Description

Book Synopsis

Whenever a contractor undertakes work using one of the standard building contracts, however small the job, writing a good many letters will be involved. Some will be formal notices it is necessary to give; others will be letters it is prudent to send.

This book provides a set of over 300 standard letters for use with the standard forms of building contract and sub-contract and aims to cover all the common situations which contractors will encounter when involved in a contract. It has been substantially revised to take account of the 2005 suite of JCT contracts, together with changes in case law and the 2007 CDM Regulations.

The letters are for use with the following contracts:

  • JCT Standard Building Contract (SBC),
  • JCT Intermediate Building Contract (IC) and ''with contractor''s design'' (ICD),
  • JCT Minor Works Building Contract (MW) and ''with contractor''s design'' (MWD),
  • JCT Design and Build Contract (DB),
  • JCT Standard

    Table of Contents

    Preface to the Fourth Edition xvii

    Introduction xix

    1 Tendering 1
    Letters

    1 To architect, requesting inclusion in list of tenderers 2

    2 To architect, if no response to request for inclusion on list of tenderers 3

    3 To architect, agreeing to tender 4

    4 To architect, if contractor unwilling to tender 5

    5 To architect, if contractor asked to provide information prior to inclusion on tender list 6

    6 To architect, if the contractor is informed that the tender date is delayed and is still willing to submit tender 7

    7 To architect, if the contractor is informed that the tender date is delayed and is unwilling to tender 8

    8 To architect, acknowledging receipt of tender documents 9

    9 To architect, regarding questions during the tender period 10

    10 To architect, requesting extension of tender period 11

    11 To architect, withdrawing qualification to tender 12

    12 To architect, if confirming offer where the overall price is dominant 13

    13 To architect, if withdrawing offer where the overall price is dominant 14

    14 To architect, if amending offer where the pricing document is dominant 15

    15 To architect, if tender accepted (a) 16

    16 To architect, if tender accepted (b) 17

    17 To architect, if tender accepted (c) 18

    18 To architect, if purporting to accept tender 19

    19 To architect, if another tender accepted 20

    2 Contract Documents 21
    Letters

    20 To architect, returning contract documents 23

    21 To architect, if mistakes in contract documents and previous

    22 To architect, if mistakes in contract documents and no previous acceptance of tender 25

    23 To architect, if contractor asked to commence before contract documents signed, but tender accepted 26

    24 To architect, if contractor asked to commence before contract documents signed and tender not accepted 27

    25 To architect, if contract not signed and certification due 28

    3 Insurance and Other Project Planning Matters 29
    Letters

    26 To architect, seeking approval to the names of insurers for employer’s liability 30

    27 To architect, regarding contractor’s insurance (a) 31

    28 To architect, regarding contractor’s insurance (b) 32

    29 To employer, regarding contractor’s insurance (c) 33

    30 To employer, within 21 days of acceptance of tender or renewal of insurance 34

    31 To architect, after approval of insurers for employer’s liability 35

    32 To architect, regarding professional indemnity insurance 36

    33 To architect, if professional indemnity insurance is no longer available at commercially reasonable rates 37

    34 To architect, if Joint Fire Code remedial measures are a variation 38

    35 To architect, if Joint Fire Code remedial measures are a variation, but require emergency action 39

    36 To employer, regarding employer’s insurance (a) 40

    37 To employer, regarding employer’s insurance (b) 41

    38 To employer, regarding employer’s insurance (c) 42

    39 To employer, who fails to maintain insurance cover (a) 43

    40 To employer, who fails to maintain insurance cover (b) 44

    41 To architect and employer, if any damage occurs due to an insured risk (a) 45

    42 To architect and employer, if any damage occurs due to an insured risk (b) 46

    43 To architect, on receipt of letter of intent 47

    44 To architect, if contractor asked to sign a warranty 48

    45 To architect, on receipt of defective third party rights notice 49

    46 To architect, on receipt of request for warranty 50

    47 To architect, if contractor asked to supply a performance bond 51

    48 To employer, if asked to execute a novation agreement 52

    49 To architect, enclosing the construction phase plan 54

    50 To architect, regarding person-in-charge or agent (a) 56

    51 To architect, regarding the appointment of a site manager (b) 57

    52 To architect, regarding consent to removal or replacement of site manager 58

    53 To architect, if required to furnish names and addresses of operatives 59

    54 To architect, if passes are required 60

    55 To employer, regarding the employer’s representative 61

    56 To employer, regarding the project manager 62

    4 Operations on Site 63
    Letters

    57 To employer, if possession not given on the due or the deferred date (a) 64

    58 To employer, if possession not given on the due date (b) 66

    59 To architect, if date for possession advanced 67

    60 To employer, giving consent to the engagement of other persons 68

