Description

Book Synopsis
Many building projects are the subject of claims the assertion of a right, usually by the contractor, to an extension of the contract period or an additional payment under the terms of the building contract. Many of these claims are unsound or ill-founded, often because the basic principles are misunderstood.

This highly regarded book examines the legal basis of claims for extensions of time and additional payment, and what can and cannot be claimed under the main forms of contract. It includes chapters dealing with direct loss and expense, liquidated damages, extension of time, concurrency problems, acceleration, time at large, common law and contractual claims, global claims, and heads of claim and their substantiation. With the publication of the fifth edition, Building Contract Claims has been thoroughly revised to ensure it is fully up to date with the latest contracts, court judgments and building practice. Changes include:

  • Coverage of over 60 additional

    Table of Contents
    Preface vii

    Acknowledgements x

    Contract abbreviations xi

    PART I 1

    1 Introduction 3

    1.1 Structure of the book 3

    1.2 Types of claims 3

    1.3 The basis of claims 8

    1.4 Architect's and contract administrator's powers and liability to contractor 11

    1.5 Quantity surveyor’s powers 16

    2 Time 20

    2.1 Time of the essence 20

    2.2 Time at large 22

    2.3 Extension of time clauses in contracts 26

    2.4 Concurrency 32

    2.5 Acceleration 40

    2.6 Sectional completion 47

    2.7 The SCL extension of time Protocol 51

    3 Liquidated damages 57

    3.1 The meaning and purpose of liquidated damages 57

    3.2 Liquidated damages or penalty 58

    3.3 Liquidated damages as limitation of liability 65

    3.4 Sums greater than a genuine pre-estimate 66

    3.5 Liquidated damages as an exhaustive remedy 67

    3.6 Injunction 72

    3.7 Liquidated damages in relation to loss 74

    3.8 Where there is no breach of contract 75

    3.9 Calculation of liquidated damages 77

    3.10 Where there is partial possession 78

    3.11 Maximum recovery if sum is a penalty 80

    3.12 Maximum recovery if liquidated damages do not apply 82

    3.13 Defences to liquidated damages in building contracts 84

    3.14 Bonus clauses 93

    4 Basis for common law claims 95

    4.1 General 95

    4.2 Implied terms 97

    4.3 Variation of contract 103

    4.4 Omission of work to give it to others 104

    4.5 Extra work 107

    4.6 Possession of site 109

    4.7 Site conditions 113

    5 Direct loss and/or expense 117

    5.1 Defi nition 117

    5.2 Direct v indirect 118

    5.3 Exclusion of consequential loss 120

    6 Points of principle 123

    6.1 Measure of damages 123

    6.2 Burden of proof 124

    6.3 Res ipsa loquitur 125

    6.4 Mitigation of loss 125

    6.5 Betterment 127

    6.6 Notices 128

    6.7 Categories of claim 135

    7 Potential heads of claim 140

    7.1 Foreshortened programme 140

    7.2 The ‘knock-on’ effect 143

    7.3 The more common heads of loss 147

    7.4 Cost of a claim 180

    8 Causation 182

    8.1 Theory 182

    8.2 Use of networks 184

    8.3 Float 189

    9 Global claims 192

    9.1 Basic principles of global claims 192

    9.2 Unacceptable global claims 194

    9.3 The current position 196

    10 Preparation and substantiation of claims 201

    10.1 Preparing a claim 201

    10.2 Types of evidence required to support a claim 206

    10.3 ‘Scott schedules’ 213

    PART II 217

    11 Extension of time under JCT standard form contracts 219

    11.1 Standard Building Contract (SBC) 219

    11.2 Intermediate Building Contract (IC and ICD) 248

    11.3 Minor Works Building Contract (MW and MWD) 251

    11.4 Design and Build Contract (DB) 254

    11.5 Prime Cost Building Contract (PCC) 256

    11.6 Management Building Contract (MC) 257

    11.7 Construction Management Trade Contract (CM/TC) 259

    11.8 Major Project Construction Contract (MP) 260

