building 307

      Defects and making good 308

      Final account 309

      Adjustment of the contract sum 309

      Practical considerations 311

      Final certificate 312

      32 Delays and Disputes 316

      Introduction 316

      Delays caused by the contractor 317

      Delays caused by the employer or his representatives 317

      Delays caused by events outside the control of either party 318

      Force majeure 319

      Exceptionally adverse weather conditions 319

      SBC procedure in the event of delay 320

      Best endeavours 320

      Notification of delay 321

      New completion dates 321

      Final adjustment 322

      Duties and decisions 322

      Reimbursement of loss and/or expense under the SBC 323

      Liquidated damages 324

      Disputes and dispute resolution 325

      Mediation 326

      Adjudication 326

      Arbitration 330

      Litigation 332

      33 An Introduction to Sustainability in Construction 335

      Sustainable development 335

      Key concepts 335

      The importance of the environment and the importance of energy 336

      Sustainability in the built environment 336

      The regulatory framework for construction 337

      European Union developments 337

      UK regulatory and policy developments 338

      Assessing the sustainability of construction and buildings 340

      UK building environmental assessment schemes and standards 341

      International building environmental assessment schemes and standards 342

      Author’s comment 343

      Sustainable procurement 344

      Key concepts 344

      Guidance and standards 345

      Other important issues 346

      References 346

      34 Future Trends 349

      Global -v- local 349

      Industry and corporate trends 351

      Opportunities and challenges 352

      BIM 352

      Lean process and procedures 353

      Knowledge management 353

      Behaviours 354

      Index 357

      Recently viewed products

      © 2026 Book Curl

        • American Express
        • Apple Pay
        • Diners Club
        • Discover
        • Google Pay
        • Maestro
        • Mastercard
        • PayPal
        • Shop Pay
        • Union Pay
        • Visa

        Login

        Forgot your password?

        Don't have an account yet?
        Create account