    61 To employer, withholding consent to the engagement of other persons 69

    62 To architect, regarding items in minutes of site meeting 70

    63 To architect, enclosing master programme (a) 71

    64 To architect, enclosing master programme (b) 72

    65 To architect, enclosing revision to the master programme 73

    66 To architect, requesting information 74

    67 To architect, if insufficient information on setting out drawings 75

    68 To architect, requesting information that setting out is correct 76

    69 To architect, if information received late 77

    70 To architect, if information not received in accordance with the information release schedule 78

    71 To architect, if design fault in architect’s or consultant’s drawings 79

    72 To architect, if a design fault in architect’s or consultant’s drawings which the architect refuses to correct 80

    73 To architect, if contractor providing contractor’s design documents 81

    74 To architect, who fails to return the contractor’s drawings in due time 82

    75 To architect, if architect returns contractor’s design document marked ‘C’ 83

    76 To architect, if architect confirms a comment on documents marked ‘C’ 84

    77 To architect, if contractor providing contractor’s design documents 85

    78 To architect, if contractor providing levels and setting out information 86

    79 To architect, who returns contractor’s drawings with comments 87

    80 To architect, if discrepancy found between documents 88

    81 To architect, if discrepancy within the Employer’s Requirements 89

    82 To architect, if discrepancy within the Contractor’s Proposals 90

    83 To architect, if discrepancy found between Employer’s Requirements and Contractor’s Proposals 91

    84 To architect, if alleging that contractor should have checked the design 92

    85 To employer, pointing out design error in Employer’s Requirements 93

    86 To architect, requesting directions to integrate the design 94

    87 To architect, noting divergence between statutory requirements and other documents (a) 95

    88 To architect, noting divergence between statutory requirements and other documents (b) 96

    89 To architect, if emergency compliance with statutory requirements required 97

    90 To architect, if a change in statutory requirements after base date 98

    91 To architect, if development control decision after base date 99

    92 To employer (not being a local authority), objecting to the nomination of a replacement architect 100

    93 To employer (not being a local authority), objecting to the nomination of the employer as replacement architect 101

    94 To employer, if replacement architect not appointed 102

    95 To employer, objecting to the nomination of a replacement quantity surveyor 103

    96 To architect, regarding directions issued on site by the clerk of works 104

    97 To architect, regarding instructions issued on site by the clerk of works 105

    98 To architect, if clerk of works defaces work or materials 106

    99 To architect, if numerous ‘specialist’ clerks of works visiting site 107

    100 To architect, if clerk of works instructs operatives direct 108

    101 To quantity surveyor, submitting a Schedule 2 quotation 109

    102 To architect, regarding verification of vouchers for daywork 110

    103 To employer, if disagreement over whether work is a variation or included in the contract 111

    104 To architect, requiring the specification of the clause empowering an instruction (a) 112

    105 To architect, requiring the specification of the clause empowering an instruction (b) 113

    106 To architect, confirming an oral instruction 114

    107 To architect, requesting confirmation of an oral instruction 115

    108 To architect, if oral instruction not confirmed in writing 116

    109 To architect, objecting to exclusion of person from the Works (a) 117

    110 To employer, objecting to exclusion of person from the Works (b) 118

    111 To architect, objecting to instruction varying obligations or restrictions 119

    112 To architect, withholding consent to instruction altering the design of the Works 120

    113 To architect, if attempting to vary the Contractor’s Proposals 121

    114 To architect, on receipt of 7 day notice requiring compliance with instruction (a) 122

    115 To architect, on receipt of notice requiring compliance with instruction (b) 124

    116 To architect, if instruction will affect the contractor’s designed portion 126

    117 To architect withholding consent, if instruction will affect the contractor’s design 127

    118 To architect, removal of unfixed materials 128

    119 To architect, if materials are not procurable 129

    120 To architect, if wishing to substitute materials or goods 130

    121 To architect, after failure of work or materials or goods 131

    122 To architect, if contractor objects to complying with a clause 3.15.1 instruction 132

    123 To architect, after work opened up for inspection 133

    124 To architect, if excavations ready for inspection 134

    125 To architect, if issuing an instruction after ordering removal of defective work 135

    126 To architect, if issuing instruction for opening up after ordering removal of defective work 136

    127 To architect, if issuing instruction for removal of defective work 137

    128 To architect, if wrongly issuing instruction following failure to carry out the work in a proper and workmanlike manner 138

