Description

Book Synopsis
The authoritative industry guide on good practice for planning and scheduling in construction This handbook acts as a guide to good practice, a text to accompany learning and a reference document for those needing information on background, best practice, and methods for practical application.

Table of Contents

Notes on Contributors xiv

Foreword xvii

Preface xviii

Acknowledgements xxi

About the Companion Website xxii

Section I Planning and Scheduling within the Construction Context 1

Introduction 1

1 An Introduction to Planning and Scheduling 3

A brief history of planning and scheduling 3

Critical path methods 4

The impact of the PC 5

New systems and new thinking 6

New information and communication technologies 6

Planning 7

Who plans? 8

Planning, programming and scheduling 8

The cost and benefits of planning 10

Types of plans 11

An activity of the mind 11

Planning for construction 12

The planning process in the project cycle 13

PRINCE2 14

CIOB code of practice for project management for construction and development 15

The RIBA plan of work 17

The process protocol map 19

Summary 23

How is the planning process affected by procurement? 24

The context of construction project planning 27

Procurement and the performance of the UK construction industry 28

The Egan report (1998) 29

Partnering 30

Public sector construction procurement: The private finance initiative (PFI) 31

What do construction planners do? 31

Construction planning practice: a summary 33

Key points 34

2 Managing Construction Projects 36
Li Baiyi and Simon Austin

Project management body of knowledge (PMBOK) 36

Simultaneous management 41

Lean construction 42

A theory of construction as production by projects 44

Collaborative working 46

Morris’ perspective 47

Summary 47

Key points 50

Section II Planning and Scheduling Techniques and Practices 51

Introduction 51

3 Planning and Scheduling Techniques 53

To-do lists 53

Bar charts 55

Flow diagrams 56

Flow charts 56

Work study 57

Network analysis 59

Activity-on-arrow networks 60

Drawing the network 60

Precedence diagrams 63

Drawing the network-precedence diagrams 63

Linked bar charts 65

Space diagrams 65

Time chainage charts 65

Multiple activity charts 69

Line of balance 71

Line of balance – resource scheduling 73

ADePT 74

Data flow diagrams 75

A generic model for detailed building design 75

Dependency structure matrix analysis 76

Producing project and departmental schedules 79

4D CAD 79

Key points 80

4 Planning and Scheduling Practices 81

Schedule design and structure 81

Level 1 schedule report 81

Level 2 schedule report 82

Level 3 schedule report 82

Level 4 schedule report 83

Level 5 schedule report 83

What is required on smaller projects? 83

Creating these schedules 84

Work Breakdown Structure 84

Pre-tender planning, pre-contract planning, contract planning 86

Pre-tender planning 86

Pre-contract planning 92

Contract planning 94

Activities: selection, sequencing and duration 96

Activity selection 96

Sequencing 98

Assessing the duration of each activity 99

Links, dependencies and constraints 100

Float and contingency 102

Total float 103

Free float 104

Interfering float 105

Independent float 105

Intermittent float 106

Negative float 107

Terminal float 108

Internal float 108

Contingency 109

Manipulation of float 110

Who owns the float? 111

Monitoring progress and managing the time model 112

Reviewing the assumptions used to produce the schedule 113

Collecting and reviewing production records and progress reports 114

Reviewing the activities currently in progress 114

Updating the schedule 115

Identifying intervening events 117

Assessing progress and forecasting completion 119

Reviewing contingencies and revising the working schedule to effect a recovery 119