    11.9 Measured Term Contract (MTC) 262

    11.10 Constructing Excellence Contract (CE) 264

    12 Liquidated damages under JCT standard form contracts 268

    12.1 Standard Building Contract (SBC) 268

    12.2 Intermediate Building Contract (IC and ICD) 273

    12.3 Minor Works Building Contract (MW and MWD) 273

    12.4 Design and Build Contract (DB) 274

    12.5 Prime Cost Building Contract (PCC) 275

    12.6 Management Building Contract (MC) 275

    12.7 Construction Management Trade Contract (CM/TC) 275

    12.8 Major Project Construction Contract (MP) 276

    12.9 Measured Term Contract (MTC) 276

    12.10 Constructing Excellence Contract (CE) 277

    13 Loss and/or expense under JCT standard form contracts 278

    13.1 Standard Building Contract (SBC) 278

    13.2 Intermediate Building Contract (IC and ICD) 305

    13.3 Minor Works Building Contract (MW and MWD) 309

    13.4 Design and Build Contract (DB) 311

    13.5 Prime Cost Building Contract (PCC) 315

    13.6 Management Building Contract (MC) 316

    13.7 Construction Management Trade Contract (CM/TC) 316

    13.8 Major Project Construction Contract (MP) 316

    13.9 Measured Term Contract (MTC) 318

    13.10 Constructing Excellence Contract (CE) 318

    14 Variations 319

    14.1 Introduction 319

    14.2 The baseline 320

    14.3 Bills of quantities 321

    14.4 Functions of the architect and the quantity surveyor 324

    14.5 JCT Standard Building Contract (SBC) 325

    14.6 JCT Intermediate Building Contract (IC and ICD) 345

    14.7 JCT Minor Works Building Contract (MW and MWD) 350

    14.8 JCT Design and Build Contract (DB) 352

    14.9 JCT Prime Cost Building Contract (PCC) 360

    14.10 JCT Management Building Contract (MC) 361

    14.11 JCT Construction Management Trade Contract (CM/TC) 361

    14.12 JCT Major Project Construction Contract (MP) 362

    14.13 JCT Measured Term Contract (MTC) 364

    14.14 JCT Constructing Excellence Contract (CE) 366

    PART III 367

    15 Claims Under The General Conditions of Government Contracts for Building and Civil Engineering Works (GC/Works/1(1998)) 369

    15.1 Introduction 369

    15.2 Extension of time and liquidated damages 369

    15.3 Prolongation and disruption 377

    15.4 Valuation of instructions 381

    16 Claims under the ACA Form of Building Agreement (ACA 3) 385

    16.1 Introduction 385

    16.2 Extension of time and liquidated damages 386

    16.3 Prolongation and disruption 395

    16.4 Valuation of instructions 402

    17 Claims under the ACA Standard Form of Contract for Project Partnering (PPC2000) 407

    17.1 Introduction 407

    17.2 Extension of time and damages 408

    17.3 Loss and/or expense 413

    17.4 Changes 415

    18 Claims under NEC 3 Engineering and Construction Contract (NEC 3) 418

    18.1 Introduction 418

    18.2 Compensation events 420

    18.3 Delay damages 444

    19 Sub-contract claims 446

    19.1 Introduction 446

    19.2 JCT Standard Building Sub-Contract Conditions (SBCSub/C) 446

    19.3 JCT Standard Building Sub-Contract with Sub-Contractor’s Design Conditions (SBCSub/D/C) 457

    19.4 JCT Intermediate Named Sub-Contract Conditions (ICSubNAM/SC) 458

    19.5 JCT Intermediate Sub-Contract Conditions (ICSub/C) 459

    19.6 JCT Intermediate Sub-Contract with Sub-Contractor's Design Conditions (ICSub/D/C) 460

    19.7 JCT Design and Build Sub-Contract Conditions (DBSub/C) 460

    19.8 JCT Management Works Contract Conditions (MCWC/C) 462

    19.9 ACA Form of Sub-Contract (ACA/SC) 465

    APPENDIX 473

    Example of contractor's claim for reimbursement of direct loss and/or expense under SBC with quantities clauses 4.23–4.26 – architect's and quantity surveyor's assessment with commentary 475

    Table of cases 498

    Table of standard form contract clauses 512

    Index 523

Building Contract Claims

    Product form

    £105.95

    Includes FREE delivery

    Order before 4pm tomorrow for delivery by Tue 14 Jul 2026.