    129 To architect, if work to be covered up 139

    130 To architect, if antiquities found 140

    5 Payment 142
    Letters

    131 To architect, enclosing interim application for payment (a) 143

    132 To architect, enclosing interim application for payment (b) 144

    133 To quantity surveyor, submitting valuation application 145

    134 To architect, if quantity surveyor fails to respond to the valuation application 146

    135 To architect, if interim certificate not issued 147

    136 To architect, if certificate insufficient 148

    137 To employer, if payment not made in full and no withholding notice issued 149

    138 To architect, regarding copyright if payment withheld 150

    139 To employer, if the advance payment is not paid on the due date 151

    140 To architect, if valuation not carried out in accordance with the priced activity schedule 152

    141 To architect, if contractor not asked to be present at measurement 153

    142 To architect, requesting payment for off-site materials 154

    143 To employer, giving 7 days notice of suspension 155

    144 To employer, if payment in full has not been made within 7 days despite notice of suspension 156

    145 To employer, requesting interest on late payment 157

    146 To employer, requesting retention money to be placed in a separate bank account 158

    147 To employer, if failure to place retention in separate bank account 159

    148 To architect, enclosing all information for preparation of final certificate 160

    149 To architect, enclosing final account 161

    150 To employer, disputing the final account 162

    151 To architect, if final certificate not issued on the due date (a) 163

    152 To architect, if final certificate not issued on the due date (b) 164

    153 To architect, if final certificate not issued on the due date (c) 165

    6 Extensions of Time 166
    Letters

    154 To architect, if delay occurs, but no grounds for extension of time 167

    155 To architect, when cause of delay ended if no grounds for extension of time 168

    156 To architect, if delay occurs giving grounds for extension of time (a) 169

    157 To architect, if delay occurs giving grounds for extension of time (b) 170

    158 To architect, providing further particulars for extension of time (a) 171

    159 To architect, providing further particulars for extension of time (b) 172

    160 To architect, if requesting further information in order to grant extension of time 173

    161 To architect, if unreasonably requesting further information in order to grant an extension of time 174

    162 To architect, if extension of time is insufficient 175

    163 To architect, who is not willing to reconsider an insufficient extension of time 176

    164 To architect, if extension of time not properly attributed 177

    165 To architect, if extension of time not granted within time stipulated 178

    166 To architect, if slow in granting extension of time 179

    167 To architect, if review of extensions not carried out (a) 180

    168 To architect, if review of extensions not carried out (b) 181

    169 To architect, if no final decision on extensions of time (c) 182

    170 To architect, who alleges that contractor is not using best endeavours 183

    171 To architect, if non-completion certificate or notice wrongly issued 184

    172 To employer, if liquidated damages wrongfully deducted 185

    173 To employer, if damages repaid without interest 186

    7 Loss and/or Expense 187
    Letters

    174 To architect, applying for payment of loss and/or expense (a) 188

    175 To architect, applying for payment of loss and/or expense under the supplemental provisions (b) 189

    176 To architect, applying for payment of loss and/or expense (c) 190

    177 To architect, applying for payment of expense (d) 191

    178 To architect, giving further details of loss and/or expense (a) 192

    179 To architect or quantity surveyor, enclosing details of loss and/or expense (b) 193

    180 To quantity surveyor, providing information for calculation of expense (c) 194

    181 To architect, if ascertainment delayed (a) 195

    182 To architect, if ascertainment delayed (b) 196

    183 To architect, if ascertainment too small 197

    184 To employer, regarding a common law claim 198

    185 To employer, regarding a common law claim 199

    8 Termination, Arbitration, Adjudication and Completion 200
    Letters

    186 To employer or architect, if default notice served 201

    187 To employer or architect, if default notice served justly 203

    188 To employer, if premature termination notice issued 204

    189 To employer who terminates after notification of cessation of terrorism cover 205

    190 To employer, giving notice of default before termination 206

    191 To employer, terminating employment after default notice 207

    192 To employer, terminating employment on the employer’s insolvency 208

    193 To employer, where either party may terminate 209

    194 To employer, terminating if suspension has not ceased after notice 210

    195 To employer, terminating employment after damage by insured risk 211

    196 To employer, giving notice of intention to refer a dispute to adjudication 212

    197 To nominating body, requesting nomination of an adjudicator 213

    198 To adjudicator, enclosing the referral 214

    199 To employer, if the adjudicator’s decision is in your favour 215

    200 To employer, requesting concurrence in the appointment of an arbitrator 216

    201 To appointing body, if there is no concurrence in the appointment of an arbitrator 217

    202 To architect, if practical completion of the Works or a section imminent 218

    203 To architect, if completion certificate wrongly withheld (a) 219

    204 To architect, if completion statement wrongly withheld (b) 220

    205 To employer, consenting to early use 221

    206 To employer, consenting to partial possession (a) 222

    207 To employer, consenting to partial possession (b) 223

    208 To employer, issuing written statement of partial possession 224

    209 To employer, refusing consent to partial possession 225

    210 To architect, after receipt of schedule of defects 226

    211 To architect, when making good of defects completed 227

    212 To architect, returning drawings, etc. after final payment if requested 228

    9 Sub-Contractors 229
    Letters

    213 To employer, requesting consent to assignment 230

    214 To employer, if asked to consent to assignment 231

    215 To sub-contractor, assessing competence under the CDM Regulations 232

    216 To a designer, assessing competence under the CDM Regulations 233

    217 To architect, requesting consent to sub-letting 234

    218 To employer, requesting consent to addition of persons to clause 3.8 list 235

    219 To employer, giving consent to addition of person to clause 3.8 list 236

    220 To sub-contractor: letter of intent 237