Other methods of monitoring progress 119

Milestone monitoring 119

Cash flow monitoring 120

Activity schedules 120

Planned progress monitoring 120

Earned value analysis 121

Resources and cost optimisation 122

Resources 122

Method statements 127

Format of the method statement 127

The tender method statement (for submission to the client) 127

The tender method statement (for internal use) 129

The construction or work method statement 129

The health and safety method statement 129

Planning method statement 130

Site layout plans 132

At the tender stage 132

At the pre-contract stage 134

At the contract stage 134

Site waste management plans 134

Contractors’ cash flow 135

Bank borrowings 136

Head office overheads 136

Working capital 136

Uncertainty and risk 139

Risk management 140

How do contractors price risk in bids? 143

Key points 146

Section III Planning and Scheduling Methods 149

Introduction 149

5 Critical Chain Project Management 151

Background 151

How does CCPM differ from accepted best practice in project management? 152

Establishing the critical chain 152

Monitoring and controlling the critical chain 153

A critical review of CCPM 155

Key points 157

6 Earned Value Analysis 158

Terminology and definitions 158

Cost Performance Index (CPI) 159

Cost variance 159

Earned value analysis (EVA) 159

Earned value management (EVM) 159

Earned value management system (EVMS) 159

Budgeted cost of work scheduled 159

Budget at completion (BAC) 159

Actual cost of work performed (ACWP) 160

Budgeted cost of work performed (BCWP) 160

Earned value (EV) 160

Performance measurement baseline 160

Schedule Performance Index (SPI) 160

Schedule variance (SV) 160

The basis of the EVA 160

Earned value analysis calculations and their interpretation 163

Forecasting 164

An example of EVA calculations 164

Earned value management systems 167

Problems and pitfalls of EVA and how to overcome them 168

Key points 170

7 Last Planner® 171

Background 171

The development of Last Planner® 172

Principles of the Last Planner System® (LPS) 174

Implementing the Last Planner System® (LPS) 175

Improving production performance 179

Benefits of the Last Planner® System 179

Barriers to the adoption of Last Planner® 180

Key points 181

8 ADePT–Planning, Managing and Controlling the Design Process 182

Background 182

A new way of working 183

Defining the scope of the design process 185

Process sequencing 185

Scheduling 185

Controlling the design workflow 186

Practical implementation 186

A facilitated approach to planning 186

Integrating design with procurement and construction 188

Managing constraints and measuring progress 189

Summary 191

Key points 191

9 Building Information Modelling (BIM) 192

What is building information modelling (BIM)? 192

BIM is not new 193

Why now? 194

BIM maturity levels 195

Level 0 195

Level 1 195

Level 2 196

Level 3 196

The development of 4D CAD 197

Virtual construction 200

The requirement collection phase 200

The model building phase 200

The process simulation phase 202

How will BIM change construction planning and scheduling? 202

BIM and the law 203

Key points 203

10 Planning for Sustainability with BREEAM 204
Samuel Ewuosho

Background 204

The need for sustainable construction 204

Drivers of sustainable construction 205

Legislative drivers 205

Client (market-led) requirements 206

Professional responsibility 206

Competitors 206

BREEAM 207

BREEAM sections 209

Management 209

Health and wellbeing 209

Energy 209

Transport 210

Water section 210

Materials 211

Waste 211

Land use and ecology 211

Pollution section 211

Innovation 211

Industry response to BREEAM 212

Case study analysis 213

Different projects produce different management situations 213

Individual perceptions of sustainability and BREEAM 214

Key points 215

11 Planning for Waste Management 216
Sarah-Jane Holmes and Mohamed Osmani

Background 216

Construction waste causes and origins 217

Materials procurement 217

Design 218

Site operations 218

On-site waste management practices 219

On-site waste management techniques 220

Site Waste Management Plan (SWMP) requirements 221

How the research was undertaken 222

Research results 222

Construction waste origins 222

Waste production and potential waste minimisation across projects’ life cycle 223