    A Hardback by David Chappell

    10 in stock

      Trusted by thousands of customers. See 2,385+ Customer Reviews

      View other formats and editions of Building Contract Claims by David Chappell

      Publisher: John Wiley & Sons Inc
      Publication Date: 12/08/2011
      ISBN13: 9780470657386, 978-0470657386
      ISBN10: 0470657383

      Description

      Book Synopsis
      Many building projects are the subject of claims the assertion of a right, usually by the contractor, to an extension of the contract period or an additional payment under the terms of the building contract. Many of these claims are unsound or ill-founded, often because the basic principles are misunderstood.

      This highly regarded book examines the legal basis of claims for extensions of time and additional payment, and what can and cannot be claimed under the main forms of contract. It includes chapters dealing with direct loss and expense, liquidated damages, extension of time, concurrency problems, acceleration, time at large, common law and contractual claims, global claims, and heads of claim and their substantiation. With the publication of the fifth edition, Building Contract Claims has been thoroughly revised to ensure it is fully up to date with the latest contracts, court judgments and building practice. Changes include:

      • Coverage of over 60 additional

        Table of Contents
        Preface vii

        Acknowledgements x

        Contract abbreviations xi

        PART I 1

        1 Introduction 3

        1.1 Structure of the book 3

        1.2 Types of claims 3

        1.3 The basis of claims 8

        1.4 Architect's and contract administrator's powers and liability to contractor 11

        1.5 Quantity surveyor’s powers 16

        2 Time 20

        2.1 Time of the essence 20

        2.2 Time at large 22

        2.3 Extension of time clauses in contracts 26

        2.4 Concurrency 32

        2.5 Acceleration 40

        2.6 Sectional completion 47

        2.7 The SCL extension of time Protocol 51

        3 Liquidated damages 57

        3.1 The meaning and purpose of liquidated damages 57

        3.2 Liquidated damages or penalty 58

        3.3 Liquidated damages as limitation of liability 65

        3.4 Sums greater than a genuine pre-estimate 66

        3.5 Liquidated damages as an exhaustive remedy 67

        3.6 Injunction 72

        3.7 Liquidated damages in relation to loss 74

        3.8 Where there is no breach of contract 75

        3.9 Calculation of liquidated damages 77

        3.10 Where there is partial possession 78

        3.11 Maximum recovery if sum is a penalty 80

        3.12 Maximum recovery if liquidated damages do not apply 82

        3.13 Defences to liquidated damages in building contracts 84

        3.14 Bonus clauses 93

        4 Basis for common law claims 95

        4.1 General 95

        4.2 Implied terms 97

        4.3 Variation of contract 103

        4.4 Omission of work to give it to others 104

        4.5 Extra work 107

        4.6 Possession of site 109

        4.7 Site conditions 113

        5 Direct loss and/or expense 117

        5.1 Defi nition 117

        5.2 Direct v indirect 118

        5.3 Exclusion of consequential loss 120

        6 Points of principle 123

        6.1 Measure of damages 123

        6.2 Burden of proof 124

        6.3 Res ipsa loquitur 125

        6.4 Mitigation of loss 125

        6.5 Betterment 127

        6.6 Notices 128

        6.7 Categories of claim 135

        7 Potential heads of claim 140

        7.1 Foreshortened programme 140

        7.2 The ‘knock-on’ effect 143

        7.3 The more common heads of loss 147

        7.4 Cost of a claim 180

        8 Causation 182

        8.1 Theory 182

        8.2 Use of networks 184

        8.3 Float 189

        9 Global claims 192

        9.1 Basic principles of global claims 192

        9.2 Unacceptable global claims 194

        9.3 The current position 196

        10 Preparation and substantiation of claims 201

        10.1 Preparing a claim 201

        10.2 Types of evidence required to support a claim 206

        10.3 ‘Scott schedules’ 213

        PART II 217

        11 Extension of time under JCT standard form contracts 219

        11.1 Standard Building Contract (SBC) 219

        11.2 Intermediate Building Contract (IC and ICD) 248

        11.3 Minor Works Building Contract (MW and MWD) 251

        11.4 Design and Build Contract (DB) 254

        11.5 Prime Cost Building Contract (PCC) 256

        11.6 Management Building Contract (MC) 257