    221 To sub-contractor, regarding part of the construction phase plan 238

    222 To sub-contractor, enclosing part of the construction phase plan 239

    223 To domestic sub-contractor, requiring a warranty if not noted in the invitation to tender 240

    224 To domestic sub-contractor, requiring a warranty if not noted in the contract documents 241

    225 To architect, if domestic sub-contractor refuses to provide a warranty which was not originally requested 242

    226 To architect, objecting to a named person (a) 243

    227 To architect, objecting to a nominated sub-contractor (b) 244

    228 To architect, if contractor unable to enter into a sub-contract with named person (a) 245

    229 To architect, if unable to enter into sub-contract with named person in accordance with particulars (b) 246

    230 To architect, if some listed sub-contractors will not tender 247

    231 To architect, if contractor enters into a sub-contract with named person 248

    232 To architect, if contractor enters into contract with named person 249

    233 To sub-contractor, regarding insurance 250

    234 To sub-contractor that fails to maintain insurance cover 251

    235 To sub-contractor, enclosing drawings 252

    236 To sub-contractor, if asked to consent to assignment 253

    237 To sub-contractor that sub-lets without consent 254

    238 To sub-contractor, giving consent to sub-letting 255

    239 To sub-contractor, if no person-in-charge 256

    240 To sub-contractor, requiring compliance with direction 257

    241 To sub-contractor that fails to comply with direction 258

    242 To sub-contractor, if contractor dissents from alleged oral direction 259

    243 To sub-contractor that wrongly confirms an oral direction 260

    244 To sub-contractor that confirms an oral direction which was given 261

    245 To sub-contractor, if non-compliant work allowed to remain 262

    246 To sub-contractor, if defective work opened up 263

    247 To sub-contractor, inspection after failure of work 264

    248 To sub-contractor, after failure of work 265

    249 To sub-contractor, accepting Schedule 2 quotation 266

    250 To sub-contractor, rejecting Schedule 2 quotation 267

    251 To sub-contractor, if necessary to measure work 268

    252 To sub-contractor, fixing a new period for completion 269

    253 To sub-contractor, fixing a new period for completion after practical completion of the sub-contract works 270

    254 To sub-contractor, if no extension of time due 271

    255 To sub-contractor, if claim for extension of time is not valid 272

    256 To sub-contractor, if sub-contract works not complete by due date (a) 273

    257 To sub-contractor, if sub-contract works not complete within the period for completion (b) 274

    258 To sub-contractor, requesting further information in support of a financial claim 275

    259 To sub-contractor, applying for payment of loss and/or expense (a) 276

    260 To sub-contractor, applying for payment of loss and/or expense (b) 277

    261 To sub-contractor, giving notice of an interim payment 278

    262 To sub-contractor, enclosing payment 279

    263 To sub-contractor, giving withholding notice 280

    264 To adjudicator, enclosing written statement 281

    265 To sub-contractor if adjudicator appointed, but there is no dispute 282

    266 To adjudicator, if there is no dispute 283

    267 To sub-contractor, if sub-contractor has wrongly sent 7 day notice of intention to suspend performance of obligations 284

    268 To sub-contractor, if sub-contractor has correctly sent 7 day notice of intention to suspend performance of obligations 286

    269 To sub-contractor, requesting documents for calculation of the final sub-contract sum 287

    270 To sub-contractor that has failed to submit documents for the calculation of the final sub-contract sum (a) 288

    271 To sub-contractor that has failed to submit documents for the calculation of the final sub-contract sum (b) 289

    272 To sub-contractor, enclosing final payment 290

    273 To employer, giving notice of the named sub-contractor’s default 291

    274 To sub-contractor, giving notice of default before termination 292

    275 To sub-contractor, giving notice before determination 293

    276 To architect, if termination of named person’s employment possible 294

    277 To sub-contractor, terminating employment after default notice (a) 295

    278 To sub-contractor, determining the sub-contract after notice (b) 296

    279 To sub-contractor, determining the sub-contract without prior notice 297

    280 To sub-contractor, terminating employment after termination of the main contract 298

    281 To sub-contractor, termination on insolvency 299

    282 To sub-contractor, if cessation of terrorism cover notified 300

    283 To sub-contractor, notifying the employer’s election after cessation of terrorism cover notified 301

    284 To sub-contractor that serves a default notice (a) 302

    285 To sub-contractor that serves a default notice before determination (b) 303

    286 To sub-contractor that serves notice of termination (a) 304

    287 To sub-contractor that serves notice of determination (b) 306

    288 To architect, if employment of named person terminated 308

    289 To architect, if employment of named person terminated under ICSub/NAM/C clause 7.4, 7.5 or 7.6 309

    290 To architect, if contractor instructed to carry out named person’s work after termination of named person’s employment 311

    291 To architect, if contractor decides to sub-let after termination of named person’s employment 312

    292 To employer, if money recovered after termination of named person’s employment 313

    293 To sub-contractor, requesting details for the health and safety file 314

    294 To sub-contractor, if contractor dissents from date of practical completion 315

    295 To sub-contractor, notifying practical completion after earlier dissent 316

    296 To sub-contractor, enclosing schedule of defects 317

    297 To sub-contractor, directing that some defects are not to be made good 318

    298 To sub-contractor, if deduction made under main contract for inaccurate setting out 319

    299 To architect, if action threatened because of named person’s design failure 320

    300 To sub-contract architect, engineer or other consultant, regarding professional indemnity insurance 321

    301 To sub-contract architect, engineer or other consultant, if late in providing information 322

    302 To sub-contract architect, engineer or other consultant, if action threatened because of design failure 323

    303 To sub-contract architect, engineer or other consultant, at the end of a successful project 324

    Index 325

Standard Letters for Building Contractors

    Product form

    £72.86

    Includes FREE delivery

    RRP £80.95 – you save £8.09 (9%)

    Order before 4pm tomorrow for delivery by Sat 4 Jul 2026.