Discussion 225

Key challenges associated with implementing SWMPs 226

Key points 227

12 Planning for Safety, Health and Environment 228
Alastair Gibb

Background 228

SHE management model: An overview 228

Planning 230

Hazard/risk identification and control 231

Risk control measures 231

Developing the SHE plan 239

Programme for occupational health 242

Right info, right people, right time 243

Construction risk assessments 243

Constructability reviews 243

Method statements 244

Job safety analysis (JSA) 244

Environment 245

Emergency preparedness 245

Key points 246

Section IV Delay and Forensic Analysis 247

Introduction 247

13 Delays 249

Delay and disruption: Definitions 249

Delays 250

Categories of delay 251

Types of delay 251

Date 251

Total 252

Extended 252

Additional 254

Progress 254

Sequence 255

Fragnets 256

Prospective versus retrospective delay and other concepts 256

Key points 259

14 Factual Information 260

The As-Planned schedule 260

Correcting the As-Planned schedule 261

Key contract dates 262

Missing logic links 262

Constraints 263

Activity durations 264

Sequence of activities 264

Missing activities 265

Additional activities 265

Scope change 266

Software 266

Bar chart to network 267

As-built/progress records 269

As-built schedule 272

Key points 275

15 Protocols and Methods of Analysis 276

The Society of Construction Law Delay and Disruption Protocol 276

AACEI recommended practice no. 29R-03 – Forensic schedule analysis 279

Methods of analysis 280

Global claims 286

As-planned versus as-built 289

Impacted as-planned 291

Time impact analysis 300

Collapsed as-built 317

Windows 319

As-Planned versus As-Built 325

Time impact analysis 325

As-Planned versus As- Built #2 Or Time Slice Analysis 326

Key points 327

16 Disruption 328

Definitions and background 328

Methods of analysis 329

Measured mile 329

Leonard/Ibbs curves 332

Indices and statistics 335

Key points 336

17 Other Issues 337

Out-of-Sequence progress 337

Progress override 338

Retained logic 338

Omissions 340

Calendars 341

Weather 345

Concurrent delay 348

Pacing 352

Mitigation 352

Acceleration 354

Employer/contractor/subcontractor schedules 355

Key points 356

Appendices

Appendix 1 BIM Case Study: One Island East 358

Appendix 2 The Shepherd Way and Collaborative Planning 362

Appendix 3 Building Information Modelling (BIM) and English Law 367
Stacy Sinclair

Glossary 371

References 389

Index 399

Handbook for Construction Planning and Scheduling

    Product form

    £47.45

    Includes FREE delivery

    RRP £49.95 – you save £2.50 (5%)

    Order before 4pm today for delivery by Mon 22 Jun 2026.

    A Paperback / softback by Andrew Baldwin, David Bordoli

    1 in stock

      Trusted by thousands of customers. See 2,385+ Customer Reviews

      View other formats and editions of Handbook for Construction Planning and Scheduling by Andrew Baldwin

      Publisher: John Wiley & Sons Inc
      Publication Date: 13/06/2014
      ISBN13: 9780470670323, 978-0470670323
      ISBN10: 0470670320

      Description

      Book Synopsis
      The authoritative industry guide on good practice for planning and scheduling in construction This handbook acts as a guide to good practice, a text to accompany learning and a reference document for those needing information on background, best practice, and methods for practical application.