        11.7 Construction Management Trade Contract (CM/TC) 259

        11.8 Major Project Construction Contract (MP) 260

        11.9 Measured Term Contract (MTC) 262

        11.10 Constructing Excellence Contract (CE) 264

        12 Liquidated damages under JCT standard form contracts 268

        12.1 Standard Building Contract (SBC) 268

        12.2 Intermediate Building Contract (IC and ICD) 273

        12.3 Minor Works Building Contract (MW and MWD) 273

        12.4 Design and Build Contract (DB) 274

        12.5 Prime Cost Building Contract (PCC) 275

        12.6 Management Building Contract (MC) 275

        12.7 Construction Management Trade Contract (CM/TC) 275

        12.8 Major Project Construction Contract (MP) 276

        12.9 Measured Term Contract (MTC) 276

        12.10 Constructing Excellence Contract (CE) 277

        13 Loss and/or expense under JCT standard form contracts 278

        13.1 Standard Building Contract (SBC) 278

        13.2 Intermediate Building Contract (IC and ICD) 305

        13.3 Minor Works Building Contract (MW and MWD) 309

        13.4 Design and Build Contract (DB) 311

        13.5 Prime Cost Building Contract (PCC) 315

        13.6 Management Building Contract (MC) 316

        13.7 Construction Management Trade Contract (CM/TC) 316

        13.8 Major Project Construction Contract (MP) 316

        13.9 Measured Term Contract (MTC) 318

        13.10 Constructing Excellence Contract (CE) 318

        14 Variations 319

        14.1 Introduction 319

        14.2 The baseline 320

        14.3 Bills of quantities 321

        14.4 Functions of the architect and the quantity surveyor 324

        14.5 JCT Standard Building Contract (SBC) 325

        14.6 JCT Intermediate Building Contract (IC and ICD) 345

        14.7 JCT Minor Works Building Contract (MW and MWD) 350

        14.8 JCT Design and Build Contract (DB) 352

        14.9 JCT Prime Cost Building Contract (PCC) 360

        14.10 JCT Management Building Contract (MC) 361

        14.11 JCT Construction Management Trade Contract (CM/TC) 361

        14.12 JCT Major Project Construction Contract (MP) 362

        14.13 JCT Measured Term Contract (MTC) 364

        14.14 JCT Constructing Excellence Contract (CE) 366

        PART III 367

        15 Claims Under The General Conditions of Government Contracts for Building and Civil Engineering Works (GC/Works/1(1998)) 369

        15.1 Introduction 369

        15.2 Extension of time and liquidated damages 369

        15.3 Prolongation and disruption 377

        15.4 Valuation of instructions 381

        16 Claims under the ACA Form of Building Agreement (ACA 3) 385

        16.1 Introduction 385

        16.2 Extension of time and liquidated damages 386

        16.3 Prolongation and disruption 395

        16.4 Valuation of instructions 402

        17 Claims under the ACA Standard Form of Contract for Project Partnering (PPC2000) 407

        17.1 Introduction 407

        17.2 Extension of time and damages 408

        17.3 Loss and/or expense 413

        17.4 Changes 415

        18 Claims under NEC 3 Engineering and Construction Contract (NEC 3) 418

        18.1 Introduction 418

        18.2 Compensation events 420

        18.3 Delay damages 444

        19 Sub-contract claims 446

        19.1 Introduction 446

        19.2 JCT Standard Building Sub-Contract Conditions (SBCSub/C) 446

        19.3 JCT Standard Building Sub-Contract with Sub-Contractor’s Design Conditions (SBCSub/D/C) 457

        19.4 JCT Intermediate Named Sub-Contract Conditions (ICSubNAM/SC) 458

        19.5 JCT Intermediate Sub-Contract Conditions (ICSub/C) 459

        19.6 JCT Intermediate Sub-Contract with Sub-Contractor's Design Conditions (ICSub/D/C) 460

        19.7 JCT Design and Build Sub-Contract Conditions (DBSub/C) 460

        19.8 JCT Management Works Contract Conditions (MCWC/C) 462

        19.9 ACA Form of Sub-Contract (ACA/SC) 465

        APPENDIX 473

        Example of contractor's claim for reimbursement of direct loss and/or expense under SBC with quantities clauses 4.23–4.26 – architect's and quantity surveyor's assessment with commentary 475

        Table of cases 498

        Table of standard form contract clauses 512

        Index 523

      Recently viewed products

      © 2026 Book Curl

        • American Express
        • Apple Pay
        • Diners Club
        • Discover
        • Google Pay
        • Maestro
        • Mastercard
        • PayPal
        • Shop Pay
        • Union Pay
        • Visa

        Login

        Forgot your password?

        Don't have an account yet?
        Create account