    A Hardback by David Chappell

      Trusted by thousands of customers. See 2,385+ Customer Reviews

      View other formats and editions of Standard Letters for Building Contractors by David Chappell

      Publisher: John Wiley and Sons Ltd
      Publication Date: 29/02/2008
      ISBN13: 9781405177894, 978-1405177894
      ISBN10: 1405177896

      Description

      Book Synopsis

      Whenever a contractor undertakes work using one of the standard building contracts, however small the job, writing a good many letters will be involved. Some will be formal notices it is necessary to give; others will be letters it is prudent to send.

      This book provides a set of over 300 standard letters for use with the standard forms of building contract and sub-contract and aims to cover all the common situations which contractors will encounter when involved in a contract. It has been substantially revised to take account of the 2005 suite of JCT contracts, together with changes in case law and the 2007 CDM Regulations.

      The letters are for use with the following contracts:

      • JCT Standard Building Contract (SBC),
      • JCT Intermediate Building Contract (IC) and ''with contractor''s design'' (ICD),
      • JCT Minor Works Building Contract (MW) and ''with contractor''s design'' (MWD),
      • JCT Design and Build Contract (DB),
      • JCT Standard

        Table of Contents

        Preface to the Fourth Edition xvii

        Introduction xix

        1 Tendering 1
        Letters

        1 To architect, requesting inclusion in list of tenderers 2

        2 To architect, if no response to request for inclusion on list of tenderers 3

        3 To architect, agreeing to tender 4

        4 To architect, if contractor unwilling to tender 5

        5 To architect, if contractor asked to provide information prior to inclusion on tender list 6

        6 To architect, if the contractor is informed that the tender date is delayed and is still willing to submit tender 7

        7 To architect, if the contractor is informed that the tender date is delayed and is unwilling to tender 8

        8 To architect, acknowledging receipt of tender documents 9

        9 To architect, regarding questions during the tender period 10

        10 To architect, requesting extension of tender period 11

        11 To architect, withdrawing qualification to tender 12

        12 To architect, if confirming offer where the overall price is dominant 13

        13 To architect, if withdrawing offer where the overall price is dominant 14

        14 To architect, if amending offer where the pricing document is dominant 15

        15 To architect, if tender accepted (a) 16

        16 To architect, if tender accepted (b) 17

        17 To architect, if tender accepted (c) 18

        18 To architect, if purporting to accept tender 19

        19 To architect, if another tender accepted 20

        2 Contract Documents 21
        Letters

        20 To architect, returning contract documents 23

        21 To architect, if mistakes in contract documents and previous

        22 To architect, if mistakes in contract documents and no previous acceptance of tender 25

        23 To architect, if contractor asked to commence before contract documents signed, but tender accepted 26

        24 To architect, if contractor asked to commence before contract documents signed and tender not accepted 27

        25 To architect, if contract not signed and certification due 28

        3 Insurance and Other Project Planning Matters 29
        Letters

        26 To architect, seeking approval to the names of insurers for employer’s liability 30

        27 To architect, regarding contractor’s insurance (a) 31

        28 To architect, regarding contractor’s insurance (b) 32

        29 To employer, regarding contractor’s insurance (c) 33

        30 To employer, within 21 days of acceptance of tender or renewal of insurance 34

        31 To architect, after approval of insurers for employer’s liability 35

        32 To architect, regarding professional indemnity insurance 36

        33 To architect, if professional indemnity insurance is no longer available at commercially reasonable rates 37

        34 To architect, if Joint Fire Code remedial measures are a variation 38

        35 To architect, if Joint Fire Code remedial measures are a variation, but require emergency action 39

        36 To employer, regarding employer’s insurance (a) 40

        37 To employer, regarding employer’s insurance (b) 41

        38 To employer, regarding employer’s insurance (c) 42

        39 To employer, who fails to maintain insurance cover (a) 43

        40 To employer, who fails to maintain insurance cover (b) 44

        41 To architect and employer, if any damage occurs due to an insured risk (a) 45

        42 To architect and employer, if any damage occurs due to an insured risk (b) 46

        43 To architect, on receipt of letter of intent 47

        44 To architect, if contractor asked to sign a warranty 48

        45 To architect, on receipt of defective third party rights notice 49

        46 To architect, on receipt of request for warranty 50

        47 To architect, if contractor asked to supply a performance bond 51

        48 To employer, if asked to execute a novation agreement 52

        49 To architect, enclosing the construction phase plan 54

        50 To architect, regarding person-in-charge or agent (a) 56

        51 To architect, regarding the appointment of a site manager (b) 57

        52 To architect, regarding consent to removal or replacement of site manager 58

        53 To architect, if required to furnish names and addresses of operatives 59

        54 To architect, if passes are required 60

        55 To employer, regarding the employer’s representative 61

        56 To employer, regarding the project manager 62

        4 Operations on Site 63
        Letters

        57 To employer, if possession not given on the due or the deferred date (a) 64