      Table of Contents

      Notes on Contributors xiv

      Foreword xvii

      Preface xviii

      Acknowledgements xxi

      About the Companion Website xxii

      Section I Planning and Scheduling within the Construction Context 1

      Introduction 1

      1 An Introduction to Planning and Scheduling 3

      A brief history of planning and scheduling 3

      Critical path methods 4

      The impact of the PC 5

      New systems and new thinking 6

      New information and communication technologies 6

      Planning 7

      Who plans? 8

      Planning, programming and scheduling 8

      The cost and benefits of planning 10

      Types of plans 11

      An activity of the mind 11

      Planning for construction 12

      The planning process in the project cycle 13

      PRINCE2 14

      CIOB code of practice for project management for construction and development 15

      The RIBA plan of work 17

      The process protocol map 19

      Summary 23

      How is the planning process affected by procurement? 24

      The context of construction project planning 27

      Procurement and the performance of the UK construction industry 28

      The Egan report (1998) 29

      Partnering 30

      Public sector construction procurement: The private finance initiative (PFI) 31

      What do construction planners do? 31

      Construction planning practice: a summary 33

      Key points 34

      2 Managing Construction Projects 36
      Li Baiyi and Simon Austin

      Project management body of knowledge (PMBOK) 36

      Simultaneous management 41

      Lean construction 42

      A theory of construction as production by projects 44

      Collaborative working 46

      Morris’ perspective 47

      Summary 47

      Key points 50

      Section II Planning and Scheduling Techniques and Practices 51

      Introduction 51

      3 Planning and Scheduling Techniques 53

      To-do lists 53

      Bar charts 55

      Flow diagrams 56

      Flow charts 56

      Work study 57

      Network analysis 59

      Activity-on-arrow networks 60

      Drawing the network 60

      Precedence diagrams 63

      Drawing the network-precedence diagrams 63

      Linked bar charts 65

      Space diagrams 65

      Time chainage charts 65

      Multiple activity charts 69

      Line of balance 71

      Line of balance – resource scheduling 73

      ADePT 74

      Data flow diagrams 75

      A generic model for detailed building design 75

      Dependency structure matrix analysis 76

      Producing project and departmental schedules 79

      4D CAD 79

      Key points 80

      4 Planning and Scheduling Practices 81

      Schedule design and structure 81

      Level 1 schedule report 81

      Level 2 schedule report 82

      Level 3 schedule report 82

      Level 4 schedule report 83

      Level 5 schedule report 83

      What is required on smaller projects? 83

      Creating these schedules 84

      Work Breakdown Structure 84

      Pre-tender planning, pre-contract planning, contract planning 86

      Pre-tender planning 86

      Pre-contract planning 92

      Contract planning 94

      Activities: selection, sequencing and duration 96

      Activity selection 96

      Sequencing 98

      Assessing the duration of each activity 99

      Links, dependencies and constraints 100

      Float and contingency 102

      Total float 103

      Free float 104

      Interfering float 105

      Independent float 105

      Intermittent float 106

      Negative float 107

      Terminal float 108

      Internal float 108

      Contingency 109

      Manipulation of float 110

      Who owns the float? 111

      Monitoring progress and managing the time model 112

      Reviewing the assumptions used to produce the schedule 113

      Collecting and reviewing production records and progress reports 114

      Reviewing the activities currently in progress 114

      Updating the schedule 115

      Identifying intervening events 117

      Assessing progress and forecasting completion 119

      Reviewing contingencies and revising the working schedule to effect a recovery 119