        58 To employer, if possession not given on the due date (b) 66

        59 To architect, if date for possession advanced 67

        60 To employer, giving consent to the engagement of other persons 68

        61 To employer, withholding consent to the engagement of other persons 69

        62 To architect, regarding items in minutes of site meeting 70

        63 To architect, enclosing master programme (a) 71

        64 To architect, enclosing master programme (b) 72

        65 To architect, enclosing revision to the master programme 73

        66 To architect, requesting information 74

        67 To architect, if insufficient information on setting out drawings 75

        68 To architect, requesting information that setting out is correct 76

        69 To architect, if information received late 77

        70 To architect, if information not received in accordance with the information release schedule 78

        71 To architect, if design fault in architect’s or consultant’s drawings 79

        72 To architect, if a design fault in architect’s or consultant’s drawings which the architect refuses to correct 80

        73 To architect, if contractor providing contractor’s design documents 81

        74 To architect, who fails to return the contractor’s drawings in due time 82

        75 To architect, if architect returns contractor’s design document marked ‘C’ 83

        76 To architect, if architect confirms a comment on documents marked ‘C’ 84

        77 To architect, if contractor providing contractor’s design documents 85

        78 To architect, if contractor providing levels and setting out information 86

        79 To architect, who returns contractor’s drawings with comments 87

        80 To architect, if discrepancy found between documents 88

        81 To architect, if discrepancy within the Employer’s Requirements 89

        82 To architect, if discrepancy within the Contractor’s Proposals 90

        83 To architect, if discrepancy found between Employer’s Requirements and Contractor’s Proposals 91

        84 To architect, if alleging that contractor should have checked the design 92

        85 To employer, pointing out design error in Employer’s Requirements 93

        86 To architect, requesting directions to integrate the design 94

        87 To architect, noting divergence between statutory requirements and other documents (a) 95

        88 To architect, noting divergence between statutory requirements and other documents (b) 96

        89 To architect, if emergency compliance with statutory requirements required 97

        90 To architect, if a change in statutory requirements after base date 98

        91 To architect, if development control decision after base date 99

        92 To employer (not being a local authority), objecting to the nomination of a replacement architect 100

        93 To employer (not being a local authority), objecting to the nomination of the employer as replacement architect 101

        94 To employer, if replacement architect not appointed 102

        95 To employer, objecting to the nomination of a replacement quantity surveyor 103

        96 To architect, regarding directions issued on site by the clerk of works 104

        97 To architect, regarding instructions issued on site by the clerk of works 105

        98 To architect, if clerk of works defaces work or materials 106

        99 To architect, if numerous ‘specialist’ clerks of works visiting site 107

        100 To architect, if clerk of works instructs operatives direct 108

        101 To quantity surveyor, submitting a Schedule 2 quotation 109

        102 To architect, regarding verification of vouchers for daywork 110

        103 To employer, if disagreement over whether work is a variation or included in the contract 111

        104 To architect, requiring the specification of the clause empowering an instruction (a) 112

        105 To architect, requiring the specification of the clause empowering an instruction (b) 113

        106 To architect, confirming an oral instruction 114

        107 To architect, requesting confirmation of an oral instruction 115

        108 To architect, if oral instruction not confirmed in writing 116

        109 To architect, objecting to exclusion of person from the Works (a) 117

        110 To employer, objecting to exclusion of person from the Works (b) 118

        111 To architect, objecting to instruction varying obligations or restrictions 119

        112 To architect, withholding consent to instruction altering the design of the Works 120

        113 To architect, if attempting to vary the Contractor’s Proposals 121

        114 To architect, on receipt of 7 day notice requiring compliance with instruction (a) 122

        115 To architect, on receipt of notice requiring compliance with instruction (b) 124

        116 To architect, if instruction will affect the contractor’s designed portion 126

        117 To architect withholding consent, if instruction will affect the contractor’s design 127

        118 To architect, removal of unfixed materials 128

        119 To architect, if materials are not procurable 129

        120 To architect, if wishing to substitute materials or goods 130

        121 To architect, after failure of work or materials or goods 131

        122 To architect, if contractor objects to complying with a clause 3.15.1 instruction 132

        123 To architect, after work opened up for inspection 133

        124 To architect, if excavations ready for inspection 134

        125 To architect, if issuing an instruction after ordering removal of defective work 135

        126 To architect, if issuing instruction for opening up after ordering removal of defective work 136

        127 To architect, if issuing instruction for removal of defective work 137

        128 To architect, if wrongly issuing instruction following failure to carry out the work in a proper and workmanlike manner 138

        129 To architect, if work to be covered up 139

        130 To architect, if antiquities found 140

        5 Payment 142
        Letters

        131 To architect, enclosing interim application for payment (a) 143

        132 To architect, enclosing interim application for payment (b) 144

        133 To quantity surveyor, submitting valuation application 145

        134 To architect, if quantity surveyor fails to respond to the valuation application 146

        135 To architect, if interim certificate not issued 147

        136 To architect, if certificate insufficient 148

        137 To employer, if payment not made in full and no withholding notice issued 149

        138 To architect, regarding copyright if payment withheld 150

        139 To employer, if the advance payment is not paid on the due date 151

        140 To architect, if valuation not carried out in accordance with the priced activity schedule 152

        141 To architect, if contractor not asked to be present at measurement 153

        142 To architect, requesting payment for off-site materials 154

        143 To employer, giving 7 days notice of suspension 155

        144 To employer, if payment in full has not been made within 7 days despite notice of suspension 156

        145 To employer, requesting interest on late payment 157

        146 To employer, requesting retention money to be placed in a separate bank account 158

        147 To employer, if failure to place retention in separate bank account 159

        148 To architect, enclosing all information for preparation of final certificate 160

        149 To architect, enclosing final account 161

        150 To employer, disputing the final account 162

        151 To architect, if final certificate not issued on the due date (a) 163

        152 To architect, if final certificate not issued on the due date (b) 164

        153 To architect, if final certificate not issued on the due date (c) 165

        6 Extensions of Time 166
        Letters

        154 To architect, if delay occurs, but no grounds for extension of time 167

        155 To architect, when cause of delay ended if no grounds for extension of time 168

        156 To architect, if delay occurs giving grounds for extension of time (a) 169

        157 To architect, if delay occurs giving grounds for extension of time (b) 170

        158 To architect, providing further particulars for extension of time (a) 171

        159 To architect, providing further particulars for extension of time (b) 172

        160 To architect, if requesting further information in order to grant extension of time 173

        161 To architect, if unreasonably requesting further information in order to grant an extension of time 174

        162 To architect, if extension of time is insufficient 175

        163 To architect, who is not willing to reconsider an insufficient extension of time 176

        164 To architect, if extension of time not properly attributed 177

        165 To architect, if extension of time not granted within time stipulated 178

        166 To architect, if slow in granting extension of time 179

        167 To architect, if review of extensions not carried out (a) 180

        168 To architect, if review of extensions not carried out (b) 181

        169 To architect, if no final decision on extensions of time (c) 182

        170 To architect, who alleges that contractor is not using best endeavours 183

        171 To architect, if non-completion certificate or notice wrongly issued 184

        172 To employer, if liquidated damages wrongfully deducted 185

        173 To employer, if damages repaid without interest 186

        7 Loss and/or Expense 187
        Letters

        174 To architect, applying for payment of loss and/or expense (a) 188

        175 To architect, applying for payment of loss and/or expense under the supplemental provisions (b) 189

        176 To architect, applying for payment of loss and/or expense (c) 190

        177 To architect, applying for payment of expense (d) 191

        178 To architect, giving further details of loss and/or expense (a) 192

        179 To architect or quantity surveyor, enclosing details of loss and/or expense (b) 193

        180 To quantity surveyor, providing information for calculation of expense (c) 194

        181 To architect, if ascertainment delayed (a) 195

        182 To architect, if ascertainment delayed (b) 196

        183 To architect, if ascertainment too small 197

        184 To employer, regarding a common law claim 198

        185 To employer, regarding a common law claim 199

        8 Termination, Arbitration, Adjudication and Completion 200
        Letters

        186 To employer or architect, if default notice served 201

        187 To employer or architect, if default notice served justly 203

        188 To employer, if premature termination notice issued 204

        189 To employer who terminates after notification of cessation of terrorism cover 205

        190 To employer, giving notice of default before termination 206

        191 To employer, terminating employment after default notice 207

        192 To employer, terminating employment on the employer’s insolvency 208

        193 To employer, where either party may terminate 209

        194 To employer, terminating if suspension has not ceased after notice 210

        195 To employer, terminating employment after damage by insured risk 211

        196 To employer, giving notice of intention to refer a dispute to adjudication 212

        197 To nominating body, requesting nomination of an adjudicator 213

        198 To adjudicator, enclosing the referral 214

        199 To employer, if the adjudicator’s decision is in your favour 215

        200 To employer, requesting concurrence in the appointment of an arbitrator 216

        201 To appointing body, if there is no concurrence in the appointment of an arbitrator 217

        202 To architect, if practical completion of the Works or a section imminent 218

        203 To architect, if completion certificate wrongly withheld (a) 219

        204 To architect, if completion statement wrongly withheld (b) 220

        205 To employer, consenting to early use 221

        206 To employer, consenting to partial possession (a) 222

        207 To employer, consenting to partial possession (b) 223

        208 To employer, issuing written statement of partial possession 224

        209 To employer, refusing consent to partial possession 225

        210 To architect, after receipt of schedule of defects 226

        211 To architect, when making good of defects completed 227

        212 To architect, returning drawings, etc. after final payment if requested 228

        9 Sub-Contractors 229
        Letters

        213 To employer, requesting consent to assignment 230

        214 To employer, if asked to consent to assignment 231

        215 To sub-contractor, assessing competence under the CDM Regulations 232

        216 To a designer, assessing competence under the CDM Regulations 233

        217 To architect, requesting consent to sub-letting 234

        218 To employer, requesting consent to addition of persons to clause 3.8 list 235

        219 To employer, giving consent to addition of person to clause 3.8 list 236

        220 To sub-contractor: letter of intent 237