      Other methods of monitoring progress 119

      Milestone monitoring 119

      Cash flow monitoring 120

      Activity schedules 120

      Planned progress monitoring 120

      Earned value analysis 121

      Resources and cost optimisation 122

      Resources 122

      Method statements 127

      Format of the method statement 127

      The tender method statement (for submission to the client) 127

      The tender method statement (for internal use) 129

      The construction or work method statement 129

      The health and safety method statement 129

      Planning method statement 130

      Site layout plans 132

      At the tender stage 132

      At the pre-contract stage 134

      At the contract stage 134

      Site waste management plans 134

      Contractors’ cash flow 135

      Bank borrowings 136

      Head office overheads 136

      Working capital 136

      Uncertainty and risk 139

      Risk management 140

      How do contractors price risk in bids? 143

      Key points 146

      Section III Planning and Scheduling Methods 149

      Introduction 149

      5 Critical Chain Project Management 151

      Background 151

      How does CCPM differ from accepted best practice in project management? 152

      Establishing the critical chain 152

      Monitoring and controlling the critical chain 153

      A critical review of CCPM 155

      Key points 157

      6 Earned Value Analysis 158

      Terminology and definitions 158

      Cost Performance Index (CPI) 159

      Cost variance 159

      Earned value analysis (EVA) 159

      Earned value management (EVM) 159

      Earned value management system (EVMS) 159

      Budgeted cost of work scheduled 159

      Budget at completion (BAC) 159

      Actual cost of work performed (ACWP) 160

      Budgeted cost of work performed (BCWP) 160

      Earned value (EV) 160

      Performance measurement baseline 160

      Schedule Performance Index (SPI) 160

      Schedule variance (SV) 160

      The basis of the EVA 160

      Earned value analysis calculations and their interpretation 163

      Forecasting 164

      An example of EVA calculations 164

      Earned value management systems 167

      Problems and pitfalls of EVA and how to overcome them 168

      Key points 170

      7 Last Planner® 171

      Background 171

      The development of Last Planner® 172

      Principles of the Last Planner System® (LPS) 174

      Implementing the Last Planner System® (LPS) 175

      Improving production performance 179

      Benefits of the Last Planner® System 179

      Barriers to the adoption of Last Planner® 180

      Key points 181

      8 ADePT–Planning, Managing and Controlling the Design Process 182

      Background 182

      A new way of working 183

      Defining the scope of the design process 185

      Process sequencing 185

      Scheduling 185

      Controlling the design workflow 186

      Practical implementation 186

      A facilitated approach to planning 186

      Integrating design with procurement and construction 188

      Managing constraints and measuring progress 189

      Summary 191

      Key points 191

      9 Building Information Modelling (BIM) 192

      What is building information modelling (BIM)? 192

      BIM is not new 193

      Why now? 194

      BIM maturity levels 195

      Level 0 195

      Level 1 195

      Level 2 196

      Level 3 196

      The development of 4D CAD 197

      Virtual construction 200

      The requirement collection phase 200

      The model building phase 200

      The process simulation phase 202

      How will BIM change construction planning and scheduling? 202

      BIM and the law 203

      Key points 203

      10 Planning for Sustainability with BREEAM 204
      Samuel Ewuosho

      Background 204

      The need for sustainable construction 204

      Drivers of sustainable construction 205

      Legislative drivers 205

      Client (market-led) requirements 206

      Professional responsibility 206

      Competitors 206

      BREEAM 207

      BREEAM sections 209

      Management 209

      Health and wellbeing 209

      Energy 209

      Transport 210

      Water section 210

      Materials 211

      Waste 211

      Land use and ecology 211

      Pollution section 211

      Innovation 211

      Industry response to BREEAM 212

      Case study analysis 213

      Different projects produce different management situations 213

      Individual perceptions of sustainability and BREEAM 214

      Key points 215

      11 Planning for Waste Management 216
      Sarah-Jane Holmes and Mohamed Osmani

      Background 216

      Construction waste causes and origins 217

      Materials procurement 217

      Design 218

      Site operations 218

      On-site waste management practices 219

      On-site waste management techniques 220

      Site Waste Management Plan (SWMP) requirements 221

      How the research was undertaken 222

      Research results 222

      Construction waste origins 222

      Waste production and potential waste minimisation across projects’ life cycle 223

      Discussion 225

      Key challenges associated with implementing SWMPs 226

      Key points 227

      12 Planning for Safety, Health and Environment 228
      Alastair Gibb

      Background 228

      SHE management model: An overview 228

      Planning 230

      Hazard/risk identification and control 231

      Risk control measures 231

      Developing the SHE plan 239

      Programme for occupational health 242

      Right info, right people, right time 243

      Construction risk assessments 243

      Constructability reviews 243

      Method statements 244

      Job safety analysis (JSA) 244

      Environment 245

      Emergency preparedness 245

      Key points 246

      Section IV Delay and Forensic Analysis 247

      Introduction 247

      13 Delays 249

      Delay and disruption: Definitions 249

      Delays 250

      Categories of delay 251

      Types of delay 251

      Date 251

      Total 252

      Extended 252

      Additional 254

      Progress 254

      Sequence 255

      Fragnets 256

      Prospective versus retrospective delay and other concepts 256

      Key points 259

      14 Factual Information 260

      The As-Planned schedule 260

      Correcting the As-Planned schedule 261

      Key contract dates 262

      Missing logic links 262

      Constraints 263

      Activity durations 264

      Sequence of activities 264

      Missing activities 265

      Additional activities 265

      Scope change 266

      Software 266

      Bar chart to network 267

      As-built/progress records 269

      As-built schedule 272

      Key points 275

      15 Protocols and Methods of Analysis 276

      The Society of Construction Law Delay and Disruption Protocol 276

      AACEI recommended practice no. 29R-03 – Forensic schedule analysis 279

      Methods of analysis 280

      Global claims 286

      As-planned versus as-built 289

      Impacted as-planned 291

      Time impact analysis 300

      Collapsed as-built 317

      Windows 319

      As-Planned versus As-Built 325

      Time impact analysis 325

      As-Planned versus As- Built #2 Or Time Slice Analysis 326

      Key points 327

      16 Disruption 328

      Definitions and background 328

      Methods of analysis 329

      Measured mile 329

      Leonard/Ibbs curves 332

      Indices and statistics 335

      Key points 336

      17 Other Issues 337

      Out-of-Sequence progress 337

      Progress override 338

      Retained logic 338

      Omissions 340

      Calendars 341

      Weather 345

      Concurrent delay 348

      Pacing 352

      Mitigation 352

      Acceleration 354

      Employer/contractor/subcontractor schedules 355

      Key points 356

      Appendices

      Appendix 1 BIM Case Study: One Island East 358

      Appendix 2 The Shepherd Way and Collaborative Planning 362

      Appendix 3 Building Information Modelling (BIM) and English Law 367
      Stacy Sinclair

      Glossary 371

      References 389

      Index 399

      Recently viewed products

      © 2026 Book Curl

        • American Express
        • Apple Pay
        • Diners Club
        • Discover
        • Google Pay
        • Maestro
        • Mastercard
        • PayPal
        • Shop Pay
        • Union Pay
        • Visa

        Login

        Forgot your password?

        Don't have an account yet?
        Create account