        221 To sub-contractor, regarding part of the construction phase plan 238

        222 To sub-contractor, enclosing part of the construction phase plan 239

        223 To domestic sub-contractor, requiring a warranty if not noted in the invitation to tender 240

        224 To domestic sub-contractor, requiring a warranty if not noted in the contract documents 241

        225 To architect, if domestic sub-contractor refuses to provide a warranty which was not originally requested 242

        226 To architect, objecting to a named person (a) 243

        227 To architect, objecting to a nominated sub-contractor (b) 244

        228 To architect, if contractor unable to enter into a sub-contract with named person (a) 245

        229 To architect, if unable to enter into sub-contract with named person in accordance with particulars (b) 246

        230 To architect, if some listed sub-contractors will not tender 247

        231 To architect, if contractor enters into a sub-contract with named person 248

        232 To architect, if contractor enters into contract with named person 249

        233 To sub-contractor, regarding insurance 250

        234 To sub-contractor that fails to maintain insurance cover 251

        235 To sub-contractor, enclosing drawings 252

        236 To sub-contractor, if asked to consent to assignment 253

        237 To sub-contractor that sub-lets without consent 254

        238 To sub-contractor, giving consent to sub-letting 255

        239 To sub-contractor, if no person-in-charge 256

        240 To sub-contractor, requiring compliance with direction 257

        241 To sub-contractor that fails to comply with direction 258

        242 To sub-contractor, if contractor dissents from alleged oral direction 259

        243 To sub-contractor that wrongly confirms an oral direction 260

        244 To sub-contractor that confirms an oral direction which was given 261

        245 To sub-contractor, if non-compliant work allowed to remain 262

        246 To sub-contractor, if defective work opened up 263

        247 To sub-contractor, inspection after failure of work 264

        248 To sub-contractor, after failure of work 265

        249 To sub-contractor, accepting Schedule 2 quotation 266

        250 To sub-contractor, rejecting Schedule 2 quotation 267

        251 To sub-contractor, if necessary to measure work 268

        252 To sub-contractor, fixing a new period for completion 269

        253 To sub-contractor, fixing a new period for completion after practical completion of the sub-contract works 270

        254 To sub-contractor, if no extension of time due 271

        255 To sub-contractor, if claim for extension of time is not valid 272

        256 To sub-contractor, if sub-contract works not complete by due date (a) 273

        257 To sub-contractor, if sub-contract works not complete within the period for completion (b) 274

        258 To sub-contractor, requesting further information in support of a financial claim 275

        259 To sub-contractor, applying for payment of loss and/or expense (a) 276

        260 To sub-contractor, applying for payment of loss and/or expense (b) 277

        261 To sub-contractor, giving notice of an interim payment 278

        262 To sub-contractor, enclosing payment 279

        263 To sub-contractor, giving withholding notice 280

        264 To adjudicator, enclosing written statement 281

        265 To sub-contractor if adjudicator appointed, but there is no dispute 282

        266 To adjudicator, if there is no dispute 283

        267 To sub-contractor, if sub-contractor has wrongly sent 7 day notice of intention to suspend performance of obligations 284

        268 To sub-contractor, if sub-contractor has correctly sent 7 day notice of intention to suspend performance of obligations 286

        269 To sub-contractor, requesting documents for calculation of the final sub-contract sum 287

        270 To sub-contractor that has failed to submit documents for the calculation of the final sub-contract sum (a) 288

        271 To sub-contractor that has failed to submit documents for the calculation of the final sub-contract sum (b) 289

        272 To sub-contractor, enclosing final payment 290

        273 To employer, giving notice of the named sub-contractor’s default 291

        274 To sub-contractor, giving notice of default before termination 292

        275 To sub-contractor, giving notice before determination 293

        276 To architect, if termination of named person’s employment possible 294

        277 To sub-contractor, terminating employment after default notice (a) 295

        278 To sub-contractor, determining the sub-contract after notice (b) 296

        279 To sub-contractor, determining the sub-contract without prior notice 297

        280 To sub-contractor, terminating employment after termination of the main contract 298

        281 To sub-contractor, termination on insolvency 299

        282 To sub-contractor, if cessation of terrorism cover notified 300

        283 To sub-contractor, notifying the employer’s election after cessation of terrorism cover notified 301

        284 To sub-contractor that serves a default notice (a) 302

        285 To sub-contractor that serves a default notice before determination (b) 303

        286 To sub-contractor that serves notice of termination (a) 304

        287 To sub-contractor that serves notice of determination (b) 306

        288 To architect, if employment of named person terminated 308

        289 To architect, if employment of named person terminated under ICSub/NAM/C clause 7.4, 7.5 or 7.6 309

        290 To architect, if contractor instructed to carry out named person’s work after termination of named person’s employment 311

        291 To architect, if contractor decides to sub-let after termination of named person’s employment 312

        292 To employer, if money recovered after termination of named person’s employment 313

        293 To sub-contractor, requesting details for the health and safety file 314

        294 To sub-contractor, if contractor dissents from date of practical completion 315

        295 To sub-contractor, notifying practical completion after earlier dissent 316

        296 To sub-contractor, enclosing schedule of defects 317

        297 To sub-contractor, directing that some defects are not to be made good 318

        298 To sub-contractor, if deduction made under main contract for inaccurate setting out 319

        299 To architect, if action threatened because of named person’s design failure 320

        300 To sub-contract architect, engineer or other consultant, regarding professional indemnity insurance 321

        301 To sub-contract architect, engineer or other consultant, if late in providing information 322

        302 To sub-contract architect, engineer or other consultant, if action threatened because of design failure 323

        303 To sub-contract architect, engineer or other consultant, at the end of a successful project 324

        Index 325

      Recently viewed products

      © 2026 Book Curl

        • American Express
        • Apple Pay
        • Diners Club
        • Discover
        • Google Pay
        • Maestro
        • Mastercard
        • PayPal
        • Shop Pay
        • Union Pay
        • Visa

        Login

        Forgot your password?

        Don't have an account yet?
        Create account